APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Establishment of Pesticide Specific Intermediates (Insect Pheromone) manufacturing unit, by, Jaydev Chemical Industries, At plot L-43 Additional Mahad MIDC, Tal. : Mahad, Dist.: Raigad, Maharashtra State.
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/MH/IND2/113023/2019
Project Cost 700 lacs
2.
S. No. in the schedule5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
Project Sector Industrial Projects - 2
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 43.41 MT/M ha.
4.
New/Expansion/ModernizationNew
5. Existing Capacity/Area etc. 0.42 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify Yes
c) Notified Eco-sensitive areas
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectAt plot L-43 Additional Mahad MIDC, Tal. : Mahad, Dist.: Raigad, Maharashtra State.
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.L-43
Town / VillageMahad
State of the projectMaharashtra
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)MaharashtraRaigadMahad
10.
Nearest railway station along with distance in kms Veer Railway Station, 10.45 km
Nearest airport along with distance in kms Pune Airport, 78 km
11. Nearest Town/City/District Headquarters along with distance in kms Mahad city , 11 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Village Panchayats - Kambale T Mahad, Raigad - Zilla Parishad, Mahad Municipal Corporation
13. Name of the Applicant Sanjay
14. Registered Address Plot No. L-43, Additional Mahad MIDC, Mahad
15.
Address for correspondance:
Name of the Company JAYDEV CHEMICAL INDUSTRIES
Name of the Applicant Sanjay
Designation (Owner/ Partner/ CEO) Partner
Pin code 400028
E-mail info@jaydevchemicals.com
Telephone No. 22-27633732
Fax No. 22-
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No The proposed project site is located in MIDC Additional Mahad, Mahad. Hence, it’s designated for industrial purpose only. There would be no any change in Land Use, Land Cover or Topography of plot. The project activities would be implemented on site as per the rules and regulations led by the MIDC Authority. Apart from the set-up for Chemical Manufacturing on site, a dense Green Belt would be developed in consultation with the District Forest Officer (DFO) in project premises.
1.2 Clearance of existing land, vegetation and buildings? No The land for the proposed project is vacant and situated in Additional MIDC Mahad. There is no any requirement for clearing of vegetation / buildings on proposed site.
1.3 Creation of new land uses? No Not Applicable.
1.4 Pre-construction investigations e.g. bore houses, soil testing? No Not Applicable.
1.5 Construction works? Yes Construction of buildings as well as infrastructural facilities required for implementation of the Manufacturing unit would be done on site
1.6 Demolition works? No Not Applicable.
1.7 Temporary sites used for construction works or housing of construction workers? Yes Temporary Sheds would be constructed for laborers till the completion of construction work.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations No Not Applicable.
1.9 Underground works including mining or tunnelling? No Not Applicable.
1.10 Reclamation works? No Not Applicable.
1.11 Dredging? No Not Applicable.
1.12 Offshore structures? No Not Applicable.
1.13 Production and manufacturing processes? No There would be no physical change in topography and landuse of locality since production and manufacturing operations shall be carried out, on the plot allocated for JCI. Manufacturing set-up shall be for production of 16 products at a time from range of 98 products. Refer Annexure I for list of products, And Annexure II for manufacturing process and mass balance.
1.14 Facilities for storage of goods or materials? Yes For the storage of chemicals, finished products and packing material a separate storage arrangements would be done. An area of about 84.55 Sq. M. would be used for storage area.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Solid Waste generated in the form process Plastic Bags–0.05 MT/M; Carboy HDPE–0.20 MT/M; Drum HDPE-0.88 MT/M; Drum MS-4.68 MT/M will be sale as scrap. The waste will be stored in covered area. The effluent generated during manufacturing would be treated in segregation of effluent stream thereby achieving ‘ZERO LIQUID DISCHARGE’ of the effluents. Salts would be dispatched to CHWTSDF.
1.16 Facilities for long term housing of operational workers? No Not Applicable.
1.17 New road, rail or sea traffic during construction or operation? No Slight road traffic is expected during the transfer of material required for fabrication/construction from the local area shops to site.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Not Applicable.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Not Applicable.
1.20 New or diverted transmission lines or pipelines? No Not Applicable.
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No There would be no change in hydrology of water sources due to establishment project. The water required for the project activities would be taken from the MIDC water supply scheme.
1.22 Stream crossings? No Not Applicable.
1.23 Abstraction or transfers of water from ground or surface waters? No Not Applicable, since water required for various industrial activities would be taken from MIDC Area water supply scheme.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No Not Applicable.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Transport of material and personnel would occur during the project construction period as well as during the operation. During the same, movement of equipment and machinery as well as labor would occur at the project site.
1.26 Long-term dismantling or decommissioning or restoration works? No Not Applicable.
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No Not Applicable.
1.28 Influx of people to an area in either temporarily or permanently? Yes Temporarily for construction work The permanent staff and workers would be employed from local area as well as from outside area in Industry on permanent basis.
1.29 Introduction of alien species? No Not Applicable.
1.30 Loss of native species or genetic diversity? No Not Applicable.
1.31 Any other actions? No Not Applicable.
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No The proposed project is going to be implemented in notified Industrial area
2.2 Water (expected source & competing users) unit: KLD Yes Daily water consumption (Annexure III) would be 21.30 CMD and 15.80 CMD would be taken from MIDC Water Supply Scheme from river Savitri. 5.5 CMD will recycle & used for Cooling & Gardening.
2.3 Minerals (MT) No Not Applicable.
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Yes, the required construction materials would be purchased from local market and sources.
2.5 Forests and timber (source – MT) Yes Negligible quantity would be required for doors, frames etc.
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes The power supply required for the proposed establishment activity would be taken from Maharashtra State Electricity Board (MSEB) Total electricity required would be 500 HP. LDO as fuel will be used in boiler.
2.7 Any other natural resources (use appropriate standard units) No Not Applicable.
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes The Material Safety Data Sheet (MSDS) of different chemicals would be used for manufacturing of products.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No There would not be any change in occurrence of disease or affect disease vectors due to this unit. Regular health checkup program for the workers working in the unit would be conducted after commissioning of project.
3.3 Affect the welfare of people e.g. by changing living conditions? No The project would not affect the welfare of people in nearby areas, since site is located in Additional MIDC area. In turn, the proposed project will provide direct and indirect employment opportunities in the project area. This would result in positive impact on the social and economic status of local people.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Not Applicable.
3.5 Any other causes No Not Applicable.
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes Yes During construction of building and infrastructure facilities required for the project, there would be activities such as excavation, back filling etc. However, once the construction gets over, the entire excess soil, if any, would be utilized through proper landscaping in the premises of the industry.
4.2 Municipal waste (domestic and or commercial wastes) No Not Applicable.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes The Hazardous Waste (Annexure IV) generated from the proposed activities would be as follows: Date-expired and off-specification pesticides - (Cat : 29.3) – 0.4 MT/ Year; Spent solvents - (Cat : 29.4) – 10 MT/ Year; Contaminated cotton rags or other cleaning material - (Cat : 33.2) – 7.2 MT/Year; ETP Sludge - (Cat : 35.3) – 0.6 MT/Year; Distillation Residue - (Cat : 36.1) – 12.62 MT/Year which will be send to CHWTSDF
4.4 Other industrial process wastes No Not Applicable.
4.5 Surplus product Yes By-products will be generated in proposed activity.
4.6 Sewage sludge or other sludge from effluent treatment Yes ETP Sludge, Chemical Sludge from wastewater treatment, Drums cleaning, Chemical containing residue from decontamination & disposal would be generated and will be disposed off by dispatch to CHWTSDF.
4.7 Construction or demolition wastes Yes Negligible quantity of construction waste would be generated. The same shall be disposed off by back filling the low line area in premises.
4.8 Redundant machinery or equipment No Not Applicable.
4.9 Contaminated soils or other materials No Not Applicable.
4.10 Agricultural wastes No Not Applicable.
4.11 Other solid wastes Yes Plastic Bags–0.05 MT/M; Carboy HDPE–0.20 MT/M; Drum HDPE-0.88 MT/M; Drum MS-4.68 MT/M same will be sold to authorized processor. Refer additional attachment for solid waste details. Refer Solid waste details in Annexure- V of additional attachments.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Under proposed unit, One Steam boiler of 1 TPH and Two Thermic Fluid Heater 2 LKcal TPH each would be installed. LDO to the tune of 1 TPD and 60 Kg/hr would be used as fuel respectively. For Boiler and Thermic Fluid Heater Scrubber would be used as an Air Pollution Control Equipment (APC). Stacks with heights 16 M (each) would be installed for Boiler and Thermic Fluid Heater respectively. One D.G. Sets (512 KVA) would be installed in which HSD to the tune of 135 lit/hr would be used as fuel.
5.2 Emissions from production processes Yes Process emissions in the form of acidic, alkaline and solvent vapours is generated from proposed activity. The same would be taken care off through installation of scrubbers.
5.3 Emissions from materials handling including storage or transport Yes Negligible amount of emissions would be generated during storage/transport of material. The same would be taken care off through installation of scrubbers in the area.
5.4 Emissions from construction activities including plant and equipment Yes Negligible dust emissions are expected. However, the same would be taken care off through the onsite measures such as water sprinkling, controlled operations through covered processes etc.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No Not Applicable.
5.6 Emissions from incineration of waste No Not Applicable.
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Not Applicable.
5.8 Emissions from any other sources No Not Applicable.
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers No Not Applicable.
6.2 From industrial or similar processes Yes There would be no any major Noise generating sources in the proposed project other than the Boiler, Reactors, and Compressors & D.G. Sets etc. The same would be kept in an isolated area, which would be provided with proper acoustic treatment to have the ambient noise levels as per CPCB standards. The workers would be provided with Earmuffs and other Personal Protective Equipments (PPE). As per Noise Pollution (Regulation and Control) Amendment Rules 2010, D.G. Set would be enclosed in a canopy.
6.3 From construction or demolition Yes During the construction or fabrication work, some noise would be generated. The same would be due to operations of machinery and equipment. However, the same would be of a temporary nature and the workers getting exposed to same would be provided with PPE
6.4 From blasting or piling No Not Applicable.
6.5 From construction or operational traffic Yes Movement of trucks for construction material would generate noise. However, this would not be of a continuous nature and would not have much impact on the work environment of the project site.
6.6 From lighting or cooling systems No Not Applicable.
6.7 From any other sources No Not Applicable.
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No Proper handling, dyke wall would be provided to avoid spillage/ leakage of hazardous materials. Routine monitoring of storage area would be done for any leakages. Leakages found would be immediately fixed in order to avoid its further contamination with water, air, soil. In the form of ETP sludge would be stored in predefined area in the premises. To avoid seepage of leachate from waste stored into the underlined ground water, area would be provided with HDPE liner as per CPCB Norms.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No Effluent (Annexure VI) - process – 2.5 CMD & washing - 1 CMD. Boiler blow downs - 0.5 CMD, cooling water make up - 0.5 CMD. The effluent generated during manufacturing would be treated in segregation of effluent stream thereby achieving ‘ZERO LIQUID DISCHARGE’ of the effluents. Salts would be dispatched to CHWTSDF.
7.3 By deposition of pollutants emitted to air into the land or into water No There would be no any deposition of air pollutants on land/surface water. Since APC will be installed to Boiler & LDO is used as fuel.
7.4 From any other sources No Not Applicable
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Not Applicable
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No Proper safety measures would be taken to avoid any mishap or accidents during construction/ operation phase of project. The workers shall be provided with proper Personal Protective Equipments (PPE). Also, training of Fire Fighting would also be given to the workers working in the Industry. An ‘On-site Emergency Plan’ has been prepared and is implemented for any emergency.
8.2 From any other causes No Not Applicable.
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No Project being affected by environmental damage is negligible.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes There would be development of internal roads in plant area and power supply lines required for various machinery operations as well as lighting in the plant premises.
9.2 Lead to after-use of the site, which could have an impact on the environment No Not Applicable.
9.3 Set a precedent for later developments No Not Applicable.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No Not Applicable.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes Not Applicable
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Solamkond Village is listed as ESA in draft notification of Western Ghat dated 03.10. 2018
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration Yes Not Applicable.
4 Inland, coastal, marine or underground waters No Not Applicable.
5 State, National boundaries Yes Not Applicable.
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No National Highway of NH-66 (NH-66 Mumbai-Goa Rd) is about 2.5 Km.
7 Defence installations No Not Applicable.
8 Densely populated or built-up area No Mahad is located at about 15 Km from project site.
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) No Not Applicable.
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No Not Applicable.
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No Not Applicable.
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No Not Applicable.
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
Additional Attachments, if any
Attached File
compliance w.r.t. EDS by MS Dated 13.08.2019
Possession Receipt
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAThe correction have been made as per the instruction received 17 Aug 2019
2.NAPlease inform whether the project site falls under critically polluted area/severely polluted area 13 Aug 2019
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.