APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Proposed establishment of Synthetic Organic Chemicals Manufacturing Facility By Aarav Fragrances & Flavors Pvt. Ltd. at Gut No./ Survey No.: 150, 151, 166 to 172 of village Lakhmapur and Gut No./ Survey No. 239A, 242, 286 (Part), 287 (Part), 289 (Part), 290(2), 291 (Part), 292 to 296 of village Jamghar, Taluka Wada, District Palghar
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/MH/IND2/94966/2019
Project Cost 2000 lacs
2.
S. No. in the schedule5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Project Sector Industrial Projects - 2
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled Plot area: 97,750 sq. m ha.
4.
New/Expansion/ModernizationNew
5. Existing Capacity/Area etc. 70 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectGut No./ Survey No.: 150, 151, 166 to 172 of village Lakhmapur and Gut No./ Survey No. 239A, 242, 286 (Part), 287 (Part), 289 (Part), 290(2), 291 (Part), 292 to 296 of village Jamghar, Taluka Wada, District Palghar
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.Gut No./ Survey No.: 150, 151, 166 to 172 of village Lakhmapur and Gut No./ Survey No. 239A, 242, 286 (Part), 287 (Part), 289 (Part), 290(2), 291 (Part), 292 to 296
Town / VillageJamghar & lakhmapur
State of the projectMaharashtra
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)MaharashtraPalgharVada
10.
Nearest railway station along with distance in kms Atgaon, 25 km
Nearest airport along with distance in kms Mumbai International Airport, 61 km
11. Nearest Town/City/District Headquarters along with distance in kms Wada , 7.4 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Jamghar & lakhmapur
13. Name of the Applicant Shailesh
14. Registered Address Gut No. 167, 169, 170, 171, 296, Village Jamghar -Lakhamapur, Tal. Wada, District: Thane- Maharashtra.
15.
Address for correspondance:
Name of the Company AARAV FRAGRANCES & FLAVOURS PVT. LTD.
Name of the Applicant Shailesh
Designation (Owner/ Partner/ CEO) Senior Manager Chemicals
Pin code 400604
E-mail shailesh.deshmukh@aarav.co
Telephone No. 022-41130206
Fax No. 022-25827419
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . NIL
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?Yes
StatusWildlife Clearance Under Process
MoEF file numberFP/MH/IND/1665/2017
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No The proposed establishment project site is located within existing facility, which is designed for industrial purpose only. There would be no change in Land Use, Land Cover or Topography of plot.
1.2 Clearance of existing land, vegetation and buildings? No No vegetation in the area of proposed activity. Green belt area will be developed within plot.
1.3 Creation of new land uses? No Proposed project will be established within site.
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Will be done as required.
1.5 Construction works? Yes Proposed project will be established within the plot.
1.6 Demolition works? No Not applicable.
1.7 Temporary sites used for construction works or housing of construction workers? No Not applicable.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Plot plan layout is given in pre- feasibility report.
1.9 Underground works including mining or tunnelling? No Not applicable.
1.10 Reclamation works? No Not applicable.
1.11 Dredging? No Not applicable.
1.12 Offshore structures? No Not applicable.
1.13 Production and manufacturing processes? Yes Please refer pre-feasibility report.
1.14 Facilities for storage of goods or materials? Yes Storage facility for products and raw materials shall be provided within the existing premises. All chemicals/raw materials/products will be stored in drums/tanks and warehouse with adequate safety measures.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Hazardous waste will be disposed of as per hazardous waste rule, 2016. Treated effluent will be recycle back. Unit will maintain Zero Liquid Discharge facility.
1.16 Facilities for long term housing of operational workers? No No on-site housing of operational workers is envisaged.
1.17 New road, rail or sea traffic during construction or operation? No Not applicable.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Site is well connected by road and railway.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Not applicable.
1.20 New or diverted transmission lines or pipelines? No Not applicable.
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No Not applicable.
1.22 Stream crossings? No Not applicable.
1.23 Abstraction or transfers of water from ground or surface waters? Yes Water will be sourced from existing Bore well & dug well. NOC from CGWA received for Ground water withdrawal (ref Letter No. 21-4(211)/ CR/CGWA/ 2015-2297 dated 11th December 2018)
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No Treated effluent shall be recycle. Unit will maintain Zero Liquid discharge facility.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Local laborers would be employed during construction phase.
1.26 Long-term dismantling or decommissioning or restoration works? No Not applicable.
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No Not applicable.
1.28 Influx of people to an area in either temporarily or permanently? No Not applicable.
1.29 Introduction of alien species? No Not applicable.
1.30 Loss of native species or genetic diversity? No Not applicable.
1.31 Any other actions? No Not applicable.
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No Not applicable. Proposed project will be established within existing manufacturing facility.
2.2 Water (expected source & competing users) unit: KLD Yes Source: Ground water withdrawal Total fresh water requirement: 115.5 cmd
2.3 Minerals (MT) No Not applicable.
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Construction material will be sourced from local area.
2.5 Forests and timber (source – MT) No Not applicable.
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Electricity requirement: 500 KVA, DG sets: 500 KVA & 160 KVA each, Fuel: Bio-briquettes: 27 TPD OR Agricultural Waste: 27 TPD OR Furnace oil: 12.5 TPD
2.7 Any other natural resources (use appropriate standard units) No Not applicable.
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes Chemicals will be stored/ handled according to respective MSDS.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Not applicable.
3.3 Affect the welfare of people e.g. by changing living conditions? Yes Due to project, employment to the local resident will be provided which can result in upgrading the living standard of people. Positive impact on the social and economic status of local people due to direct and indirect employment opportunities.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Not applicable.
3.5 Any other causes No Not applicable.
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No Not applicable.
4.2 Municipal waste (domestic and or commercial wastes) Yes Municipal Waste will be disposed as per norms.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Hazardous waste will be handled and disposed as per HW Rules, 2016.
4.4 Other industrial process wastes No Not applicable.
4.5 Surplus product No Not applicable.
4.6 Sewage sludge or other sludge from effluent treatment Yes Sludge from ETP shall be handled as per HW rules 2016
4.7 Construction or demolition wastes Yes Construction waste will be disposed off as per norm
4.8 Redundant machinery or equipment No Not applicable.
4.9 Contaminated soils or other materials No Not applicable.
4.10 Agricultural wastes No Not applicable.
4.11 Other solid wastes No Not applicable.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes SO2, NOx, and PM Emission are envisaged from fuel burning sources. Scrubber will be provided to scrub emissions with adequate stack height.
5.2 Emissions from production processes Yes Emission from Process will be scrubbed by installing scrubber and maintained within the stipulated limits by CPCB/ MPCB.
5.3 Emissions from materials handling including storage or transport Yes Liquid will be stored & handled in closed operation method. Negligible amount of emissions would be generated during storage/ transport of material. The same will be taken care off through ID fans / scrubbers proposed to be installed at site.
5.4 Emissions from construction activities including plant and equipment Yes Particulate matter is expected from construction activities.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No Not applicable.
5.6 Emissions from incineration of waste No Not applicable.
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Not applicable.
5.8 Emissions from any other sources No Not applicable.
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Noise generating equipment’s will be provided with acoustic enclosures to ensure compliance with CPCB/ MPCB standards.
6.2 From industrial or similar processes Yes Noise generating equipment’s will be provided with acoustic enclosures to ensure compliance with CPCB/ MPCB standards.
6.3 From construction or demolition Yes During the construction work noise would be generated which will be temporary in nature. Workers getting exposed would be provided with PPE.
6.4 From blasting or piling No Not applicable.
6.5 From construction or operational traffic No Noise from traffic will not have much impact on the work environment of the project site.
6.6 From lighting or cooling systems No Not applicable.
6.7 From any other sources No Not applicable.
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No Closed handling practices, dyke wall will be provided to avoid spillage / leakage of Hazardous Chemicals. Routine monitoring of chemical storage area will be done to check leakages to avoid contamination with water, air, soil etc. Storage of chemicals in tank farms and warehouse with adequate safety features, and proper dyke enclosures will be provided as per industrial norms.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No There will be no discharge of sewage or other effluents on land.
7.3 By deposition of pollutants emitted to air into the land or into water No Air Pollution Control equipment will be provided at source to prevent emissions in air.
7.4 From any other sources No Not applicable.
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Not applicable.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No Proper safety measures will be taken to avoid any accident in the plant and fuel Storage Yard or Chemical Storage Yard or any other area in plant. Fire-Fighting Training will be provided to workers. An ‘On-site Emergency Plan’ will be prepared and will be implemented for any emergency situation. Fire protection measures will be carried as per statutory requirements.
8.2 From any other causes No Not applicable.
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No The project will be designed by taking into consideration these factors as per relevant codes and standards. DMP will be prepared and executed in case of any such eventualities.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
No Not applicable.
9.2 Lead to after-use of the site, which could have an impact on the environment No Not applicable.
9.3 Set a precedent for later developments No Not applicable.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No Not applicable.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes Project is located at 5.8 km from Tansa WLS Protected area boundary & 1.46 km from boundary of proposed Eco sensitive zone for Tansa WLS as per draft ESZ Notification No. SO 2566 (E) on 10th August 2017
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Vaitarna river- 3 km to North, Manichi river- 5.9 km to North west, Mokhai river- 3 km to South, Dhandela river- 2 km to North
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No Not applicable.
4 Inland, coastal, marine or underground waters Yes Vaitarna river- 3 km to North, Manichi river- 5.9 km to North west, Mokhai river- 3 km to South, Dhandela river- 2 km to North
5 State, National boundaries Yes Not applicable.
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes Bhiwandi Wada road
7 Defence installations No Not applicable.
8 Densely populated or built-up area Yes Wada about 7.4 km
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Wada about 7.4 km, Carved stones, Wada- 7.16 km to North East, Parshuram Temple, Gunj- 7.96 km to South West
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No Not applicable.
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No Not applicable.
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No Not applicable.
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantShailesh
DesignationSenior Manager Chemicals
Name of Company (Applicant Name should not be given here)AARAV FRAGRANCES & FLAVOURS PVT. LTD.
AddressGut No. 167, 169, 170, 171, 296, Village Jamghar -Lakhamapur, Tal. Wada, District: Thane- Maharashtra.