APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Integrated Municipal Solid Waste Processing facility Rewari | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/HR/MIS/69625/2017 | Project Cost | 650 lacs | |
| 2. | |
S. No. in the schedule | 7(i) Common Municipal Solid Waste Management Facility (CMSWMF)
| Project Sector | INFRA-2 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 19 acres ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 197 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | Yes | d) | Inter-State boundaries and international boundaries | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Near Ramsinghpura Village Rewari | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | 00 | Town / Village | Village Ramsinghpura | State of the project | Haryana | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Haryana | Rewari | Rewari | | 10. | |
Nearest railway station along with distance in kms | Bawal railway station, 3.19 km | Nearest airport along with distance in kms | New Delhi Airport, 76 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Rewari , 5.7 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Rewari Municipal Council
Near Bharawas Gate, Rewari.
01274-225263 | | 13. | Name of the Applicant | Ajay | | 14. | Registered Address | Rewari Municipal council Near Bharawas Gate | | 15. | |
Address for correspondance: | Name of the Company | REWARI MUNICIPAL COUNCIL | Name of the Applicant | Ajay | Designation (Owner/ Partner/ CEO) | Engineer | Pin code | 123401 | E-mail | rewari2017@gmail.com | Telephone No. | 0141-4160568 | Fax No. | 0141- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | Total land = 19 acres
The project will change the land use, land cover or topography with respect to local land use as it was an barren land which will be converted into industrial land and will be developed into Integrated Municipal Solid Waste Management Facility. The project will be developed as in accordance with local development plan. | 1.2 | Clearance of existing land, vegetation and buildings? | No | NA | 1.3 | Creation of new land uses? | Yes | Barren land converted into industrial use.
Development of secured landfill facility Municipal Solid waste treatment | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Preliminary Survey shows that average quality of soil is available. Detailed Soil Investigation shall be done during EIA study | 1.5 | Construction works? | Yes | Construction of
• Intermediate storage
• Wheel wash facility
• Office building
• Approach and internal road
• Compound wall
• Secured landfill cell in phases
• Leachate well
• Ground water monitoring well | 1.6 | Demolition works? | No | NA | 1.7 | Temporary sites used for construction works or housing of construction workers? | Yes | Local laborers to be employed from nearby villages. If required make labor camp with basic amenities shall be set up within the site only. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | All buildings (i.e. Shed, Lab, Office etc.) are above ground except landfill cells, foundations and underground storage tank. | 1.9 | Underground works including mining or tunnelling? | Yes | NA | 1.10 | Reclamation works? | No | NA | 1.12 | Offshore structures? | No | NA | 1.13 | Production and manufacturing processes? | Yes | Detail process description is discussed in Pre-feasibility report | 1.14 | Facilities for storage of goods or materials? | Yes | MSW collected will be stored, segregated, processed and disposed by different means | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Detail disposal of solid waste is discussed in Pre-feasibility report | 1.16 | Facilities for long term housing of operational workers? | No | Priority to be given to local villagers | 1.17 | New road, rail or sea traffic during construction or operation? | Yes | Only Road traffic will increase. Traffic due to transportation of construction material during construction phase, during nonpeak, day hours of approximately 5 trucks.
During operation phase:
Approximately 20 trucks.
Increase in Vehicular traffic due to commute of employees and workers during construction and operation phase. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Existing infrastructure is sufficient to cater the extra traffic load due to the proposed project. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | NA | 1.20 | New or diverted transmission lines or pipelines? | No | NA | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | NA | 1.22 | Stream crossings? | No | NA | 1.23 | Abstraction or transfers of water from ground or surface waters? | No | Water shall be available from Municipal Corporation Rewari. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | NA | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | Laborers and raw material will be transported via the existing Infrastructure | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not Applicable. Closure of landfill cell at end as per CPCB guidelines. Green belt/garden will be developed | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | NA | 1.28 | Influx of people to an area in either temporarily or permanently? | No | Priority will be given to local area people | 1.29 | Introduction of alien species? | No | NA | 1.30 | Loss of native species or genetic diversity? | No | NA | 1.31 | Any other actions? | No | NA | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | Barren land | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Construction Phase: 8 KLD
Source: Municipal Corporation of Rewari
Operation Phase: 80.06 KLD
Source: Ground water / Treated sewage from Municipal Corporation of Rewari | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Cement, Steel, Rocks and aggregates, Sand, Geo Membrane Stone, Aggregate, Steel, Cement
Source: Local Supplier | 2.5 | Forests and timber (source – MT) | No | NA | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | 1 D.G set of 250 KVA will be utilized for power during construction phase. During operation phase 250KW power will be taken from of State Electricity Board and for emergency 1 D.G set of 250 KVA will be utilized as backup. | 2.7 | Any other natural resources (use appropriate standard units) | No | NA | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | Spent Oil from DG Set 300 Liters/Year.
Different category of incinerable & Landfillable hazardous waste will be handled at site As per
Hazardous Waste management and Handling Rules 2008 and amendments thereafter | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | NA | 3.3 | Affect the welfare of people e.g. by changing living conditions? | No | Improved living condition by direct & indirect employment. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | NA | 3.5 | Any other causes | No | NA | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | All the excavated material generated out of foundation excavation will be used for construction of embankment of the cell. | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | The Municipal solid waste handled during operation phase is expected to be 197 TPD in 2017, 236 TPD in 2025 and 283 TPD in 2035. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Used Oil (Category: 5.1) will be generated from MSW site. Most of the oil will be utilized in greasing etc. of machineries and balance which shall be sent to authorized recyclers. | 4.4 | Other industrial process wastes | No | NA | 4.5 | Surplus product | No | NA | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | 6 Kg/day will be generated in Leachate & Effluent treatment plant which will be disposed off in the landfill after dewatering | 4.7 | Construction or demolition wastes | Yes | The construction waste will consist of construction debris along with cement bags, steel in bits and pieces, insulating and packaging materials etc. Cement bags, waste paper and cardboard packing material will be sold off to recyclers. Unusable steel scrap will also be collected at site and sold to recyclers | 4.8 | Redundant machinery or equipment | No | NA | 4.9 | Contaminated soils or other materials | No | NA | 4.10 | Agricultural wastes | No | NA | 4.11 | Other solid wastes | No | NA | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Not envisaged except for movement of vehicles for transporting waste to site. | 5.2 | Emissions from production processes | Yes | Air emissions will be generated from production process based on RDF. The same will be treated as per the SPCB/CPCB norms using flue gas cleaning system before its release in environment. | 5.3 | Emissions from materials handling including storage or transport | No | NA | 5.4 | Emissions from construction activities including plant and equipment | Yes | Fugitive emissions during unloading of construction material, concrete mixers etc. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust and Odour will be generated during transportation and handling of Municipal solid waste. Same will be kept under control by water spraying, odour control measures and other methods. | 5.6 | Emissions from incineration of waste | No | NA | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | NA | 5.8 | Emissions from any other sources | Yes | D. G Emission | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Increase in noise level due to the movement of vehicles and construction machinery | 6.2 | From industrial or similar processes | Yes | Noise will be generated during MSW processing but same will be kept as per noise limitation of SPCB. | 6.3 | From construction or demolition | Yes | Minor increase in noise due to transportation of construction material | 6.4 | From blasting or piling | No | NA | 6.5 | From construction or operational traffic | Yes | Minor increase due to transportation activity | 6.6 | From lighting or cooling systems | No | NA | 6.7 | From any other sources | No | NA | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | Spent oil will be stored in container at a designated area and will be sent to authorized recycle As Suggested in Hazardous Waste management and Handling Rules 2016, hence impact is not envisaged | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | There will be no discharge of waste water from the proposed MSW processing facility to water or the land.
Leachate, effluent and sewage will be collected and treated in treatment plant for safe disposals as per CPCB/SPCB norms. | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | NA | 7.4 | From any other sources | No | NA | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | NA | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | • Hazards pertaining to fires in project/plant area
• Fire in diesel storage areas, garbage storage areas and disposal areas
• Proper fire management systems will be installed | 8.2 | From any other causes | Yes | During Construction phase there are possibilities of accidents, fall, cut or Burn injuries during cutting and welding activities. During operation phase possibility of accidents due to fire hazard may occur. Same will be addressed as per norms. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | The project fall under seismic zone IV | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| No | This is a new project; The existing infrastructure around the project site will be used. The effluent treatment plant will be developed within the plant premises for the treatment of leachate and sewage. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | Yes | Sanitary Land filling site shall be capped as per the MSW rules and other statutory norms of state. | 9.3 | Set a precedent for later developments | Yes | Integrated MSW processing facility and Waste to Compost plant with Sanitary Land fill will reduce the burden of MSW and only processing inerts/rejects will be disposed. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | NA | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | NA | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | No | NA | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | NA | 4 | Inland, coastal, marine or underground waters | No | NA | 5 | State, National boundaries | No | Inter State boundary of Haryana and Rajasthan lies at a distance of 2.23 km from project site. | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | NA | 7 | Defence installations | No | NA | 8 | Densely populated or built-up area | Yes | Rewari lies at a distance of 5.7 km from project site. | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Rewari lies at a distance of 5.7 km from Integrated MSW Processing facility. | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | NA | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | NA | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | NA | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | | Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | EDS Reply as per 32nd EAC Meeting held on 2nd & 4th July 2018. | 11 Feb 2019 | 2. | NA | Kindly see the final minutes of 32nd meeting of EAC (Infra-2) | 16 Jul 2018 | 3. | ADS Reply Letter | 24th & 30th EAC Meeting (EDS Reply along with Form-1) | 21 May 2018 | 4. | NA | Kindly see the final minutes. | 03 May 2018 | 5. | ADS Reply Letter | Form-1 | 29 Mar 2018 | 6. | NA | as per 24 EAC minutes | 07 Nov 2017 | | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Ajay | Designation | Engineer | Name of Company (Applicant Name should not be given here) | REWARI MUNICIPAL COUNCIL | Address | Rewari Municipal council Near Bharawas Gate |
|
|