APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Greenfield Common Hazardous Waste Treatment, Storage and Disposal Facility (CHWIF) cum Incineration facility at Plot No. 48, Village Rampara, Tehsil Chotila, Dist. Surendranagar, Gujarat. | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/GJ/MIS/95505/2019 | Project Cost | 2500 lacs | |
| 2. | |
S. No. in the schedule | 7(d) Common hazardous waste treatment, storage and disposal facilities (TSDFs)
| Project Sector | INFRA-2 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | Total Area: 72,877 sq.m (Total Incinerator Area: 4232 sq.m + Total TSDF Area: 68645 sq.m) ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 7.2 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Plot No 48, Village Rampara, Chotila, District Surendranagar, Gujarat | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | Survey No. 48, near Village Rampara, Taluka Chotila, District Surendranagar | Town / Village | Rampara Village | State of the project | Gujarat | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Gujarat | Surendranagar | Chotila | | 10. | |
Nearest railway station along with distance in kms | Than railway station, 10.29 km | Nearest airport along with distance in kms | Rajkot Airport, 45.84 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Chotila , 6.96 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Gram Panchayat Rupavati (Rampara), Taluka Chotila, Dist. Surendranagar, Gujarat. | | 13. | Name of the Applicant | Reenaben | | 14. | Registered Address | 8, Madhavvatika, Above Golden Super Market, Limbudiwadi, Rajkot | | 15. | |
Address for correspondance: | Name of the Company | VARNI ENVIRO CARE PRIVATE LIMITED | Name of the Applicant | Reenaben | Designation (Owner/ Partner/ CEO) | Director | Pin code | 360001 | E-mail | ashirwadpm@gmail.com | Telephone No. | 0281-2586416 | Fax No. | 0281- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | Yes | Uploaded details | Annexure-Uploaded details | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | No | Existing land use is fallow land.
Site Location Map is shown as Annexure 2. The project site on Google Satellite Image and Topo sheet is presented at Annexure 3. | 1.2 | Clearance of existing land, vegetation and buildings? | No | Not Applicable, as existing land is a fallow land. | 1.3 | Creation of new land uses? | Yes | Agricultural fallow land will be converted into industrial use for Disposal of Hazardous waste in a confined area along with Industrial plant for Liquid + Solid Waste Incineration facility. There will be development of secured landfill site with common hazardous waste incineration plant in the area. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | No | Geotechnical investigations like soil testing and similar activities will be conducted prior to construction. | 1.5 | Construction works? | Yes | Major construction work will involve civil works of Incineration Facility, Solid and Liquid Storage Areas, Weighbridge, Admin, Internal Roads, Utility areas, Green Belt and Landfill site etc.
Site Layout Map is presented at Annexure 4. Area Break Up of total site area is presented at Annexure 5. | 1.6 | Demolition works? | No | Demolition works are not envisaged since there is no existing infrastructure at the proposed site. | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | Most of the construction workers will be hired locally and workers housing will be provided in temporary structures. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | All building will be above ground except landfill cell, foundations and underground storage tank. | 1.9 | Underground works including mining or tunnelling? | No | Not Applicable.
No mining activity is envisaged. | 1.10 | Reclamation works? | No | Not Applicable. | 1.11 | Dredging? | No | Not Applicable. | 1.12 | Offshore structures? | No | Not Applicable. | 1.13 | Production and manufacturing processes? | No | Not Applicable since the proposed facility is TSDF and Incineration of Hazardous Solid and Liquid Waste. The description of TSDF and Incineration is given in Annexure 7. | 1.14 | Facilities for storage of goods or materials? | Yes | Separate storage areas will be provided for solid and liquid waste as well as other materials as per requirement in their individual areas earmarked on the site as per layout plan. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Solid Waste:
Incinerator ash will be disposed into adjoining landfill.
Liquid Waste:
Leachate from the landfill site will be disposed off to Spray Dryer / Quencher System.
The scrubber media discarded occasionally, will be disposed to ETP and then to Spray Dryer.
The domestic waste water, scrubber waters and other washing waters will be treated in ETP and treated outlet from ETP will be sent to spray dryer. | 1.16 | Facilities for long term housing of operational workers? | No | No Long term Housing is envisaged in the project. Mostly local people will be hired for operation of the various plants and equipment’s. | 1.17 | New road, rail or sea traffic during construction or operation? | Yes | There will be marginal increase in road traffic for transportation of waste to the site. There will be no increase in rail and sea traffic. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | Yes | Depending upon the site required infrastructure will be developed. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Closure or diversion of existing routes in traffic movement is not foreseen. | 1.20 | New or diverted transmission lines or pipelines? | No | Not envisaged in the project | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not envisaged in the project | 1.22 | Stream crossings? | No | There is no any stream crossing through the project site. | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Source of water – Borewell. Necessary CGWA permission will be taken for abstraction of ground water resources. The area falls under safe zone as per Ground Water Availability. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | Not Applicable. | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | Construction phase
Transport of personnel: 100
These workers will not require any special transport facilities since they will be hired locally.
Operation Phase
Transport of personnel: 50 employees will be working for the proposed project and they will be locally hired. So no special transport facility will be provided for local persons. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not Applicable | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not Applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | Since local people will be hired, influx of people will be minimum.
Construction Phase - 100 workers
Operation Phase - 50 workers | 1.29 | Introduction of alien species? | No | No | 1.30 | Loss of native species or genetic diversity? | No | No | 1.31 | Any other actions? | No | No | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | The site is Agriculture fallow land. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Total water demand will be 254 KLD, which will be met with from borewell. ETP Treated waters will be send to spray dryer.
Water Consumption and Waste Water Generation, Water Balance diagram is presented at Annexure 8. | 2.3 | Minerals (MT) | No | Not applicable | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Construction materials like stones, aggregates, sand, bricks, steel, cement, rubble, etc. will be procured from the local market of the region. | 2.5 | Forests and timber (source – MT) | No | Not Applicable | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Power requirement of 1000 KVA at site will be supplied by MGVCL
One DG set of will be installed for emergency backup supply.
Capacity of DG Sets as below:
1000 KVA (1 No.)
Fuel Requirement:
250 lit/hr. of HSD will be required for D.G set.
450 Kg/Hr. HSD / FO will be required for Process. | 2.7 | Any other natural resources (use appropriate standard units) | No | Not Applicable | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | Different category of incinerable & landfillable hazardous waste will be handled at site as per Hazardous and Other Wastes (Management and Transboundary Movement) Amendment Rules, 2016. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | No change or occurrence of disease vectors. | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | The employment opportunities generated due to the proposed project will improve the living standard positively. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | - | 3.5 | Any other causes | No | - | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | No mining of area is anticipated. Only filling and leveling / grading of site will be carried out. | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | MSW and Recyclables will be sent to approved recyclers. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Details of Hazardous Waste Generation and Management facility is given in Annexure 10 | 4.4 | Other industrial process wastes | No | No industrial process waste is envisaged in the project. | 4.5 | Surplus product | No | No Surplus product is envisaged in the project. | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Domestic Sewage along with other washings will be treated in ETP and will be sent to Spray Dryer. Details of Waste Water Treatment Facility is presented in Annexure 9. | 4.7 | Construction or demolition wastes | Yes | All structures will be newly constructed. There is no demolition activity on site. Minor construction waste generated during construction activity on site will be managed as per the C & D Waste Rules by the Construction company. | 4.8 | Redundant machinery or equipment | No | Not Applicable | 4.9 | Contaminated soils or other materials | No | No Contaminated soils or other material is envisaged as the site is a vacant land. | 4.10 | Agricultural wastes | Yes | Cleaning and clearing of the site will be disposed of as MSW | 4.11 | Other solid wastes | No | Incinerator Ash will be disposed of in the in-house secured landfill cell. | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Construction phase
Emission of fossil fuels shall be from use of Construction machineries, vehicles.
Operation Phase
Adequate stack height is provided to flue gas stacks of D.G. Set and Incinerator. Stack emission quality will be maintained as per the GPCB norms.
Stack details are presented in Annexure 12.
Fuel Consumption Details are presented in Annexure 11. | 5.2 | Emissions from production processes | Yes | Gaseous emissions of PM, Pb, SO2, CO, VOC, NH3 and NOx as per Air Quality Standards are envisaged. | 5.3 | Emissions from materials handling including storage or transport | No | Adequate cover will be provided in storage area and on trucks for transportation of materials / waste to the site and out of the site. | 5.4 | Emissions from construction activities including plant and equipment | Yes | During construction activities, emissions will be in the form of dust. Suitable dust suppression techniques such as waster sprinkling will be taken at these times as relevant. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Obnoxious odour of solid and liquid waste will be limited to plant area is envisaged. Odor Control Plan shall be made and followed. | 5.6 | Emissions from incineration of waste | Yes | Emission of PM, Pb, SO2, CO, VOC, NH3, NOx are envisaged from Incinerator. Online monitoring system will be installed and emission parameters will be continuously monitored. The Incinerator design is made in such a way that emissions are within the permissible limits as laid by Air quality standards. | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not Applicable | 5.8 | Emissions from any other sources | No | Not Applicable | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | No | Not Applicable | 6.2 | From industrial or similar processes | Yes | Noise from Operation of D.G. Set and Pumps, Incineration system etc. This will be controlled by periodic maintenance of equipment’s. In Operational areas PPEs will be used during operations. | 6.3 | From construction or demolition | Yes | Temporary noise generation during construction activities. | 6.4 | From blasting or piling | No | Not Applicable | 6.5 | From construction or operational traffic | Yes | Minor increase due to vehicular movement during construction and operation phase. | 6.6 | From lighting or cooling systems | No | Not Applicable | 6.7 | From any other sources | No | Not Envisaged | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | Occasional spills may occur. These will not affect water or land because of appropriate flooring & presence of spill control procedures in place in entire plant premises. Moreover all of the Hazardous wastes will be disposed of as per guidelines of CPCB/SPCB/MOEF. All spillages will be arrested and will be taken to ETP for treatment before utilization in Spray Dryer. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | Sewage will also be treated in ETP along with other liquid waste.
The leachate generated from landfill will be treated in ETP and sent to spray dryer. | 7.3 | By deposition of pollutants emitted to air into the land or into water | Yes | Shall be provided with EIA report after air dispersion modeling using site specific meteorological data. | 7.4 | From any other sources | No | - | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Release of pollutants in air will be within acceptable limits of SPCB as pollution control equipment’s will be provided. | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | Occurrence of spillage is envisaged during storage, handling and charging of waste material in various operations of facilities. The storages shall be designed as Hazardous Storage Guidelines. The plant shall have an Onsite & Offsite Emergency Plan. | 8.2 | From any other causes | Yes | Common risks in factories such as Electric Shock, Hit by Objects, Fall/Slips, Hot Work such as Welding and Cutting & during maintenance activities. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | Yes | Project area is categorized in the seismic zone III, which is classified as Moderate Damage Risk Zone. The structure Design will be as per Codes to negate the threat of environmental and other damages. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | The project will indirectly lead to industrial growth in the region and also facilitate other industries in the Industrial Belts of Central Saurashtra, Ahmedabad and other Industrial areas of Gujarat State due to availability of a secured landfill and incineration facility for safe disposal of industrial hazardous waste from the nearby Industries. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not Applicable | 9.3 | Set a precedent for later developments | No | - | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | - | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | No such areas within 15 km of site. | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Water Body:
Bhogava River: 3.2 Km, SE.
Maha River: 4.3 Km, NE.
Machhon Nadi: 9.05 Km, W.
Maha Nadi Reservoir: 6.27 Km, N.
Nava Pond: 2.6 Km, SE.
Nearest Forest:
Rampara Reserve Forest: 0.3 Km, NW.
Devsar Reserve Forest: 4.60 Km, ENE.
Vavdi Reserve Forest: 7.33 Km, NE.
Kalyani Reserve Forest: 7.81 Km, NW.
Lakhamachi Reserve Forest: 8.64 Km, NW.
Mandav Reserve Forest – 2.5 km, NNW | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | No such areas within 15 km of site. | 4 | Inland, coastal, marine or underground waters | Yes | Water Body:
Bhogava River: 3.2 Km, SE.
Maha River: 4.3 Km, NE.
Machhon Nadi: 9.05 Km, W.
Maha Nadi Reservoir: 6.27 Km, N.
Nava Pond: 2.6 Km, SE. | 5 | State, National boundaries | No | No | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | Road ways:
NH-8A: 6.34 Km, S.
SH-119: 2.7 Km, E.
SH-113: 9.61 Km, N. | 7 | Defence installations | No | No such area within 10 Km from Project Site. | 8 | Densely populated or built-up area | Yes | Chotila: 6.96 Km, S | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | School:
Shri N.N Shah High School: 5.96 Km, SSE.
Primary School Sangani: 6.76 Km, SE.
Hospital:
Sarvajanik Hospital: 6.96 Km, S.
Ochwani Hospital: 7.44 Km, S. | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | Not Applicable | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | Not Applicable | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | Yes | As per the geological map published by Geological survey of India, The area comes under the moderate risk zone (Zone-III) of the Seismic Zonation. | | (IV) | Proposed Terms of Reference for EIA studies | | Additional Attachments, if any |
---|
Attached File |
---|
ADS Letter |
| | Essential Detail Sought : NIL | | Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Uploaded the reply of query raised during EAC (Infra-2) meeting held on dated 26th March, 2019:
1. Revised Form I [mentioning complete details of facilities: Total Capacity of TSDF (3,25,000 MT Capacity), 7 years of Life span]
2. Detailed Site Alternative. (As per the meeting, Site 2 located near Surai was suggested by EAC Committee based on CPCB Criteria of Site selection/knock out criteria).
Kindly consider the proposal and do the needful. | 18 Dec 2019 | 2. | NA | Kindly see the final minutes of 39th meeting of EAC (Infra-2)
| 05 Apr 2019 | | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Reenaben | Designation | Director | Name of Company (Applicant Name should not be given here) | VARNI ENVIRO CARE PRIVATE LIMITED | Address | 8, Madhavvatika, Above Golden Super Market, Limbudiwadi, Rajkot |
|
|