APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Modification in existing 2.0MTPA Deshaled crushing unit to 2.0MTPA Wet coal washery.
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/MH/CMIN/72327/2018
Project Cost 950 lacs
2.
S. No. in the schedule2(a) Coal washeries
Project Sector Coal Mining
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 2.0MTPA Wet Coal Washery ha.
4.
New/Expansion/ModernizationNew
5. Existing Capacity/Area etc. 0000 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectVillage :Muthara Tahsil : Rajura District : Chandrapur State : Maharashtra
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.131/2, 131/3, 131/4
Town / VillageMuthara
State of the projectMaharashtra
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)MaharashtraChandrapurRajura
10.
Nearest railway station along with distance in kms Ballarshah 13.0 Km at NE Direction, 13 km
Nearest airport along with distance in kms Nagpur, 166 km
11. Nearest Town/City/District Headquarters along with distance in kms Rajura , 9.5 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Village :Muthara Panchayat :Muthara Tahsil :Rajura District :Chandrapur
13. Name of the Applicant K
14. Registered Address Survey No.131/2, 131/3, 131/4 Village: Muthara, Tehsil: Rajura, District: Chandrapur (MS)
15.
Address for correspondance:
Name of the Company N. N. GLOBAL MERCANTILE PRIVATE LIMITED
Name of the Applicant K
Designation (Owner/ Partner/ CEO) CEO
Pin code 442401
E-mail nngloble12568@gmail.com
Telephone No. 0712-2293225
Fax No. 0712-2293225
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No Modification will be carried out in existing machines and equipment.
1.2 Clearance of existing land, vegetation and buildings? No NA
1.3 Creation of new land uses? No NA
1.4 Pre-construction investigations e.g. bore houses, soil testing? No Will be initiated only after all approval, clearance & consent.
1.5 Construction works? No Existing facility is sufficient for wet coal washery.
1.6 Demolition works? No NA
1.7 Temporary sites used for construction works or housing of construction workers? No Worker required for construction will be arrange from nearby villages.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Dense Media Wemco Drum Separator, Desliming Screen, D/R Screen, Heavy Media & Dilute media Sump, Thickener
1.9 Underground works including mining or tunnelling? Yes Underground reclaimed tunnel below concrete hopper about 6-6.5 m below ground level.
1.10 Reclamation works? No NA
1.11 Dredging? No NA
1.12 Offshore structures? No NA
1.13 Production and manufacturing processes? Yes Beneficiation of raw coal @ 2.0MTPA
1.14 Facilities for storage of goods or materials? Yes There will be sufficient space available for storing raw coal and coal rejected and washed coal which are a fast moving item.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes A well designed effluent treatment plant consisting of Thickener, High frequency screen, classifying cyclone filler press etc are proposed. Entire effluent after treatment shall be reused in process. It shall be zero discharge unit.
1.16 Facilities for long term housing of operational workers? No NA
1.17 New road, rail or sea traffic during construction or operation? No Existing road network is well developed.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Existing road network is sufficient.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No NA
1.20 New or diverted transmission lines or pipelines? No NA
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No NA
1.22 Stream crossings? No NA
1.23 Abstraction or transfers of water from ground or surface waters? Yes Ground water will be used for domestic and industrial purpose.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No NA
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Raw Coal will be received by truck and railway. Washed coal will be transported by railway and Tarpaulin covered trucks. Reject will be transported by both tarpaulin covered trucks and rail.
1.26 Long-term dismantling or decommissioning or restoration works? No NA
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No NA
1.28 Influx of people to an area in either temporarily or permanently? Yes About 50 Construction workers for temporary period. About 51 Number of workers and staff required for operation of plant.
1.29 Introduction of alien species? No NA
1.30 Loss of native species or genetic diversity? No NA
1.31 Any other actions? No NA
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No All modification will be carried out in existing.
2.2 Water (expected source & competing users) unit: KLD Yes The total water requirement for industrial use is 120 m3/ day, including for Industrial, Domestic and Dust Suppression purpose will be pumped out from existing bore well in plant premises.
2.3 Minerals (MT) Yes Raw coal 2.0 MTPA
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Shall be finalize after design and drawing. Source will be local market.
2.5 Forests and timber (source – MT) No NA
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Total electrical power will be 11 KV Source will be MSEDCL.
2.7 Any other natural resources (use appropriate standard units) No NA
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes For DG set in emergency power failure.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No NA
3.3 Affect the welfare of people e.g. by changing living conditions? No Additional jobs available in proposed project will improve the socio – economic status by providing direct and indirect employment.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No NA
3.5 Any other causes No NA
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No NA
4.2 Municipal waste (domestic and or commercial wastes) Yes Only domestic waste 1.5m3/day , and coal rejects @ 15-20 % of raw coal.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Only used machine oil shall generate during maintenance and overhauling and shall be stored in environment friendly manner and will be sold to registered oil vendors only.
4.4 Other industrial process wastes No The total rejects will be 15-20% of Raw coal i.e. maximum 0.40 MT/annum. Will be sold to nearby power plant, sponge iron plant and other plants.
4.5 Surplus product No NA
4.6 Sewage sludge or other sludge from effluent treatment No The total rejects will be 15-20% of Raw coal i.e. maximum 0.40 MT/annum. Will be sold to nearby power plant, sponge iron plant and other plants.
4.7 Construction or demolition wastes No NA
4.8 Redundant machinery or equipment No NA
4.9 Contaminated soils or other materials No NA
4.10 Agricultural wastes No NA
4.11 Other solid wastes No NA
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Operation of dumpers and trucks used for the transport of coal and washed coal.
5.2 Emissions from production processes Yes Crushing and Screening operations during washing process generates dust. Air Pollution Control Devices will be installed. Coal dust collector of 28000m3/hr shall be installed.
5.3 Emissions from materials handling including storage or transport Yes Due to handling of raw material i.e. coal. Dust suppression system is proposed to control dust. Sprinkler will be install at appropriate location
5.4 Emissions from construction activities including plant and equipment Yes The fugitive dust will be confined to construction, loading, and unloading of material only, it shall be negligible.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Fugitive emission will be generated due to construction activity. It will be controlled by water spraying
5.6 Emissions from incineration of waste No NA
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No NA
5.8 Emissions from any other sources No NA
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Operation of Machineries, Movements of Vehicles shall generate noise.
6.2 From industrial or similar processes Yes Noise will be generated during operation of machinery.
6.3 From construction or demolition No NA
6.4 From blasting or piling No NA
6.5 From construction or operational traffic No NA
6.6 From lighting or cooling systems No NA
6.7 From any other sources No NA
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No NA
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes It is a Zero Discharge, Close Circuit industry with no discharge out of the premises. Entire effluent after treatment shall be reused for coal washing purpose.
7.3 By deposition of pollutants emitted to air into the land or into water No NA
7.4 From any other sources No NA
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No NA
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes Coal is combustible material which can burn due to spontaneous heating if stock for long time. Emergency plan and proper arrangements for firefighting will be provided.
8.2 From any other causes No NA
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? Yes Earthquake, Cloudburst. Emergency preparedness plan will be prepared.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
No Employment Generation
9.2 Lead to after-use of the site, which could have an impact on the environment No NA
9.3 Set a precedent for later developments No NA
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects Yes Use of washed Coal is an environmental friendly activity. The inherited ash content of the coal along with sulphur is reduced from the coal during washing. Consequently, the emission of ash and sulphur during combustion for industrial use gets reduced.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No NA
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Patches of Rajura R.F from 6.0Km NE direction to 7.0Km East direction. • Nallah adjacent to baoundary wall at west direction • Chinna Vagur river 7.0km at North direction • Sondo Nallah 9.0Km at South direction. • Wardha River 11Km NE direction
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No NA
4 Inland, coastal, marine or underground waters No NA
5 State, National boundaries No NA
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No NA
7 Defence installations No NA
8 Densely populated or built-up area Yes Rajura at 9.5Km East direction.
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes AREA Hospital, Dhopatala, Rajura.9.0Km at NE direction
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No NA
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No NA
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No NA
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
5Uploaded Approval of mining PlanN/A
Additional Attachments, if any
Attached File
ADS Letter
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterCompliance to ADS 13 Nov 2019
2.NAPlease inform/clarify the following: - EC for the present 2.0 MTPA deshaled coal crishing unit, - Consent to Establish/operate from the SPCB for the present industrial operations, - Present operational status of the unit along with supporting documents, 05 Feb 2018
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantK
DesignationCEO
Name of Company (Applicant Name should not be given here)N. N. GLOBAL MERCANTILE PRIVATE LIMITED
AddressSurvey No.131/2, 131/3, 131/4 Village: Muthara, Tehsil: Rajura, District: Chandrapur (MS)