APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s VITTHALRAO SHINDE SSK LTD 45 KLPD GRAIN BASED DISTILLERY
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/MH/IND2/82807/2018
Project Cost 6532.82 lacs
2.
S. No. in the schedule5(g) Distilleries
Project Sector Industrial Projects - 2
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled SOLAPUR ha.
4.
New/Expansion/ModernizationNew
5. Existing Capacity/Area etc. 6 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectGANGAMAINAGAR-PIMPALNER TQ MADAH DIST SOLAPUR 413210
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.417 418
Town / VillageGANGAMAINAGAR PIMPALNER TQ MADHA DIST SOLAPUR
State of the projectMaharashtra
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)MaharashtraSolapurMadha
10.
Nearest railway station along with distance in kms Kurduwadi, 19 km
Nearest airport along with distance in kms Solapur, 100 km
11. Nearest Town/City/District Headquarters along with distance in kms Solapur , 100 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Village Grampanchyat – Pimpalner Tal – Madha, Dist – Solapur. 413214. Ph-(02183) 233005
13. Name of the Applicant R
14. Registered Address Gangamai nagar, Pimpalner, Tal- Madha, Dist- Solapur
15.
Address for correspondance:
Name of the Company VITTHALRAO SHINDE SSK LTD
Name of the Applicant R
Designation (Owner/ Partner/ CEO) Managing Director
Pin code 413214
E-mail vs.sugar@gmail.com
Telephone No. 02183-233056
Fax No. 02183-233005
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No The land is already acquired and used for industrial purpose. Hence there is no change in land use.
1.2 Clearance of existing land, vegetation and buildings? No NA
1.3 Creation of new land uses? No NA
1.4 Pre-construction investigations e.g. bore houses, soil testing? No Soil Investigations already done. The soil is having good bearing capacity for foundations.
1.5 Construction works? Yes Total Plot Area:60724.8 m2 Total proposed built up area- 10120.8 m2
1.6 Demolition works? No NA
1.7 Temporary sites used for construction works or housing of construction workers? Yes Temporary housing shall be provided for construction workers for period of 12 months
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes The factory shed shall be above ground. The cutting and filling shall be nearly matched. Excess material shall be used to fill low lying areas
1.9 Underground works including mining or tunnelling? No NA
1.10 Reclamation works? No NA
1.11 Dredging? No NA
1.12 Offshore structures? No NA
1.13 Production and manufacturing processes? Yes List of products and Raw materials Attached as an Refer Annexure II Manufacturing Process is attached Refer Annexure III
1.14 Facilities for storage of goods or materials? Yes Godowns of large area for storage of goods & material stored in earmarked area at site. The Alcohol are stored in MS tanks
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Industrial Effluent : 131CMD Full Fledge ETP will be Provided Domestic Effluent : 04CMD Water Balance Annexure attached Refer Annexure IV Solid Waste Non Hazardous Waste: Boiler Ash- 05 T/M Sale to Brick Manufacturer Grain Residue-01 T/M Used as cattle feed. Hazardous Solid Waste: NA ETP Details (For Treatment & Disposal) Refer Annexure V
1.16 Facilities for long term housing of operational workers? Yes A housing colony is already established in the campus of sugar complex
1.17 New road, rail or sea traffic during construction or operation? No Existing road will be used
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No The proposed project site is in Pimpalner Grampanchayat and has well developed infrastructure facilities like Road
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No NA
1.20 New or diverted transmission lines or pipelines? No NA
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No NA
1.22 Stream crossings? No NA
1.23 Abstraction or transfers of water from ground or surface waters? Yes The total water requirement shall be 697 cum/day. VSSSKL will receive water from Ujjani Dam as well as open well, Bore well to constructed raw water reservoir.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No N.A.
1.25 Transport of personnel or materials for construction, operation or decommissioning? No N.A.
1.26 Long-term dismantling or decommissioning or restoration works? No N.A.
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No N.A.
1.28 Influx of people to an area in either temporarily or permanently? Yes During Construction Phase: Workers: 72 During Operation Phase : Skilled:15 Unskilled:35
1.29 Introduction of alien species? No N.A.
1.30 Loss of native species or genetic diversity? No N.A.
1.31 Any other actions? No N.A.
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes Agriculture Area:70 Acres NA copy is attached Refer Annexure VI
2.2 Water (expected source & competing users) unit: KLD Yes Main source of water supply is Ujjani Dam Reservoir, open well & bore well. Distillery-697KLD
2.3 Minerals (MT) No NA
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Industry will appoint approved Govt. Registered contractor for Execution.
2.5 Forests and timber (source – MT) Yes Source - Local Vendor
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Electricity required during Season: 1140 KWh During off Season –25 KWH Fuels - Bagasse:210 MT/Day Source – Own Power Generation
2.7 Any other natural resources (use appropriate standard units) No N.A
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No No use of hazardous Materials or substances.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No N.A
3.3 Affect the welfare of people e.g. by changing living conditions? No N.A
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No N.A
3.5 Any other causes No N.A
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No
4.2 Municipal waste (domestic and or commercial wastes) Yes Canteen waste
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) No NA
4.4 Other industrial process wastes Yes Boiler Ash, Grains Residue
4.5 Surplus product No
4.6 Sewage sludge or other sludge from effluent treatment No
4.7 Construction or demolition wastes Yes Excess Excavated material or construction waste during construction will be used for leveling of land at site
4.8 Redundant machinery or equipment No NA
4.9 Contaminated soils or other materials No NA
4.10 Agricultural wastes No NA
4.11 Other solid wastes No NA
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Emission from the combustion will be NOX , SOx and TPM
5.2 Emissions from production processes Yes The source of emission shall be proposed Boiler-1 No, 18 TPH& Stack Height-40 Mtr. PM shall be main pollutant from Boiler
5.3 Emissions from materials handling including storage or transport Yes Dust in the form of PM shall be generated during construction activities. Suitable preventive measures planned.
5.4 Emissions from construction activities including plant and equipment Yes PM, Sox, Nox etc. shall be generated during construction works due to machinery used and handling of cement, dust from excavation. Suitable preventive measures are planned for same
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Sewage and waste will be treated in such way that, there will not be any dust or odor release. Proper preventive measures for odor control shall be adopted
5.6 Emissions from incineration of waste No NA
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No NA
5.8 Emissions from any other sources No NA
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Boiler shall be sources of Noise generation. Adequate measures for control of noise levels will be implemented to maintain noise levels within limits. Workers shall be provided with PPE’s to protect from high noise levels.
6.2 From industrial or similar processes No NA
6.3 From construction or demolition Yes Adequate measures for control of noise levels will be implemented during construction phase.
6.4 From blasting or piling No NA
6.5 From construction or operational traffic No Construction work shall be done only during day time
6.6 From lighting or cooling systems No NA
6.7 From any other sources No NA
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials Yes The effluent storage shall be done in HDPE sheet lined tanks. All storage tanks shall be provided with dyke walls
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No Effluent generated will be treated in Effluent Treatment Plant .ETP Details Attached as an Annexure VII
7.3 By deposition of pollutants emitted to air into the land or into water Yes Wet Scrubber will be providing for arresting Fly ash generated from Boiler.
7.4 From any other sources No NA
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No NA
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes Disaster Management Plan and Risk assessment shall be done. All such operations shall be identified and suitable preventive measures shall be adopted.
8.2 From any other causes No NA
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No Floods and landslides are not expected in the area. Earthquake proneness: the area falls under Zone Iv as per IS 1893-2002. Hence relevant design parameters as per zone III have been considered for RCC design of the building.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes 1) Power supply is available. 2) Wide road is available
9.2 Lead to after-use of the site, which could have an impact on the environment No NA
9.3 Set a precedent for later developments No NA
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No NA
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No N.A
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No N.A
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No N.A
4 Inland, coastal, marine or underground waters No N.A
5 State, National boundaries No N.A
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No N.A
7 Defence installations No N.A
8 Densely populated or built-up area No N.A
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) No N.A
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No N.A
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No N.A
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No N.A
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantR
DesignationManaging Director
Name of Company (Applicant Name should not be given here)VITTHALRAO SHINDE SSK LTD
AddressGangamai nagar, Pimpalner, Tal- Madha, Dist- Solapur
Print