APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s GUJARAT BHAL CONSTRUCTION LIMITED
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/GJ/NCP/67353/2017
Project Cost 16029 lacs
2.
S. No. in the schedule7(c) Industrial estates/ parks/ complexes/ areas, export processing Zones
Project Sector INFRA-1
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 100,18,301 square meter i.e 2504 acre ha.
4.
New/Expansion/ModernizationNew
5. Existing Capacity/Area etc. 10018301 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectDHOLKA
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.VARIOUS SURVEY NUMBERS OF BORU,BHOLAD AS PER FORM 1
Town / VillageDholka
State of the projectGujarat
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)GujaratAhmedabadDholka
10.
Nearest railway station along with distance in kms Dholka, 12 km
Nearest airport along with distance in kms Ahmedababd, 23 km
11. Nearest Town/City/District Headquarters along with distance in kms ahmedabad , 30 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) not applicable
13. Name of the Applicant udayan
14. Registered Address 231,Platinum Plaza,Opp IOC petrol Pump,Satya Marg,JUdges Bunglow,Bodakdev: 380051
15.
Address for correspondance:
Name of the Company UDAYAN
Name of the Applicant udayan
Designation (Owner/ Partner/ CEO) engineer
Pin code 380054
E-mail ikagzigpcb@gmail.com
Telephone No. 79-40025663
Fax No. 79-
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet Yes
Uploaded detailsAnnexure-Uploaded details
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes this is an area development project
1.2 Clearance of existing land, vegetation and buildings? Yes As per form 1 and project summary
1.3 Creation of new land uses? Yes As per form 1 and project summary
1.4 Pre-construction investigations e.g. bore houses, soil testing? No As per form 1 and project summary
1.5 Construction works? No As per form 1 and project summary
1.6 Demolition works? No As per form 1 and project summary
1.7 Temporary sites used for construction works or housing of construction workers? No As per form 1 and project summary
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes As per form 1 and project summary
1.9 Underground works including mining or tunnelling? No As per form 1 and project summary
1.10 Reclamation works? No As per form 1 and project summary
1.11 Dredging? No As per form 1 and project summary
1.12 Offshore structures? No As per form 1 and project summary
1.13 Production and manufacturing processes? Yes As per form 1 and project summary
1.14 Facilities for storage of goods or materials? Yes As per form 1 and project summary
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes As per form 1 and project summary
1.16 Facilities for long term housing of operational workers? Yes As per form 1 and project summary
1.17 New road, rail or sea traffic during construction or operation? Yes As per form 1 and project summary
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? Yes As per form 1 and project summary
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No As per form 1 and project summary
1.20 New or diverted transmission lines or pipelines? No As per form 1 and project summary
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No As per form 1 and project summary
1.22 Stream crossings? No As per form 1 and project summary
1.23 Abstraction or transfers of water from ground or surface waters? Yes As per form 1 and project summary
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No As per form 1 and project summary
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes As per form 1 and project summary
1.26 Long-term dismantling or decommissioning or restoration works? No As per form 1 and project summary
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No As per form 1 and project summary
1.28 Influx of people to an area in either temporarily or permanently? Yes As per form 1 and project summary
1.29 Introduction of alien species? No As per form 1 and project summary
1.30 Loss of native species or genetic diversity? No As per form 1 and project summary
1.31 Any other actions? No As per form 1 and project summary
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes As per form 1 and project summary
2.2 Water (expected source & competing users) unit: KLD Yes As per form 1 and project summary
2.3 Minerals (MT) No As per form 1 and project summary
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes As per form 1 and project summary
2.5 Forests and timber (source – MT) No As per form 1 and project summary
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes as per form 1
2.7 Any other natural resources (use appropriate standard units) Yes as per form 1
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes as per form1
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No NA
3.3 Affect the welfare of people e.g. by changing living conditions? Yes NA
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No NA
3.5 Any other causes No NA
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes Yes As per form 1 and project summary
4.2 Municipal waste (domestic and or commercial wastes) Yes As per form 1 and project summary
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes As per form 1 and project summary
4.4 Other industrial process wastes Yes As per form 1 and project summary
4.5 Surplus product Yes As per form 1 and project summary
4.6 Sewage sludge or other sludge from effluent treatment Yes As per form 1 and project summary
4.7 Construction or demolition wastes No NA
4.8 Redundant machinery or equipment Yes As per form 1 and project summary
4.9 Contaminated soils or other materials No NA
4.10 Agricultural wastes No NA
4.11 Other solid wastes No NA
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes As per form 1 and project summary
5.2 Emissions from production processes Yes As per form 1 and project summary
5.3 Emissions from materials handling including storage or transport Yes As per form 1 and project summary
5.4 Emissions from construction activities including plant and equipment Yes As per form 1 and project summary
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No NA
5.6 Emissions from incineration of waste No As per form 1 and project summary
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) Yes NA
5.8 Emissions from any other sources No NA
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes As per form 1 and project summary
6.2 From industrial or similar processes Yes As per form 1 and project summary
6.3 From construction or demolition Yes As per form 1 and project summary
6.4 From blasting or piling No NA
6.5 From construction or operational traffic Yes As per form 1 and project summary
6.6 From lighting or cooling systems Yes As per form 1 and project summary
6.7 From any other sources No NA
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials Yes As per form 1 and project summary
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No As per form 1 and project summary
7.3 By deposition of pollutants emitted to air into the land or into water No As per form 1 and project summary
7.4 From any other sources No As per form 1 and project summary
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No NA
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No As per form 1 and project summary
8.2 From any other causes No As per form 1 and project summary
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No As per form 1 and project summary
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes As per form 1 and project summary
9.2 Lead to after-use of the site, which could have an impact on the environment Yes As per form 1 and project summary
9.3 Set a precedent for later developments Yes As per form 1 and project summary
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No NA
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No NA
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No NA
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No NA
4 Inland, coastal, marine or underground waters No NA
5 State, National boundaries No NA
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No NA
7 Defence installations No NA
8 Densely populated or built-up area No NA
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) No NA
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No NA
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No NA
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No NA
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
Additional Attachments, if any
Attached File
EDS querry reply
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAThe correction have been made as per the instruction received 13 Sep 2017
2.NAplease upload and submit these below information as separate file 1. In Form-1, area is mentioned as Zero (0). Please indicate total area of the proposed Industrial Estate. 2. Please furnish the list of A category and B category industries, as per the EIA notification proposed in industrial area separately. 12 Sep 2017
3.NAThe correction have been made as per the instruction received 23 Aug 2017
4.NA1. In Form-1, area is mentioned as Zero (0). Please indicate total area of the proposed Industrial Estate. 2. Please furnish the list of A category and B category industries, separately. 22 Aug 2017
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of Applicantudayan
Designationengineer
Name of Company (Applicant Name should not be given here)UDAYAN
Address231,Platinum Plaza,Opp IOC petrol Pump,Satya Marg,JUdges Bunglow,Bodakdev: 380051
Print