APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Expansion of New Majri UG to OC
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/MH/CMIN/107217/2019
Project Cost 40827.65 lacs
2.
S. No. in the schedule1(a) Mining of minerals
Project Sector Coal Mining
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 3.75 ha.
4.
New/Expansion/ModernizationExpansion
Proposal NumberIA/MH/CMIN/8127/2008
MoEFCC file number(Previous EC)J-11015/25/2008-IA.II(M)
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 1.20 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectShivaji Nagar, Majri
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.Latitudes : N 20°06'45.43" to 20°08'43.08" Longitudes: E 79°00'13.53" to 79°01'59.9" Survey of India Topo Sheet No. 55 P/4
Town / VillageShivaji Nagar, Majri
State of the projectMaharashtra
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)MaharashtraChandrapurBhadravati
10.
Nearest railway station along with distance in kms Majri railway station which is on Wardha – Kazipeth main line of Central Railway, 3 km
Nearest airport along with distance in kms Nagpur, 130 km
11. Nearest Town/City/District Headquarters along with distance in kms Majri , 3 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Shivaji Nagar, Majri Tahsil –Bhadravati, Dt. Chandrapur, Maharashtra State
13. Name of the Applicant KAUSHIK
14. Registered Address Coal Estate Civil lines, Nagpur-440001
15.
Address for correspondance:
Name of the Company Western Coalfields Limited
Name of the Applicant KAUSHIK
Designation (Owner/ Partner/ CEO) G.M (MINING)/ ENVIRONMENT.
Pin code 440001
E-mail gmenvironment.wcl@coalindia.in
Telephone No. 712-2510151
Fax No. 712-2510151
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes The proposed Expansion Project Report of New Majri UG to OC mine has envisaged further expansion of mine in dip side and increase in ML area from 479.16 ha to 706.28 ha. Additional land requirement is 227.12 ha. The major land use type within the core zone is agriculture. The mining has been planned in such a way that minimum amount of land is degraded. The additional land proposed for the mine is basically required for mine expansion and construction of final embankment, road diversion etc. No
1.2 Clearance of existing land, vegetation and buildings? Yes The present proposal is expansion of existing New Majri UG to OC. The mining operations require clearance of existing land, vegetation and buildings. The land use changes details are provided above. As per the data provided by Majri Area WCL, about 40 nos.of hutments/ quarters belonging to WCL employees in WCL land and 70 nos. of private hutments in private land are required to be dismantled as these hutments fall within safety zone of the mine. Accordingly, provision has been made in this repo
1.3 Creation of new land uses? Yes Post mining land use pattern are as follows total land involved is 706.28 ha, plantation will be carried out in 250.80 ha, water body of 358.35 ha, Public use 46.20 ha, Undisterb land 50.93 ha. (External OB dump 84.60 ha, Top soil dump 4.20 ha, Excavation 358.35 ha, Infrastructure 15.0 ha, Embankment 53.20 ha, Undisturbed area 190.53 ha)
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes The proposed New Majri UG to OC Expansion mine has been envisaged upto 250m depth and the total 21 boreholes in the quarry area has been done in 2.78 km2 area.
1.5 Construction works? Yes Following infrastructure has been constructed and it will be utilized for expansion proposal also: 1. Explosive Building 2. Statutory Building 3. Community Building 4. Colony 5. Office 6. Effluent Treatment Plant 7. Sedimentation Tank Following additional infrastructure will be constructed for expansion proposal: 1. Excavation Workshop 2. E&M Workshop 3. Unit Store 4. Substation 5. Approach Road – 3 km 6. Haul Road – 4 km 7. Heavy Duty Road – 4 km 8. Service Road – 1 km 9. Dive
1.6 Demolition works? Yes • About 40 nos.of hutments/ quarters belonging to WCL employees in WCL land and 70 nos. of private hutments in private land are required to be dismantled. • Demolition of temporary construction. • Further, demolition of infrastructure will be carried out at the time of Mine Closure as per the approved Mine Closure Plan.
1.7 Temporary sites used for construction works or housing of construction workers? No It is an existing project. Temporary site for construction works will not be required.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Quarry area 358.35 ha having depth 250 m. External dump area of 84.60 ha having height 60m. OB is being dumped on surface in the form of well-designed OB dump with maximum height of 90.0 m. Embankment of 6 m above HFL and 30 m width for total approx 8.0 kms of length has also been constructed along the Wardha River and Periphery of the mine.
1.9 Underground works including mining or tunnelling? No Excavation by Opencast mining.
1.10 Reclamation works? Yes Post mining land use pattern are as follows total land involved is 706.28 ha, plantation will be carried out in 250.80 ha, water body of 358.35 ha, Public use 46.20 ha, Undisterb land 50.93 ha. (External OB dump 84.60 ha, Top soil dump 4.20 ha, Excavation 358.35 ha, Infrastructure 15.0 ha, Embankment 53.20 ha, Undisturbed area 190.53 ha)
1.11 Dredging? No Nil
1.12 Offshore structures? No Nil
1.13 Production and manufacturing processes? Yes Open Cast mining with Shovel - Dumper Combination method.
1.14 Facilities for storage of goods or materials? Yes ? The Overburden (OB) lying above the coal seam is being stacked at earmarked sites as external OB dump and also proposed to be accommodated in the de-coaled void as internal dump in adjacent New Majri Sector IA & IIA Extension OC mine. ? Coal is stored in the earmarked site in the Coal Stock Yard. ? The storage of goods and other material are made in Designated Store.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes ? The Overburden (OB) lying above the coal seam is being stacked at earmarked sites as external OB dump and also proposed to be accommodated in the de-coaled void as internal dump in adjacent New Majri Sector IA & IIA Extension OC mine. ? Coal is stored in the earmarked site in the Coal Stock Yard. ? The storage of goods and other material are made in Designated Store. Solid Waste – Solid waste is mainly overburden generated from the excavation work. The mining operation has been planned
1.16 Facilities for long term housing of operational workers? Yes It has been assumed that the manpower requirement will be fulfilled by existing mines of Majri area, accordingly quarters for the proposed manpower of the mine will be provided from the existing townships of Majri area. A hostel/guest house has been envisaged.
1.17 New road, rail or sea traffic during construction or operation? Yes Following roads are proposed: 1. Diversion of Road from Patal Village to Majri railway Station – 4 km 2. Approach Road – 3 km 3. Haul Road – 4 km 4. Heavy Duty Road – 4 km 5. Service Road – 1 km 6. Rail under bridge (RUB) or Rail over bridge (ROB) over the Wani-Majri Railway line
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Following roads are proposed: 1. Diversion of Road from Patal Village to Majri railway Station – 4 km 2. Approach Road – 3 km 3. Haul Road – 4 km 4. Heavy Duty Road – 4 km 5. Service Road – 1 km 6. Rail under bridge (RUB) or Rail over bridge (ROB) over the Wani-Majri Railway line
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Following roads are proposed: 1. Diversion of Road from Patal Village to Majri railway Station – 4 km 2. Approach Road – 3 km 3. Haul Road – 4 km 4. Heavy Duty Road – 4 km 5. Service Road – 1 km 6. Rail under bridge (RUB) or Rail over bridge (ROB) over the Wani-Majri Railway line
1.20 New or diverted transmission lines or pipelines? Yes One 66 kV and two 11 kV electric lines are passing through the property of proposed New Majri UG to OC Expansion mine which require diversion to work beyond the existing dip side mine boundary. Out of these three power lines, two power lines viz. 66 kV and 11 kV electric lines belonging to the mine and Majri area are proposed to be diverted along the rise side between quarry edge and the external dump. The 3rd power line of 11 kV capacity belonging to MSEB is proposed to be diverted along the d
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? Yes A Nallah has been already diverted for the existing proposal as per the approved plan of CDO Nashik. The present expansion proposal does not envisages any further Nallah diversion. Wardha River is flowing in the dip side of the proposed Expansion mine and an embankment has been provided along the periphery of the quarry for protection against the water inrush.
1.22 Stream crossings? No Nil
1.23 Abstraction or transfers of water from ground or surface waters? Yes Due to excavation strata seepage water gets accumulated at the floor of the coal seam in the sump having capacity to deal with peak rainfall. In order to maintain the working faces dry for coal production this water is pumped out daily.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No Nil
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Personal as well as official vehicles are used for transportation of mining personnel. Store and construction material is transported by trucks.
1.26 Long-term dismantling or decommissioning or restoration works? No • About 40 nos.of hutments/ quarters belonging to WCL employees in WCL land and 70 nos. of private hutments in private land are required to be dismantled. • Dismantling of industrial infrastructure will be carried out at the time of mine closure as per the approved final approved Mine Closure Plan. However, adequate fund for closure activities have been provided in Mine closure plan.
1.27 Ongoing activity during decommissioning which could have an impact on the environment? Yes Dismantling of industrial infrastructure will be carried out at the time of mine closure. Plantation will also be carried out for reclamation.
1.28 Influx of people to an area in either temporarily or permanently? No Dismantling of industrial infrastructure will be carried out at the time of mine closure. Plantation will also be carried out for reclamation. This is an ongoing project.
1.29 Introduction of alien species? No Nil
1.30 Loss of native species or genetic diversity? No Nil
1.31 Any other actions? No Nil
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes In expansion proposal additional 220.30 ha of agriculture/tenancy land will be acquired. The project is diverting total 680.51 ha of Agriculture/Tenancy land.
2.2 Water (expected source & competing users) unit: KLD Yes Industrial water demand- 910 KLD The complete Industrial water demand is met by the mine discharge of the mine.
2.3 Minerals (MT) Yes Coal. The total balance mineable reserves as on 1/4/2018 is 36.09 MT.
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Construction material will be required for additional infrastructure as envisaged in the Project Report.
2.5 Forests and timber (source – MT) No Nil
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Fuel - 3,75,44,473 Liter, Power Consumption (KWH)- 544020000 KWH, Explosive (kg/year)- 12997163.65 Kg (All equipment’s requirement for target production is considered in departmental option)
2.7 Any other natural resources (use appropriate standard units) No Nil
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes Sludge from ETP is transported to authorized recycler. Used oil is sent to Area Store for further selling it to authorized buyer. During proposed expansion of mine, the above practice will be continued.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Nil
3.3 Affect the welfare of people e.g. by changing living conditions? No Nil
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Nil
3.5 Any other causes No Nil
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes Yes Total overburden generation from the mine is 383.99 Mm3. Out of which 10.31 Mm3 has been generated till 31.03.2018 and dumped in rise side external dump (6.39 Mm3), black cotton soil dump (1.20 Mm3) and embankment (0.50 Mm3). Additional 373.68 Mm3 OB will be generated, out of which 32.45 Mm3 of overburden will be dumped in existing external dump and 4.50 Mm3 in embankment. The balance 336.73 Mm3 OB will be accommodated in the void and surface area of nearby New Majri Sector – IA & IIA OC mine a
4.2 Municipal waste (domestic and or commercial wastes) Yes Domestic – Recycling for manures.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Sludge from proposed ETP will be transported to authorized recycler.
4.4 Other industrial process wastes No Nil
4.5 Surplus product No Nil
4.6 Sewage sludge or other sludge from effluent treatment Yes Sludge from proposed ETP and STP will be transported to authorized recycler
4.7 Construction or demolition wastes No Nil
4.8 Redundant machinery or equipment No Nil
4.9 Contaminated soils or other materials No Nil
4.10 Agricultural wastes No Nil
4.11 Other solid wastes No Nil
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes • Operation of Heavy Earth Moving Machines (HEMMs). • The quantum of gases viz. SO2, NO2 and CO in ambient environment is being measured through ambient air quality monitoring in the mine activity area every fortnight as per Environment Protection Amendment Rule, 2000;
5.2 Emissions from production processes Yes • Dust particles including coal dust. • The quantum of Dust (PM10 & PM2.5) in the ambient environment is being measured through ambient air quality monitoring in the mine activity area every fortnight as per Environment Protection Amendment Rule, 2000.
5.3 Emissions from materials handling including storage or transport Yes • Dust particles including coal dust. • The quantum of Dust (PM10& PM2.5) in the ambient environment is being measured through ambient air quality monitoring in the mine activity area every fortnight as per Environment Protection Amendment Rule, 2000.
5.4 Emissions from construction activities including plant and equipment No Nil
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No Nil
5.6 Emissions from incineration of waste No Nil
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Nil
5.8 Emissions from any other sources No Nil
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes • Generation of Noise and Vibration is due to the following operations. i) Operation of HEMMs / Machineries. ii) Blasting Operations The quantum of noise in ambient environment is measured through ambient noise quality monitoring in the mine activity area every fortnight as per Environment Protection Amendment Rule, 2000.
6.2 From industrial or similar processes No Nil
6.3 From construction or demolition No Nil
6.4 From blasting or piling Yes Blasting is carried out as per permission from DGMS and it is maintained within the permissible limits specified by DGMS.
6.5 From construction or operational traffic Yes Operational – through movement of coal transportation trucks and dumpers. Noise level is on fortnight basis as per Environment Protection Amendment Rule, 2000.
6.6 From lighting or cooling systems No Nil
6.7 From any other sources No Nil
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials Yes Used Oil – is disposed off through approved Recyclers and same will be continued.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes The water discharged from the sedimentation tank and effluent treatment plant is utilized for industrial purpose. Quality parameters are monitored every fortnight.
7.3 By deposition of pollutants emitted to air into the land or into water Yes Fugitive emission into air from OB dumps, transportation roads.
7.4 From any other sources No Nil
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Nil
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes Explosives are used for blasting as permitted by DGMS. Safety from Fire: No person shall deposit heated material or ashes on any opencast working. No person shall light a fire or permit a fire to be lighted in any OC working except by the permission in writing of the Manager and only for a special purpose specified therein. No coal shall be left exposed in coal benches more than its incubation period to avoid fire in seam due to spontaneous heating. Proper type of the extinguisher should be
8.2 From any other causes Yes Due to – 1) Land Slide in OB Dump and mine Pit 2) Mine Inundation 3) Blasting - All operations are carried out as per statute and will be continued as per statue.
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? Yes Since there is a danger of flood water from Wardha river as well as Koradi nala, an embankment of 30m width on top and 6m height above HFL has been proposed all along the quarry boundary (for approx 8 kms) to protect the mine from sudden inrush of water. Suitable alarms connected to float in Wardha river would be provided at strategic places like Time Keeper Office, Security Office, Safety Office, Manager Residence, Pit Office etc. The floats in the river would activate the alarms as soon as
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes The project has led to development of housing, roads, ancillary industries, Improvement in social & living standards by providing opportunities of direct & indirect employment to local community
9.2 Lead to after-use of the site, which could have an impact on the environment Yes The degraded land is proposed to be biologically reclaimed which will improve the green cover in the area.
9.3 Set a precedent for later developments Yes Activities detailed out in previous paragraph above do culminate in conjunction with local setup has set precedence of economic development leading to overall socio-economic growth of the area.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects Yes Operating opencast coal mines. Coal occurs in layers and continues for large distance. Associated mining activity with such closely located centers along with other related service sector could have a cumulative impact.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No Nil
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Wardha River - The Southerly flowing Wardha River is located near the western boundary of New Majri UG to OC Mine area. No forest land is involved in this project. There are no coastal zones, biospheres, and mountains.
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No Nil
4 Inland, coastal, marine or underground waters No Nil
5 State, National boundaries No Nil
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No Nil
7 Defence installations No Nil
8 Densely populated or built-up area Yes Shivaji Nagar, Majri is located west of outside of mine boundary. Warora, Bhadravati and Wani townships are within the 10 kms aerial distance of the project.
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Shivaji Nagar, Majri is located west of outside of mine boundary. The settlement is having schools and place of worship etc.
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Yes Ground water – Yes Surface water- River, Nallah’s. Forestry – No Agricultural – Yes Fisheries - No Minerals – Coal.
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No Nil
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No Nil
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
5Uploaded Approval of mining PlanAnnexure-Uploaded Approval of mining plan
Additional Attachments, if any
Attached File
Risk and Disaster Management
FORM I
Environmental Clearance
EDS Reply
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAThe correction have been made as per the instruction received 09 Jul 2019
2.NAPls submit Pre-feasibility report (PFR) as per Ministry's guidelines 30th December, 2010. present PFR report is not as per ministry's guidelines 06 Jul 2019
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantKAUSHIK
DesignationG.M (MINING)/ ENVIRONMENT.
Name of Company (Applicant Name should not be given here)Western Coalfields Limited
AddressCoal Estate Civil lines, Nagpur-440001