APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Expansion of Sri Ram Power & Steel Pvt. Ltd. for production of Sponge Iron from 60,000 to 90,000 TPA, production of 72,000 TPA Billet by addition of 2x12 Ton Induction Furnace and 12 MW Captive Power Plant.
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/JH/IND/79533/2018
Project Cost 78.25 lacs
2.
S. No. in the schedule3(a) Metallurgical industries (ferrous & non ferrous)
Project Sector Industrial Projects - 1
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 1x100 TPD DRI Kiln – 30,000 TPA Sponge Iron 2x12 Ton Induction Furnace with CCM – 72000 TPA Billet Captive Power Plant (WHRB+AFBC) - 12 MW ha.
4.
New/Expansion/ModernizationExpansion
Proposal NumberIA/JH/IND/3779/2010
MoEFCC file number(Previous EC)J-11011/260/2009-IA.II(I)
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 60000 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectVillage: Ara Saru Bera Road, P.O. – Kuju, District- Ramgarh, State- Jharkhand-825 316
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.7, 88, 28, 28, 1/193, 1/193
Town / VillageVillage Ara Saru Bera Road P.O. Kuju
State of the projectJharkhand
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)JharkhandRamgarhPatratu
10.
Nearest railway station along with distance in kms Kuju Railway Station, 2.3 km in West km
Nearest airport along with distance in kms Birsa Munda Airport, Ranchi, ~50 km in SSW direction. km
11. Nearest Town/City/District Headquarters along with distance in kms Kuju , 1.5 km in WNW direction from plant site. km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) P.O.: Kuju Ramgarh, Jharkhand (JH), India (IN), Pin Code:- 825316
13. Name of the Applicant Mahabir
14. Registered Address Khata No:- 7,88,28,28,1/193,1/193, Aara Suru Bera Road,P.O- Kuju, District- Ramgarh, Jharkhand
15.
Address for correspondance:
Name of the Company SHRI RAM POWER AND STEEL PRIVATE LIMITED
Name of the Applicant Mahabir
Designation (Owner/ Partner/ CEO) Owner
Pin code 825316
E-mail mahabirprasadrunga54@gmail.com
Telephone No. 0124-4291036
Fax No. 0124-
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No The proposed project will be installed within the existing plant area of 4.96Ha., hence there is no temporary or permanent change in land use.
1.2 Clearance of existing land, vegetation and buildings? No Not required.
1.3 Creation of new land uses? No The proposed expansion project will be installed in the existing plant premises therefore there will be no new land use creation.
1.4 Pre-construction investigations e.g. bore houses, soil testing? No Not Required.
1.5 Construction works? Yes Construction work is required for the expansion project.
1.6 Demolition works? No No Demolition works is required.
1.7 Temporary sites used for construction works or housing of construction workers? No No temporary sites for housing of construction workers are required since the construction workers will be sourced from the nearby villages.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Building, structures or earthworks are required for expansion project.
1.9 Underground works including mining or tunnelling? No Not Applicable. Tunneling only for cabling work
1.10 Reclamation works? No Not Applicable
1.11 Dredging? Yes Not Applicable
1.12 Offshore structures? No Not Applicable
1.13 Production and manufacturing processes? Yes Production of Sponge iron through coal based Rotary Kiln process. Production of Liquid steel / Billets through Induction Furnaces and Billet Caster. Generation of Power through Waste Heart Recovery Boilers using sensible heat of DRI Gas and AFBC Boiler utilizing dolochar from DRI Kiln and coal
1.14 Facilities for storage of goods or materials? Yes Storage facilities are available for the existing plant operation. Additional storage facilities for storage of raw materials and shed for finished products will be created for the expansion project.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? No Treatment of Liquid Effluent • Neutralization Pit for DM Plant effluent Solid Waste Disposal • Utilization of Dolochar in DRI Kiln • Induction Furnace slag will be used for area development / landfilling after metal recovery • Iron Ore fines and Mill scale will be given to the outside Sinter Plant / Pallet Plant
1.16 Facilities for long term housing of operational workers? No Operational workers will be hired from nearby villages. No long term housing for operational workers, proposed.
1.17 New road, rail or sea traffic during construction or operation? No Not Required
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Not Required
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Not Required
1.20 New or diverted transmission lines or pipelines? No Not Required
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No Not Required
1.22 Stream crossings? No Not Required
1.23 Abstraction or transfers of water from ground or surface waters? Yes Total water requirement after the proposed expansion shall be 1245 KLD will be sourced from Damodar River.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No No change envisaged.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Material will be transported for construction and operational work. No transportation of personnel proposed. No decommissioning envisaged.
1.26 Long-term dismantling or decommissioning or restoration works? No No dismantling or decommissioning works required.
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No Not applicable.
1.28 Influx of people to an area in either temporarily or permanently? No Additional workforce will be hired from the nearby villages, hence no influx of people, temporary or permanent is expected
1.29 Introduction of alien species? No None
1.30 Loss of native species or genetic diversity? No No loss of native species or genetic diversity due to the project
1.31 Any other actions? No No
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No The expansion project will be executed within the existing premises so no additional land is acquired for the proposed project and therefore there will be no change in land use of the area.
2.2 Water (expected source & competing users) unit: KLD Yes Total water requirement for the project is 1245 KLD out of which 1119 KLD will be required for proposed expansion. The water will be sourced from river Damodar through surface pipelines after obtaining due permission from the concerned department.
2.3 Minerals (MT) Yes The details of raw materials required for the project are. Sponge Iron Unit Iron Ore- 1,44,000 TPA Non Coking Coal- 1,17,000 TPA Dolomite/ Limestone- 2,700 TPA
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes The construction material used during construction phase of the proposed project will be sourced from the local market.
2.5 Forests and timber (source – MT) No Not Applicable
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Power requirement: Existing – 0.50 MW Expansion – 11.30 MW Total – 11.80 MW Power will be sourced initially from DVC for construction/erection and preliminary work. Later on power will be sourced through the CPP as it will be commissioned simultaneously with the other units.
2.7 Any other natural resources (use appropriate standard units) No No other natural resources are used.
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No No hazardous substance as per MSIHC Rules will be used
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Not applicable
3.3 Affect the welfare of people e.g. by changing living conditions? Yes The proposed project shall improve the living conditions and welfare of the people.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No No applicable
3.5 Any other causes No No
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No Not Applicable
4.2 Municipal waste (domestic and or commercial wastes) Yes No housing colony proposed. For Municipal domestic waste Septic tank with Soak Pit proposed.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) No No Hazardous waste shall be generated from the project, except Used Oil, approx. 240 liters per annum Shall be sold to the registered recycler.
4.4 Other industrial process wastes Yes The solid waste generated during the operation phase are: Char-22500 TPA, Fine & Dust-6750 TPA, Fly ash-31800 TPA, Slag-15000 TPA, Bottom Ash-3825 TPA
4.5 Surplus product No None
4.6 Sewage sludge or other sludge from effluent treatment No Sewage sludge If any, shall be used as manure.
4.7 Construction or demolition wastes Yes Minimal quantity of Construction waste will be generated which will be used for landfilling and leveling.
4.8 Redundant machinery or equipment No No Redundant machinery.
4.9 Contaminated soils or other materials No No contamination of soil or other materials.
4.10 Agricultural wastes No Not Applicable.
4.11 Other solid wastes No No other solid waste generation
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Fossil fuel shall be used in Trucks used for transportation of raw materials and finished good. Emission contain PM, SO2, NOx and HC.
5.2 Emissions from production processes Yes Emissions from DRI Kilns. Emission contain PM, SO2, NOx Emissions from Induction Furnace, mostly contain dust.
5.3 Emissions from materials handling including storage or transport Yes Dust emission during transportation and storage.
5.4 Emissions from construction activities including plant and equipment Yes From construction equipment aided with fossil fuel (diesel) are Cranes, Compressor, Mortar mixing drums etc.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No The dust emissions generated from handling of construction materials are minimal in quantity. No odour problems.
5.6 Emissions from incineration of waste No Not applicable
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Not applicable
5.8 Emissions from any other sources No Not applicable
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes The major noise sources are Compressor, ID fans etc. Suitable control measures will be provided.
6.2 From industrial or similar processes Yes Major noise source from Industrial process are noise from Turbo-generator, Steam leakage, air leakage etc.
6.3 From construction or demolition Yes Noise due to operation of Cranes, Trucks, Dumpers, Construction machineries etc. The noise generated from the construction activities will be confined to the plant premises. The workers will be provided with suitable PPE’s to reduce the occupational noise.
6.4 From blasting or piling No Not Applicable.
6.5 From construction or operational traffic Yes Noise generated from constructional and operational traffic shall be limited to 85 dB (A).
6.6 From lighting or cooling systems No Not applicable
6.7 From any other sources No Not applicable
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials Yes Hazardous wastes (Used Oil) shall be suitably disposed-off through registered recyclers, as per Hazardous and Other Wastes (Management & Transboundary Movement) Rules, 2016 and subsequent amendments.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No No effluent discharge on land. ‘Zero liquid discharge (ZLD)’ shall be followed. Domestic waste water will be send to septic tank followed by soak pit.
7.3 By deposition of pollutants emitted to air into the land or into water No State of art pollution control facilities with adequate stack heights will be provided. Hence there is no risk of contamination of land or water from release of pollutants.
7.4 From any other sources No No
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No No long term built-up of pollutants.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No Not applicable
8.2 From any other causes No No
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No No such event is known to have occurred in the area. Area falls under Seismic Zone II as per Indian Standard Seismic Zoning Map.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
No Supporting facilities are available as it is an operating plant. No additional supporting facilities proposed. The development of the project does not envisage any impact on supporting facilities like road, power, housing, extractive or supply industries. The proposed project will have positive effect and enhance the growth of the region. The industry will provide employment to the locals and likely to improve the socio-economic status of the area.
9.2 Lead to after-use of the site, which could have an impact on the environment No No impact on environment is envisaged due to after use of the site.
9.3 Set a precedent for later developments Yes The proposed project will install state of art pollution control measures to reduce pollution and likely to set a precedent for later development using advanced control technologies.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No Not envisaged.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No None
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No No Reserve Forest within 15 km. Murpa Protected Forest at 1.5 km in North direction.
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No None
4 Inland, coastal, marine or underground waters No None
5 State, National boundaries No None
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No None
7 Defence installations No None
8 Densely populated or built-up area Yes Kuju at 1.5 km in WNW direction from plant site.
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Bal Vidya mandir at 2.2 km in North East Govt Hospital at Kuju, 1.5 km in WNW.
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No None
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No None
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No None Area comes under Seismic Zone-II
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
Additional Attachments, if any
Attached File
ADS Letter
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterReply of ADS for Shri Ram Power and Steel Pvt. Ltd. regarding DFO NOC. 30 Nov 2018
2.NADuring the deliberations, the project proponent informed that they have made request to DFO for clarification regarding involvement of forest land. The Committee also noted that project proponent has not made clear presentation regarding environment sensitivity of the project site, existing /proposed configuration in consonance with environment clearance accorded. Recommendations of the Committee: 15. After detailed deliberations, the Committee deferred the consideration of the proposal and advised the project proponent to submit clarification from the DFO regarding involvement of forest land for the further consideration of the proposal 12 Oct 2018
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantMahabir
DesignationOwner
Name of Company (Applicant Name should not be given here)SHRI RAM POWER AND STEEL PRIVATE LIMITED
AddressKhata No:- 7,88,28,28,1/193,1/193, Aara Suru Bera Road,P.O- Kuju, District- Ramgarh, Jharkhand
Print