S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Installation of 6 no. Material Ropeways for the construction of Chanju-III
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/HP/MIS/59995/2016
Project Cost 2340.00 lacs
2.
S. No. in the schedule7(g) Aerial ropeways
Project Sector INFRA-2
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled As per Techno Feasibility Study Report attached ha.
4.
New/Expansion/ModernizationNew
5. Existing Capacity/Area etc.  ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectVillage Dantoi, Tehsil Churah, Distt. Chamba
Shape of the project landStrip
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.Platform No.1: 242/2,5/1,5/4 =0.3034 ha Platform No.2: 46/1,242/1,5/5 =0.1780 ha Platform No.3: 39/1,38/1,244/1,5/9 =0.1659 ha Platform No.4: 218/1,5/15,5/16 =0.2346 ha Platform No.5: 346/28/1,5/19,5/22 =0.3804 ha Platform No.6: 591/1,894/882/6,797/1 =0.3723 Total of Platform Area = 1.6346 ha For Ropeways area = 2.088 ha Total Forest Area Required = 3.7226 ha
Town / VillageVillage Dantoi, Tehsil Chaurah, Distt. Chamba
State of the projectHimachal Pradesh
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)Himachal PradeshChambaChurah/Chamba
10.
Nearest railway station along with distance in kms Pathankot, 190 km
Nearest airport along with distance in kms Kangra Airport, 210 km
11. Nearest Town/City/District Headquarters along with distance in kms Chamba , 110 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given)
13. Name of the Applicant Narender
14. Registered Address Himfed Bhawan,Panjari,Below Old MLA Quarters,Bypass Raod,Shimla
15.
Address for correspondance:
Name of the Company HIMACHAL PRADESH POWER CORPORATION LIMITED
Name of the Applicant Narender
Designation (Owner/ Partner/ CEO) General Manager
Pin code 176312
E-mail dgmrcp@gmail.com
Telephone No. 1896-242042
Fax No. 1896-01896242041
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . NIL
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?Yes
StatusApplication for Forest Clearance yet to be submitted
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No
1.2 Clearance of existing land, vegetation and buildings? No The Forest Land to be diverted has no buildings, roads, power and water sully lines.No thick vegetation is there
1.3 Creation of new land uses? No The material ropeways are to be installed for temporary use only.It is only for the transportation of machinery etc.for the construction of Chanju-III 48MW HEP
1.4 Pre-construction investigations e.g. bore houses, soil testing? No Techno feasibility study has been carried out by M/s Conveyor and Ropeways Services Pvt. Ltd. Kolkata
1.5 Construction works? No
1.6 Demolition works? No
1.7 Temporary sites used for construction works or housing of construction workers? Yes Near existing village Dantoi
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations No
1.9 Underground works including mining or tunnelling? No
1.10 Reclamation works? No
1.11 Dredging? No
1.12 Offshore structures? No
1.13 Production and manufacturing processes? No
1.14 Facilities for storage of goods or materials? Yes Temporary Storage facilities would be erected in the nearest village Dantoi
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Disposal of solid waste or liquid effluents would be strictly implemented by providing proper treatment
1.16 Facilities for long term housing of operational workers? No
1.17 New road, rail or sea traffic during construction or operation? No
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No
1.20 New or diverted transmission lines or pipelines? No
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No
1.22 Stream crossings? Yes Chanju Nalla
1.23 Abstraction or transfers of water from ground or surface waters? No
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes It would be carried out by the Contractor
1.26 Long-term dismantling or decommissioning or restoration works? No
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No
1.28 Influx of people to an area in either temporarily or permanently? Yes Temporarily
1.29 Introduction of alien species? No
1.30 Loss of native species or genetic diversity? No It is mentioned that waste disposal, disposal of sewage, protection of water bodies, forests and wildlife etc. would be strictly implemented
1.31 Any other actions? No
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No
2.2 Water (expected source & competing users) unit: KLD Yes The water required during peak stage of construction for 50-60 workforce is about 60KLD
2.3 Minerals (MT) No
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) No
2.5 Forests and timber (source – MT) No
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes 50KW of Power required during operation phase. For labor, free LPG/kerosene would be provided by the contractor.2DG sets of 25KVA would be installed during construction phase
2.7 Any other natural resources (use appropriate standard units) No
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No
3.3 Affect the welfare of people e.g. by changing living conditions? Yes Living conditions will definitely improve after construction of Chanju-III HEP
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No
3.5 Any other causes No
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No
4.2 Municipal waste (domestic and or commercial wastes) No
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) No
4.4 Other industrial process wastes No
4.5 Surplus product No
4.6 Sewage sludge or other sludge from effluent treatment Yes Proper arrangements will be provided to disposed off the sewage generated
4.7 Construction or demolition wastes No
4.8 Redundant machinery or equipment No
4.9 Contaminated soils or other materials No
4.10 Agricultural wastes No
4.11 Other solid wastes No
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes DG sets will be installed as standard power supply and will be provided with acoustic enclosures to minimize the emmissions
5.2 Emissions from production processes No
5.3 Emissions from materials handling including storage or transport No
5.4 Emissions from construction activities including plant and equipment No
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No
5.6 Emissions from incineration of waste No
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No
5.8 Emissions from any other sources No
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers No
6.2 From industrial or similar processes No
6.3 From construction or demolition No
6.4 From blasting or piling No
6.5 From construction or operational traffic No
6.6 From lighting or cooling systems No
6.7 From any other sources No
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No
7.3 By deposition of pollutants emitted to air into the land or into water No
7.4 From any other sources No
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No
8.2 From any other causes No
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No Chamba District falls in earthquake Zone-V Necessary precautions during construction design of the project will be taken
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes Proposed Ropeways would help in saving many trees which would be felled in case of road construction.As the area is hilly and the construction of the road is not feasible, there is an last option to provide ropeways. This would have positive impact on environment
9.2 Lead to after-use of the site, which could have an impact on the environment No
9.3 Set a precedent for later developments No
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No
4 Inland, coastal, marine or underground waters No
5 State, National boundaries No
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No
7 Defence installations No
8 Densely populated or built-up area No
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) No
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) NIL
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantNarender
DesignationGeneral Manager
Name of Company (Applicant Name should not be given here)HIMACHAL PRADESH POWER CORPORATION LIMITED
AddressHimfed Bhawan,Panjari,Below Old MLA Quarters,Bypass Raod,Shimla