APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | M/s. Quantinental Pharmachem Private Limited | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/MH/IND2/84252/2018 | Project Cost | 404.96 lacs | |
| 2. | |
S. No. in the schedule | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Project Sector | Industrial Projects - 2 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | Plot Area- 2499 sq.mt. ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 0 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | Yes | c) | Notified Eco-sensitive areas | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | MIDC Paithan | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | A-106/1 | Town / Village | Mudhalwadi | State of the project | Maharashtra | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Maharashtra | Aurangabad | Paithan | (2.) | Maharashtra | Aurangabad | Paithan | | 10. | |
Nearest railway station along with distance in kms | Aurangabad Railway Station, 37.06 km | Nearest airport along with distance in kms | Aurangabad Airport, 36.70 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Paithan , 6.00 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Village Panchayat:-Mudhalwadi, Tal. Paithan, Dist. Aurangabad., (MS) Zillla Parishad:- Amba Apsara Rd, Near Devgiri Bank, Nageshwarwadi, Aurangabad, Maharashtra Aurangabad (MS) MIDC Paithan:- Tal. Paithan, Dist. Aurangabad (MS) | | 13. | Name of the Applicant | Mahesh | | 14. | Registered Address | A-106/1, MIDC Paithan Industrial Area, Village- Mudhalwadi, Tal. Paithan, Dist. Aurangabad, Maharashtra. | | 15. | |
Address for correspondance: | Name of the Company | QUANTINENTAL PHARMACHEM PVT LTD | Name of the Applicant | Mahesh | Designation (Owner/ Partner/ CEO) | Director | Pin code | 431148 | E-mail | quantinentalpharmachem@gmail.com | Telephone No. | 0-0 | Fax No. | 0-0 | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | The site is already in an existing Notified Industrial Area [MIDC] Maharashtra Industrial Development Corporation. Hence there will be no change in land use. | 1.2 | Clearance of existing land, vegetation and buildings? | No | There is no need of clearance of existing land | 1.3 | Creation of new land uses? | No | The said land is reserved for industrial projects by Govt. of Maharashtra. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | No | Geotechnical investigation report will be done | 1.5 | Construction works? | Yes | Construction works will be done systematically, with economy of materials and with environmental care. | 1.6 | Demolition works? | No | No demolition works are required | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | No housing for workers proposed, workers will come from nearby area. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | There will be above ground construction of structures for the said proposal including excavation, cut & fill etc | 1.9 | Underground works including mining or tunnelling? | No | No underground works including mining or tunneling is required. | 1.10 | Reclamation works? | No | No reclamation work is required. | 1.11 | Dredging? | No | No dredging is involved | 1.12 | Offshore structures? | No | Not Applicable | 1.13 | Production and manufacturing processes? | Yes | Detail list of products and Manufacturing process is described in Pre-feasibility Report | 1.14 | Facilities for storage of goods or materials? | Yes | Adequate storage facilities for raw material and finished product will be provided within the proposed project site. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Low polluting stream effluent will be treated in ETP (involving Primary Treatment, 2 stages Secondary Treatment and Tertiary Treatment). Treated effluent will be used for green belt development.
? High polluting stream effluent will be treated in a system comprising of Solvent stripper, MEE.
Hazardous waste and Non- Hazardous waste details are mentioned in Pre-feasibility Report. | 1.16 | Facilities for long term housing of operational workers? | No | The operational workers will be employed from nearby area. | 1.17 | New road, rail or sea traffic during construction or operation? | No | Proposed project is located in Notified Industrial Area [MIDC] Maharashtra Industrial Development Corporation, infrastructure facility is already available | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Proposed project is located in Notified Industrial Area [MIDC] Maharashtra Industrial Development Corporation, infrastructure facility is already available. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | No closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements will be required. | 1.20 | New or diverted transmission lines or pipelines? | No | No New or diverted transmission lines or pipelines will be laid | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | There will be no impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers. | 1.22 | Stream crossings? | No | No stream crossing the site | 1.23 | Abstraction or transfers of water from ground or surface waters? | No | Not Applicable | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | There will be no change in the water bodies or the land surface affecting drainage or run-off | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | Raw materials for construction activity such as Cement, Sand, Steel, aggregate etc. shall be transported by road. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | No long-term dismantling or decommissioning or restoration works is envisaged from the proposed project | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not Applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | Temporary and permanent influx of people will be there as the managerial and supervisory staff will be recruited from different areas.
Total employees including skilled and nonskilled shall be 10 nos.. | 1.29 | Introduction of alien species? | No | Introduction of alien species is not envisaged | 1.30 | Loss of native species or genetic diversity? | No | No such case is reported from the area so far. | 1.31 | Any other actions? | No | Not Applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | The land is part of notified Industrial Estate of Govt. of Maharashtra. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Source- Surface water supplied by MIDC Proposed 42 CMD No competing user. No encroachment on other’s supply. | 2.3 | Minerals (MT) | No | Not Applicable | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Construction material as available locally such as sand, reinforcement steel, structural steel, cement, metal etc. will be used for construction purpose. The quantification of the materials will be done during detailed engineering stage. | 2.5 | Forests and timber (source – MT) | No | No forests and timber will be used during construction / operation of the project activity. | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Boiler 600 kg/hr ; Fuel Briquette
Total power requirement of the project will be 150 KW/Hr.
(Source: - MSEDCL)
Proposed transformer - 150 KVA
Proposed D. G. Sets - 80 KVA | 2.7 | Any other natural resources (use appropriate standard units) | No | Not Applicable | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | Not Applicable. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | No effect is envisaged | 3.3 | Affect the welfare of people e.g. by changing living conditions? | No | No harmful effects to human health or the environment are envisaged from the project. There will be positive impact in the area | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | No effect envisaged. | 3.5 | Any other causes | No | Not Applicable | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | Not Applicable | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Domestic wastewater will be send to soak pit and septic tank | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Details are mentioned in Pre-feasibility Report | 4.4 | Other industrial process wastes | No | No other industrial process waste will be generated. | 4.5 | Surplus product | No | There will be no surplus product | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | ETP sludge will be send to CHWTSDF | 4.7 | Construction or demolition wastes | Yes | Construction waste like soil, brick bats, etc. will be utilized in leveling of land and construction of roads | 4.8 | Redundant machinery or equipment | No | There will no redundant machinery or equipment | 4.9 | Contaminated soils or other materials | No | There will be no contamination of soil or any other material. | 4.10 | Agricultural wastes | No | There will not be any agricultural waste | 4.11 | Other solid wastes | No | There will not be any other solid waste | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | The air pollution is mainly from emissions of air pollutants from the boiler stacks and DG set. DG SET will be used as a stand-by source of electricity.
Cyclone dust collector is proposed to combat the emissions from the boilers before releasing into atmosphere through a stack. Very little emission from fugitive sources is also predicted. | 5.2 | Emissions from production processes | Yes | Following are the gas generated from the total pollution load sheet.
1. SO2- 36.18
2. HCL- 48.3
3. HBr- 66.36
4. CO2- 81.128
5. H2- 0.4
6. NH3- 0.226 | 5.3 | Emissions from materials handling including storage or transport | Yes | Fugitive emissions from solvent storages & handling. Transportation of materials also | 5.4 | Emissions from construction activities including plant and equipment | Yes | Fugitive dust emissions are likely to be generated from construction activities and vehicular movements. These emissions will be temporary and will be controlled by water spraying and regular sweeping of internal roads. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | No | All precautions to suppress dust such as water sprinkling. Odour from the handling of chemicals but it will be limited to the operational area. | 5.6 | Emissions from incineration of waste | No | There will be no waste incinerated on site | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | There will be no burning of waste in open air. | 5.8 | Emissions from any other sources | No | There will be no emissions from any other source. | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | No | Not Applicable | 6.2 | From industrial or similar processes | Yes | Noise shall be generated from operation of Equipment’s like Boiler DG Set, compressor etc. Acoustic enclosure shall be provided to DG set & Compressors. Boiler room shall be provided with Acoustic treatment. PPE’S will be mandatory in these work areas. | 6.3 | From construction or demolition | Yes | There will be Noise generated during construction activity. i.e. crane, crusher, from vehicles used for loading and unloading of material, JCB Machines. However, this will be temporary nature. Also, there will be no work during night. | 6.4 | From blasting or piling | No | Not Applicable | 6.5 | From construction or operational traffic | Yes | Noise during construction activities will be temporary & will be maintained within the prescribed noise standards. | 6.6 | From lighting or cooling systems | No | No noise will be generated from lighting or cooling systems | 6.7 | From any other sources | No | There are no other sources of noise generation | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | The hazardous materials will be stored in a proper storage facility designed with protective measures to avoid any risk of contamination to the land or to the human through leakage or spillages.
SOPs are prepared for chemical handling and transportation. Appropriate dyke wall will be provided for proposed storage tanks and closed feeding system is adopted for chemical reaction. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | The proposed project is based on the concept of “Zero Effluent Discharge” hence no sewage or other effluent will be discharged outside the plant premises. | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | The plant will be completely based on Zero Liquid Discharge thus; no risk of contamination because of release of pollutants into water is envisaged. The air emissions will be controlled by providing adequate pollution control equipment. However, continuous online measurement of stack emissions quality will be done to assure the level of emission within the prescribed limit | 7.4 | From any other sources | No | Not Applicable | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Likelihood of such an event is not foreseen till now and suitable measures will be adopted so that there will be no such risk in the coming future. | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | Risk is involved due to fire, spillages and explosion. Proper firefighting system will be provided in the plant. The HW generated during operation will be disposed off as per the Hazardous waste (Management Handling & Transboundary Movement) Rules 2008 | 8.2 | From any other causes | No | Not Applicable | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | Proposed site falls under Seismic Zone II | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | Infrastructure already available from MIDC. The demand for housing will go up due to recruitment of people | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | There will be no significant impact on environment | 9.3 | Set a precedent for later developments | No | The site is located in developed MIDC area | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | Proposed industry is located MIDC area, MIDC has also other industries, it may cause cumulative effect. | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | Not Present within 15 km Aerial distance from proposed project site. | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Water Bodies: Jaikwadi Dam is 1.8 Km away from the project site. | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | Yes | Jayakwadi Bird Sanctuary reserved for the migratory birds, is 1.8km towards South-West Direction [As per Gazette Notification S.O. 2202 (E) amended Dated 12th July 2017].
MIDC is already existed before declaration of Eco Sensitive Zone. | 4 | Inland, coastal, marine or underground waters | Yes | Inland water Bodies: Jaikwadi Dam at Paithan is 1.8 Km towards South East Direction | 5 | State, National boundaries | No | Not Applicable | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | Aurangabad- Paithan Road | 7 | Defence installations | No | There is no Defense installation within 15 km radius of the project site. | 8 | Densely populated or built-up area | Yes | Mudhalwadi-0.75 Km
Pimpalwadi- 1.23 Km | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | There are a few primary schools, dispensaries, small hospitals, places of worship, within 15 km from the project site. | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | Jaikwadi Dam located at Paithan which is 1.8 Km away from the project site. | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | There is no critically polluted area in 10 km radius of the project site. | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | The plant site falls in Seismic Zone - II as per IS: 1893 (Part-I): 2002. | | (IV) | Proposed Terms of Reference for EIA studies | | Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | The correction have been made as per the instruction received | 12 Nov 2018 | 2. | NA | It may be noted that the project proponent's name is not the project name. Further, as the project is not attracting general condition, it requires appraisal by SEAC/SEIAA | 09 Nov 2018 | 3. | NA | The correction have been made as per the instruction received | 06 Nov 2018 | 4. | NA | Please mention project name properly in Form 1, S.No.1.
As such the proposal requires appraisal at State level by the SEAC/SEIAA | 05 Nov 2018 | | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Mahesh | Designation | Director | Name of Company (Applicant Name should not be given here) | QUANTINENTAL PHARMACHEM PVT LTD | Address | A-106/1, MIDC Paithan Industrial Area, Village- Mudhalwadi, Tal. Paithan, Dist. Aurangabad, Maharashtra. |
|
|