APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Setting-up of Sira Industrial Area | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/KA/NCP/64746/2017 | Project Cost | 28525 lacs | |
| 2. | |
S. No. in the schedule | 7(c) Industrial estates/ parks/ complexes/ areas, export processing Zones
| Project Sector | INFRA-1 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 329.9Ha ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 329.9 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | Yes | d) | Inter-State boundaries and international boundaries | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Mudugere kawal, Sira Taluk, Tumkur District, Karnataka | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | Enclosed as Annexure-I at the end of Form-1. | Town / Village | Mudugere kawal | State of the project | Karnataka | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Karnataka | Tumkur | Sira | | 10. | |
Nearest railway station along with distance in kms | Sira Railway Station, 5 km | Nearest airport along with distance in kms | Bangalore Air port, 120 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Sira , 5 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Mudugere Kawal Village Panchayat
Sira town taluk – 3 km
Tumkur District – 50 km | | 13. | Name of the Applicant | Mr.T.R.Swamy | | 14. | Registered Address | 4th & 5th floors, Khanija Bhavan, East Wing, No.49, Race Course Road, Bangalore 560001 | | 15. | |
Address for correspondance: | Name of the Company | Mr.T.R.Swamy | Name of the Applicant | Mr.T.R.Swamy | Designation (Owner/ Partner/ CEO) | Chief Development Officer (CDO) | Pin code | 560001 | E-mail | cdocekiadb@gmail.com | Telephone No. | 080-22267891 | Fax No. | 080-22267901 | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | | 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | The land cover / topography of the land will be altered after the establishment of the Proposed industries in the Sira Industrial Area. | 1.2 | Clearance of existing land, vegetation and buildings? | No | There are no buildings/ structures in the proposed site. | 1.3 | Creation of new land uses? | Yes | For Industrial Use. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Soil Testing would be made prior to start of the industrial area development activities. | 1.5 | Construction works? | Yes | Fencing Activities and Internal Roads, Drains and Street lights etc. to be made after the start of the Development. | 1.6 | Demolition works? | No | There are no demolition works involved | 1.7 | Temporary sites used for construction works or housing of construction workers? | Yes | Mostly local labor will be employed. However temporary labor sheds will be provided for the construction workers and they will be cleared after completion of the construction work. Concerned contractor is responsible for providing these facilities and removing them subsequently. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | During site preparation, the excavated material will be used for laying of internal roads and filling-up of low lying areas within the project area. | 1.9 | Underground works including mining or tunnelling? | No | The project does not involve any mining or tunneling activities | 1.10 | Reclamation works? | No | Not applicable | 1.11 | Dredging? | No | Not applicable | 1.12 | Offshore structures? | No | Not applicable | 1.13 | Production and manufacturing processes? | No | The Proposed Project is an Industrial Area development Project. It is proposed to be established new industries of all category B projects. The details are presented in Pre Feasibility Report (enclosed). | 1.14 | Facilities for storage of goods or materials? | Yes | Temporary facilities will be developed during construction phase for storage of construction materials. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Solid Waste
Construction Stage:
The solid waste during the construction phase will comprise of excavated earth, building construction materials.
The construction wastes will be reused mostly for leveling the site and the segregated recyclable wastes like metals, glass and plastic wastes will be sold to the authorized vendors.
In addition to that there will be some municipal solid waste generation during the construction stage which will be collected and disposed off at the designated muni | 1.16 | Facilities for long term housing of operational workers? | No | No long term housing is proposed. Mostly local labor will be employed. However temporary labor sheds will be provided for the construction workers and they will be cleared after completion of the construction work. Concerned contractor is responsible for providing these facilities and removing them subsequently. | 1.17 | New road, rail or sea traffic during construction or operation? | No | During construction new roads will be constructed for man and material movement. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | Yes | There would be an Increase in traffic due to the Proposed industrial area. However, Internal Roads would be made for maintaining the free flow of traffic. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | Yes | Internal roads will be provided, to make free flow of traffic. | 1.20 | New or diverted transmission lines or pipelines? | No | Internal electrical lines and water/sewer pipelines will be laid to provide the infrastructural facilities for the proposed project. Diversion of transmission lines and pipelines is not involved in the proposed project. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | No | 1.22 | Stream crossings? | No | No stream crossings. | 1.23 | Abstraction or transfers of water from ground or surface waters? | No | Construction Stage:
Source: Hemavathi Canal water linked with Sira Tank and Ground water from borewell.
Operation Stage:
The Industries to be proposed are “B”Category industries that utilize minimum water. Individual industries have to take permission from the Authorities for water intake. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | Yes | The project will involve construction of hard paved areas and hence the quantity of run-off will increase due to reduced infiltration.
The runoff will be managed through a well designed storm water network and will be used for artificial recharge of underground aquifers. | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | Construction materials and labour movement will be there at construction stage. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | No long term dismantling works involved. | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | Temporary influx of labour force will be there only during construction phase. However, influx of skilled and professionals will be employed on long term basis at the time of operations of the proposed industries in the Industrial development area. | 1.29 | Introduction of alien species? | No | Not applicable | 1.30 | Loss of native species or genetic diversity? | No | Only local native species will be utilized for green belt development | 1.31 | Any other actions? | No | Only local native species will be utilized for green belt development | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | The entire land has been private and govt. land that has been acquired by KIADB | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Source: Hemavathi Canal connected with Sira Tank & Bore well
Water expected capacity – 0.81 MLD
The water for drinking and domestic purposes is provided by KIADB through Water tank of 225 cusecs capacity. | 2.3 | Minerals (MT) | No | No Minerals involved | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | 1225 MT/km (approximately)
Source of the construction material is the local available market near by the project site. | 2.5 | Forests and timber (source – MT) | No | No forest cutting is involved in the project. However timber is purchased in local timber Depots. | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Sub Station is proposed for the Industrial area.
The location of the proposed sub-station is as shown in the enclosed location map. | 2.7 | Any other natural resources (use appropriate standard units) | No | No other natural resource except mentioned above will be used. | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | Sponge iron, iron re-rolling mills are the type of industries proposed.
Each individual industry will have to take Hazardous waste authorization Consent from KSPCB for running their unit. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | No Disease or affect of Disease | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | Increase employment | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Not Applicable | 3.5 | Any other causes | No | Not Applicable | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | Yes | Excavated earth to be re-used for site leveling. | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Municipal Solid Waste
Domestic Waste collection system will be collected and dumped at specified location within the site. Twin bins system will be adopted for segregation of wastes at source. Recyclable wastes will be sold off to authorized vendors. Bio-degradables will be treated on-site through Organic Waste Converter and the compost will be used as manure.
Operation Stage:
Waste generation from the individual industries, each industry has to obtain separate authorization, however there | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Each industry has to obtain separate authorization, | 4.4 | Other industrial process wastes | No | Proposed is an industrial Area, no process wastes may be generated consisting of Engineering Works, foundry, etc. | 4.5 | Surplus product | No | Not applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | The sludge generated from STP will be collected and disposed as directed by regulatory authorities | 4.7 | Construction or demolition wastes | Yes | Construction waste would be utilized internally to the maximum extent possible. | 4.8 | Redundant machinery or equipment | No | Not applicable | 4.9 | Contaminated soils or other materials | No | Not applicable | 4.10 | Agricultural wastes | No | Not applicable | 4.11 | Other solid wastes | No | Not applicable | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Particulate matter, SO2, NOx Emissions from mobile sources will be mainly from the movement of trucks and/ or tankers. | 5.2 | Emissions from production processes | Yes | • Suspended particulate matter, SO2, NOX | 5.3 | Emissions from materials handling including storage or transport | Yes | Dust emissions due to solid material handling | 5.4 | Emissions from construction activities including plant and equipment | Yes | Fugitive emissions | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Fugitive emissions
No odour problem is expected from proposed project. | 5.6 | Emissions from incineration of waste | No | Not applicable | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not applicable | 5.8 | Emissions from any other sources | No | Not applicable | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | No | Not applicable | 6.2 | From industrial or similar processes | No | Not applicable | 6.3 | From construction or demolition | Yes | The expected noise levels (dB) generated from construction equipment at a distance of 50 ft. from the source are given below:
Concrete Mixer Truck - 85 dB
Hammering - 86 dB
Loader - 81 dB | 6.4 | From blasting or piling | No | Not applicable | 6.5 | From construction or operational traffic | Yes | Traffic related noise will be generated during construction and operational phase which will not have any significant impact and is localized. | 6.6 | From lighting or cooling systems | No | Not applicable | 6.7 | From any other sources | No | Not applicable | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | Operation under closed circuit system. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | Sewage and all effluents will be treated and meeting the norms specified by CPCB/SPCB | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | None | 7.4 | From any other sources | No | None | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | None | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | Leakages and accidental release.
All preventive as well as incidental measures will be followed. All provisions of boiler & factory rules, personnel & Safety rules. Fire safety rules will be strictly observed from the inception of the project. | 8.2 | From any other causes | No | None | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | Yes | The project site falls under seismic zone – II. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| No | Not applicable | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not applicable | 9.3 | Set a precedent for later developments | No | Not applicable | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | Not applicable | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | None within 10 km radius of the proposed plant site | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | No | None within 10 km radius of the proposed plant site | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | None within 10 km radius of the proposed plant site | 4 | Inland, coastal, marine or underground waters | Yes | Sira lake – 2.5 km | 5 | State, National boundaries | No | None within 10 km radius of the proposed plant site | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | None within 10 km radius of the proposed plant site | 7 | Defence installations | No | None within 10 km radius of the proposed plant site | 8 | Densely populated or built-up area | No | | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Tumkur town – 50 km
Sira Taluk- 3.0 km | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | None within 10 Tumkur town – 50 km
Sira Taluk- 3.0 km
km radius of the proposed plant site | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | None within 10 km radius of the proposed plant site | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | None within 10 km radius of the proposed plant site | | (IV) | Proposed Terms of Reference for EIA studies | | Additional Attachments, if any |
---|
Attached File |
---|
| | | Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | The correction have been made as per the instruction received | 13 Nov 2017 | 2. | NA | 1. Whether it is a 'A'/'B category project not clear?
2. Whether wildlife sanctuary project falling within 10 km radius of the project or not?
3. If it is a B category project and wildlife sanctuary not falling within 10 km radius of the project. Please withdraw the application and apply to SEIAA, Karnataka. | 13 Nov 2017 | 3. | NA | The correction have been made as per the instruction received | 10 Nov 2017 | 4. | NA | 1.In basic information of Form-I 21(2) it was mentioned No that the proposal involves approval/clearance under the wildlife (Protection) Act,1972.But in brief summary of project kagaladu bird sanctuary is 9.8 km please clarriffy in this regard
2 .Please submit a plan showing with distance between proposed Industrial area and Kagaladu wild life santuary | 18 Jul 2017 | | Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | NA | The proposal was not considered by the EAC due to lack of clarity on scoping of the proposal. | 06 Dec 2017 | | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Mr.T.R.Swamy | Designation | Chief Development Officer (CDO) | Name of Company (Applicant Name should not be given here) | Mr.T.R.Swamy | Address | 4th & 5th floors, Khanija Bhavan, East Wing, No.49, Race Course Road, Bangalore 560001 |
|
|