APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | 1x800MW Pit Head Ultra Supercritical Thermal Power Plant, by MAHAGENCO. | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/MH/THE/73481/2018 | Project Cost | 601900000 lacs | |
| 2. | |
S. No. in the schedule | 1(d) Thermal Power Plants
| Project Sector | Thermal Projects | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 1x800MW Pit Head Ultra Supercritical Thermal Power Plant ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 00 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Village : Heoti, Tehsil : Umred, District : Nagpur, State : Maharashtra | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | The proposed site is mined area which was back filled over a period 30 years. | Town / Village | Heoti, tehsil-Umred, district - Nagpur | State of the project | Maharashtra | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Maharashtra | Nagpur | Umred | | 10. | |
Nearest railway station along with distance in kms | Umred, 6 km | Nearest airport along with distance in kms | Nagpur, 33 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Umred , 5 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Gram panchayat: Heoti | | 13. | Name of the Applicant | Nitin | | 14. | Registered Address | PRAKASHGAD,PLOT NO G-9,SECOND FLOOR,BANDRA(EAST),MUMBAI-400051 | | 15. | |
Address for correspondance: | Name of the Company | Maharashtra State Power Generation Company Limited CIN-U40100MH2005SGC153648 | Name of the Applicant | Nitin | Designation (Owner/ Partner/ CEO) | CGM | Pin code | 400051 | E-mail | cgmenvsafe@mahagenco.in | Telephone No. | 22-26582424 | Fax No. | 22-26477273 | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | The proposed project site is mined area which was back filled over a period 30 years. This site will be developed for installation of Ultra Supercritical Thermal Power Plant. | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | Presently the site is barren Land having natural vegetation. | 1.3 | Creation of new land uses? | Yes | Present land will be converted in industrial use. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Geotechnical Investigation for proposed 1x 800MW Ultra Supercritical Pit Head Thermal Power Plant has been carried out. | 1.5 | Construction works? | Yes | Construction of Office building, Ash pond, Boiler, Turbine House, Water reservoir, DM Plant, Conveyor system for coal transfer. Cooling Tower, Power Transmission Greed, Silos for ash collection etc. are proposed. | 1.6 | Demolition works? | No | Not Applicable | 1.7 | Temporary sites used for construction works or housing of construction workers? | Yes | Temporary shed with sanitation facility will be developed for workers. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | Boiler, Turbine House, Conveyor system. Power Transmission Greed , Silos for Fly Ash etc. | 1.9 | Underground works including mining or tunnelling? | No | Not applicable. | 1.10 | Reclamation works? | No | Not applicable. | 1.11 | Dredging? | No | Not applicable. | 1.12 | Offshore structures? | No | Not applicable. | 1.13 | Production and manufacturing processes? | Yes | 1x 800 MW Ultra Supercritical Pit Head Thermal Power Plant | 1.14 | Facilities for storage of goods or materials? | Yes | The coal stock yard storage area, Raw water reservoir, Ash Pond and silos for fly ash will be provided in the project site. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Effluent- Oily Waste
Method of Treatment -Tilted Plate interceptor,
oil skimmer to bring down the treated water
Effluent-Chemical contaminated waste
Treatment- Neutralisation in a neutralising pit to bring the pH to acceptable levels.
Effluent-Sewage
Treatment-Sewage treatment Plant where that sewage is large and localised anaerobic treatment
where generation of sewage is limited.
Effluent-Industrial waste with high suspended solid levels
Treatment:Treatment through Tilted Plate Interc | 1.16 | Facilities for long term housing of operational workers? | Yes | Will be located adjacent to WCL Township Area. | 1.17 | New road, rail or sea traffic during construction or operation? | Yes | Road traffic will be increased during operation of plant. Existing road network is sufficient to handle the traffic. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | Yes | Construction of conveyor system from Umred and 3 others mine to 1x800MW Ultra Super Critical Pit Head Thermal power plant. Total length of conveyor will be 4Km. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Not Applicable, as no existing public transport route will be diverted or affected due to proposed power plant. | 1.20 | New or diverted transmission lines or pipelines? | Yes | New 20 Km Power transmission line will be laid down for electrical power distribution from power generation plant to evacuation point. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not Applicable. Ground water level may be increased due to construction of raw water reservoir for power generation project. | 1.22 | Stream crossings? | Yes | Amb river is passing through project site. it will not be crossed or diverted. | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | The required plant water for the proposed plant will be the treated waste water from Nagpur city which is at distance of 45 km. As an alternate, the water from the Goshikhurd dam at a distance of nearly 56 km is also considered. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | Yes | Detail hydrology and hydrogeological study will be carried out. | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | Local laborers will be employed in construction phase. The construction material from local suppliers. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not Applicable | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not Applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | Local worker during construction and operation phase. About 900 no. of people will get direct and contractual employment during operation phase.
About 1000 people will be engaged during construction phase. | 1.29 | Introduction of alien species? | No | Not Applicable | 1.30 | Loss of native species or genetic diversity? | No | Not Applicable | 1.31 | Any other actions? | No | Not Applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | The proposed project site is mined area which was back filled over a period 30 years. This site will be developed for industrial use. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | 17.87 Million Cubic meter Per Annum (54151.51KLD)
Source: Treated Waste Water from Nagpur Municipal Corporation or from Gosekhurd dam as an alternative source. | 2.3 | Minerals (MT) | Yes | Coal 3.68 Million Tons Per Annum (11847 TPD)
Source: Form Dinesh, Unrer,MKD-1 and Gokul area of WCL coal Mine. In worst case when GCV of coal is 3000 Kcal/kg the requirement will be 4.17 MTPA. | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Stone, sand, Steel, Cement etc. will be required. Quantity will be finalized after detailed drawing. | 2.5 | Forests and timber (source – MT) | No | Not Applicable | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | During construction phase DG set will be used for emergency work during power failure. A power for construction work will be source from MSEDCL. During operation phase electrical energy from power generation plant will be used for auxiliary consumption. | 2.7 | Any other natural resources (use appropriate standard units) | No | Nil | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | LDO, FO, Chemical used in DM Plant
Oxygen Cylinder, Chorine etc. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Not envisaged. | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | The proposed project will provide additional employment opportunity and infrastructure development in the nearby areas. It will improve the living condition of the people in nearby areas. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Not Applicable | 3.5 | Any other causes | No | Not Applicable | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | Yes | Ash: 6042 TPD
Fly ash will be sold to cement plant and bottom ash will be disposed in ash pond. | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | STP will be provided. The treated water will be used for horticulture. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Transformer Oil, Machined used oil a Sludge during LDO & FO Tank cleaning. It will be handover to MPCB registered vendors for disposal. | 4.4 | Other industrial process wastes | No | Not Applicable | 4.5 | Surplus product | No | Not Applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Sewage sludge from STP will be used as manure for plantation. | 4.7 | Construction or demolition wastes | Yes | Will be used for making working area, fencing etc. | 4.8 | Redundant machinery or equipment | No | Not applicable. | 4.9 | Contaminated soils or other materials | No | Not Applicable | 4.10 | Agricultural wastes | No | Not Applicable | 4.11 | Other solid wastes | No | Not Applicable | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Emission of Particulate Matter, SO2, NOx. ESP and Chimney with appropriate height will be provided as per Standards.
FGD will be installed to control SO2. Proper Bag filter and other appropriate equipment’s will be installed at Coal crusher to control emission. Dust suppression will be controlled by installing mist type foggers at CHP, AHP, Rain Gun at Coal stack area, Ash Bund, internal roads to control fugitive emission. | 5.2 | Emissions from production processes | Yes | Emission of Particulate Matter, SO2, NOx.
ESP and Chimney with appropriate height will be provided as per standard.
FGD will be installed to control SO2. | 5.3 | Emissions from materials handling including storage or transport | Yes | Fugitive emission is envisaged due to handling of coal and ash. Water Sprinkler will be provided to control the emission. | 5.4 | Emissions from construction activities including plant and equipment | Yes | During Construction phase due to transportation of heavy vehicles, operation of equipments and construction machineries. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Solid waste & Liquid waste are envisaged during construction period | 5.6 | Emissions from incineration of waste | No | Not Applicable | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not Applicable | 5.8 | Emissions from any other sources | No | Not Applicable | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Noise will be generated from turbine Water pump house, Crusher, Blower and motors. All noise producing equipment will be maintained as per standard CPCB norms. Noise will be exist the prescribed CPCB standards. | 6.2 | From industrial or similar processes | Yes | The noise level generated will be in the range of 70-90 dB (A) at1 m from source. | 6.3 | From construction or demolition | Yes | Due to operation of heavy machineries during construction. | 6.4 | From blasting or piling | No | Not Applicable | 6.5 | From construction or operational traffic | Yes | Due to movement of heavy vehicles. | 6.6 | From lighting or cooling systems | Yes | Heat from Boiler house and pipes carrying steam, Steam water condenser. All equipment will be properly insulated. | 6.7 | From any other sources | No | Not Applicable | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | Due to storage of FO, Diesel etc. Proper care will be taken as per standard process. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | STP will be provided for domestic waste.
ETP will be provided for treatment of effluent from power plant. | 7.3 | By deposition of pollutants emitted to air into the land or into water | Yes | ESP and FGD proposed to minimize the concentration of source emission. | 7.4 | From any other sources | No | Not Applicable | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Not Applicable | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | Fire in coal storage area, FO and LDO Storage tank.
Well design fire hydrant system and firefighting equipment will be provided at required areas. | 8.2 | From any other causes | Yes | Electrification from Transformer Yard, or from Power transmission line.
The entry in this area will be prohibited and monitored by Safety and Operation officer. Permit system will be followed for this area. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | Yes | On-Site DMP will be prepared. Proper precaution will be taken to handle such situation. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | • This project will provide additional infrastructure to nearby area.
• Demand for rented house will be increased.
• Possibilities of ancillary industries will be increased.
• Possibilities of ancillary industries will be increased.
• This project will generate direct and indirect employment for nearby villages. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not anticipated. | 9.3 | Set a precedent for later developments | Yes | Ancillary industries might be developed as a consequence | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | Not Anticipated | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | Not Applicable | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Muniya Reserved Forest : 6.0 km (SW)
Bhivapur Reserved Forest : 7.0 km (NW)
Chichla Reserve Forest : 10 Km (S)
Ranbori Reserve Forest (Karhandla Wildlife sanctuary) : 10.30 Km (E) | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | Not Applicable. | 4 | Inland, coastal, marine or underground waters | No | Not Applicable. | 5 | State, National boundaries | No | Not Applicable. | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | Not Applicable. | 7 | Defence installations | No | Not Applicable. | 8 | Densely populated or built-up area | Yes | Umred 5 Km SE | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Hospital, schools, colleges and place of worship are situated at a distance of 5 km. | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | Amb River: Through project site
Pandharboli Talav: 5.0 km (S)
Umred Lake : 4.5 Km (ESE)
Makardhokra Reservoir: 5.5 Km (W)
Paradgaon Lake: 7.0 Km : (NW)
Ukkarwahi Talav: 8.0 km (NW)
Undri Nadi: 7.5 km (NE)
Khapri Talav: 12.0 Km (NW)
Kalandri Talav: 11.0 Km (N)
Kolarmet Talav: 12.0 Km (N)
SonegaonTalav: 12.5 Km (N)
Botejhari Talav : 14.0 km (SSE)
Mangli Talav : 15.0 Km (NW) | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | Not Applicable | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | Zone III (Moderate) | | (IV) | Proposed Terms of Reference for EIA studies | | Additional Attachments, if any |
---|
Attached File |
---|
ADS Letter |
| | Essential Detail Sought : NIL | | Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Raise Letter | Sub-Committee will make conduct site visit. Accordingly project is deferred | 08 May 2018 | | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Nitin | Designation | CGM | Name of Company (Applicant Name should not be given here) | Maharashtra State Power Generation Company Limited CIN-U40100MH2005SGC153648 | Address | PRAKASHGAD,PLOT NO G-9,SECOND FLOOR,BANDRA(EAST),MUMBAI-400051 |
|
|