APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s M/S. Metarolls Ispat Pvt. Ltd.
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/MH/IND/79013/2018
Project Cost 27400 lacs
2.
S. No. in the schedule3(a) Metallurgical industries (ferrous & non ferrous)
Project Sector Industrial Projects - 1
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled MS Billets - 5,70,000 TPA, TMT Bars – 5,70,000 TPA, Ferro Manganese - 21,500 TPA ha.
4.
New/Expansion/ModernizationExpansion
Proposal NumberIA/MH/IND/79012/2014
MoEFCC file number(Previous EC)SEAC 201I/CR- 683/TC2
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 7.70 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectGut No. 48, Daregaon, Adjacent to MIDC Phase II, Taluka-Jalna, District – Jalna, Maharashtra
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.Gut No. 48
Town / VillageGut No. 48, Daregaon, Adjacent to MIDC Phase II, Taluka-Jalna, District – Jalna, Maharashtra
State of the projectMaharashtra
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)MaharashtraJalnaJalna
10.
Nearest railway station along with distance in kms Jalna Railway Station, 9.0 km
Nearest airport along with distance in kms Aurangabad Airport, 48.0 km
11. Nearest Town/City/District Headquarters along with distance in kms Jalna , 4.0 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Gut No. 48, Daregaon, Adjacent to MIDC Phase II, Taluka-Jalna, District – Jalna, Maharashtra
13. Name of the Applicant DB
14. Registered Address Gunta no 48, Village Daregaon, Adjacent to MIDC Phase II, Tehsil Jalna, District Jalna, Maharashtra State
15.
Address for correspondance:
Name of the Company M/S. METAROLLS ISPAT PVT. LTD.
Name of the Applicant DB
Designation (Owner/ Partner/ CEO) Director
Pin code 431213
E-mail metarollsispat@gmail.com
Telephone No. 040-23816222
Fax No. 040-
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . NIL
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No The land is already developed for industrial use, there is no change in land use/land cover / topography.
1.2 Clearance of existing land, vegetation and buildings? No Existing land is a developed land for industrial proposes. This proposal is for expansion activity.
1.3 Creation of new land uses? No The land has to be used for Industrial use only. Hence, no change in land uses.
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Detailed investigations were carried out during initial Stage.
1.5 Construction works? Yes The proposed expansion activity includes erection of industrial structures like Induction Furnaces, Stacks, Cooling Towers, Industrial Sheds, Power Distribution Networks and other industrial structures.
1.6 Demolition works? Yes Old Induction Furnace will be replace by New Furnaces.
1.7 Temporary sites used for construction works or housing of construction workers? No During construction work, temporary housing tents will be provided to the construction workers
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Most of the structures in the plant will be above the ground. However excavations will be involved for foundations. 0BBUILDING Main plant Building, 1BFOUNDATIONS Furnaces, ground hopper etc. Pre fabricated structurals for raw material feeding system, fuel & ash handling, crane bay etc.
1.9 Underground works including mining or tunnelling? No Not Applicable
1.10 Reclamation works? No No Reclamation works are envisaged
1.11 Dredging? No No Dredging works are envisaged
1.12 Offshore structures? No Not Applicable
1.13 Production and manufacturing processes? Yes MS billets will be produced from Scrap, Pig iron and Sponge iron.
1.14 Facilities for storage of goods or materials? Yes Raw materials and finished goods would be stored in storage yards and other goods in stores building.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Liquid effluents ? Domestic waste water will be send to septic tank followed by soak pit Solid waste disposal ? Induction Furnace slags after Iron recovery sold as Construction Material. ? Mill waste generated from rolling mill we be sold to cement plant.
1.16 Facilities for long term housing of operational workers? No Majority of manpower will be recruited from local people only. Therefore no long term housing facilities for operational workers.
1.17 New road, rail or sea traffic during construction or operation? No Existing infrastructure will be used for the proposed expansion project
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Existing infrastructure is sufficient for proposed expansion project. Hence, No new road, rail or sea traffic during construction or operation.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No There will not be any closure or diversion of existing transportation routes.
1.20 New or diverted transmission lines or pipelines? No Not required to divert transmission lines/pipelines.
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No No river/stream is passing through the site.
1.22 Stream crossings? No Not Applicable
1.23 Abstraction or transfers of water from ground or surface waters? No Own water reservoir water will be used for the proposed project.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No No changes in land surface to affect drainage or run-off.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Private vehicles and tippers will be used for transport of personnel or materials during construction. During operation or decommissioning storage tankers/ lories will be used for transport of raw materials and final product.
1.26 Long-term dismantling or decommissioning or restoration works? No Not Applicable
1.27 Ongoing activity during decommissioning which could have an impact on the environment? Yes Exesting old furnaces are will be reconstructed.
1.28 Influx of people to an area in either temporarily or permanently? No No such activity is envisaged
1.29 Introduction of alien species? No As a part of greenbelt development plan, only native species that are suitable to that soil condition will be introduced.
1.30 Loss of native species or genetic diversity? No No loss of native species or genetic diversity, as the site is located in developed Industrial area.
1.31 Any other actions? Yes Plants will be grown at various points in the site and along the internal roads.
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No Existing land is sufficient for proposed expansion.
2.2 Water (expected source & competing users) unit: KLD Yes Source – Own water Reservoir Quantity– 415 KLD Existing – 215 KLD Proposed – 200 KLD
2.3 Minerals (MT) No Sponge – 310800 TPA Scrap - 438480 TPA Other Mineral – 15120 TPA Total: 764400 TPA Ferro Alloys : Manganese Ore, dolomite, and Quartz
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Particulars Source Quantity Stone aggregate (20mm&12mm) Authorized supplier 20,000 Cum Sand Authorized supplier 15,000 cum
2.5 Forests and timber (source – MT) No No timber will be used. All the structures are of MS and prefabricated.
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes ENERGY: electricity consumption will be 55 MW Source: Maharashtra State Electricity Board.
2.7 Any other natural resources (use appropriate standard units) No none
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No No materials hazardous to human health or environment are used.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No The proposed expansion activity is environment friendly.
3.3 Affect the welfare of people e.g. by changing living conditions? No The welfare of people will not be affected. Instated the socio – economic benefits arising out of this project such as creation of direct and indirect employment to local people, consequent rise in income levels, associated commercial opportunities, social infrastructure development in such remote area etc would improve living conditions of people.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No No people will be affected.
3.5 Any other causes No none
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No No mine/ mine activity. No over burden waste. The dug soil during excavation will be used for filling of low laying areas.
4.2 Municipal waste (domestic and or commercial wastes) Yes Domestic solid waste will be collected, segregated and disposed for reuse and to dumping yard.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Used oil and waste oil will be generated and will be sold to authorized vendor.
4.4 Other industrial process wastes Yes Process Slag and mill waste will be generated and will be sold as constriction material and to cement industry.
4.5 Surplus product No There is no surplus product generation. The products will be sold to the consumers.
4.6 Sewage sludge or other sludge from effluent treatment Yes STP Sludge will be generated and will used for green belt development.
4.7 Construction or demolition wastes Yes Small quantity of construction waste only and same will be reused for filling unlevel areas.
4.8 Redundant machinery or equipment Yes Any Redundant machinery or equipment will be scrapped and disposed off to scrap dealers.
4.9 Contaminated soils or other materials No No soil / material will be contaminated.
4.10 Agricultural wastes No Not Applicable
4.11 Other solid wastes Yes Kitchen waste will be converted into bio compost.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes The Induction furnaces are electric fired furnaces. Effective pollution control measures will be provided to control the emissions from the furnaces. Appropriate stack height will be maintained as per CPCB guidelines.
5.2 Emissions from production processes Yes Particulate matter and NOx will be generated.
5.3 Emissions from materials handling including storage or transport Yes Fugitive emission may generate form material handling. Water sprinkling will be done to control the fugitive emission.
5.4 Emissions from construction activities including plant and equipment Yes Exhaust emissions from vehicles and equipment deployed during the construction phase will result in marginal increase in the levels of SOR2R, NOx, PM R2.5R & PMR10.R, CO. The impact will, however, be reversible, marginal, and temporary in nature.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No Proper care will be taken during handling of materials by spraying water to suppress fugitive emissions.
5.6 Emissions from incineration of waste No No incineration of waste.
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No No open-air burning.
5.8 Emissions from any other sources No Nil.
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Noise will be only from conveyers and Fans.
6.2 From industrial or similar processes Yes Cooler and cooling tower
6.3 From construction or demolition Yes Construction equipment will cause some noise. Earplugs will be provided to construction workers who work near the noise generating equipment. The construction work will be restricted to daytime only.
6.4 From blasting or piling No No blasting or piling operations are envisaged.
6.5 From construction or operational traffic Yes Vehicle movement, etc. The noise levels will be less than 80 dB.
6.6 From lighting or cooling systems No As the cooling tower fans are made of FRP and the proposed equipment is of less noise generating type, there is no noise from cooling system. Also lighting systems generate no noise.
6.7 From any other sources No -----
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No Not Applicable
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No The generated waste water will be send to septic tank followed by soak pit
7.3 By deposition of pollutants emitted to air into the land or into water No Wet Scrubber will be provided. The furnace stack emissions will be maintained at CPCB standards.
7.4 From any other sources No Not envisaged
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Not envisaged
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No No hazardous substances.
8.2 From any other causes No ---------
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No The area of project site will not be affected by natural disasters.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes The existing infrastructure facilities are sufficient for proposed expansion. This proposal is for expansion as such no extractive industries and apartments near by locality will be attracted
9.2 Lead to after-use of the site, which could have an impact on the environment No The land is developed for industrial purpose only
9.3 Set a precedent for later developments No No such case.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No No cumulative impacts are envisaged.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No None within 10 km Aerial distance from proposed plant site.
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No None within 10 km Aerial distance from proposed plant site.
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No None within 10 km Aerial distance from plant site.
4 Inland, coastal, marine or underground waters No None within 10 km Aerial distance from plant site.
5 State, National boundaries No None within 10 km Aerial distance from plant site.
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No None within 10 km Aerial distance from plant site.
7 Defence installations No None within 10 km Aerial distance from plant site.
8 Densely populated or built-up area Yes Jalana city at a distance of 6.0 km from plant site
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Jalna city
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No None within 10 km Aerial distance from plant site.
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No None within 10 km Aerial distance from plant site.
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No The areas are not susceptible to natural hazards (as per data available from past records)
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) NIL
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantDB
DesignationDirector
Name of Company (Applicant Name should not be given here)M/S. METAROLLS ISPAT PVT. LTD.
AddressGunta no 48, Village Daregaon, Adjacent to MIDC Phase II, Tehsil Jalna, District Jalna, Maharashtra State
Print