APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Naredi-Mota-Nandra Bauxite Mining Project (Mine Lease Area – 169.5968 Ha. & Production Capacity 35,000 TPA) at Village: Naredi & Mota Nandra, Tehsil Abdasa, District Kutch, Gujarat, Regarding Validation of Environmental Clearance under the provision of EIA Notification 2006 and in compliance of MoEF&CC Notification dated 06th April 2018 | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/GJ/MIN/80946/2018 | Project Cost | 61 lacs lacs | |
| 2. | |
S. No. in the schedule | 1(a) Mining of minerals
| Project Sector | Non-Coal Mining | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 169.5968 ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 169.5968 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Village - Naredi & Mota Nandra | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | Naredi; 437- 96, 140, 141/1, 141/2, Mota Nandra- 36- 38, 41, 44, 91, 94, 95, 96A, 96B- 31, 32, 34, 35 | Town / Village | Village Naredi- Mota -Nandra | State of the project | Gujarat | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Gujarat | kutch | Abdasa | | 10. | |
Nearest railway station along with distance in kms | Deshalpar, 24.32 KM, ENE km | Nearest airport along with distance in kms | Air force Station, 49.70 KM km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Nearest Town :Deshalpar , 24.24 km,E km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Village Panchayat- Village- Naredi & Mota Nandra, Tehsil-Abdasa; Dist-Kutch (Bhuj); Gujarat- PIN- 370650
Zila Parishad- Bhuj, Gujarat.
Municipality- Bhuj, Tehsil- Abdasa, Dist–Kutch (Bhuj), Gujarat, PIN- 370650 | | 13. | Name of the Applicant | Chirag | | 14. | Registered Address | KHANIJ BHAVAN
132 FEET RING ROAD
NEAR UNIVERSITY RING ROAD
VASTRAPUR AHMEDABAD | | 15. | |
Address for correspondance: | Name of the Company | GUJARAT MINERAL DEVELOPMENT CORPORATION LIMITED | Name of the Applicant | Chirag | Designation (Owner/ Partner/ CEO) | General Manager (Environment) | Pin code | 380052 | E-mail | env@gmdcltd.com | Telephone No. | 79-27912322 | Fax No. | 79-07927913038 | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | | 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | Out of total 169.5968 Ha. ML area. Presently, the land use scenario is about area under
1. Overburden Soil Dump-0
2. Waste Dump -0.60
3. Excavation (Voids only) - 5.12
4. Roads/ mine road -0.30
5. Infrastructure (mine office, rest shelter etc.) -0.10
6. Town Ship Area-0
7. Natural Water Bodies- 8.50
8. Plantation & Greenbelt -18.86
9. Mineral Storage (Sub-grade/mineral)-0
10. Undisturbed area -136.1168
Total area -169.5968 | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | It is an existing operative mine having area under mining is 5.12 ha. Additional requirement during modified mining plan period will be 7.18 Ha. Thus, total land use at the end of modified mining plan period will be 12.30 ha during plan period (2016-17 to 2020-21).The area mainly covered by dry deciduous scrub along with thorny sparse xerophytic vegetation which will require to be cleared during plan period. The land is devoid of any major vegetation cover and appears barren. | 1.3 | Creation of new land uses? | Yes | The mining lease of 169.5968 Ha. comprises of high grade Bauxite minerals. During approved plan period following land use is –
• Excavated area will be 12.30 Ha
• Waste Dump will be 1.0 Ha
• Tar Roads/ mine road will be 0.30 Ha
• Infrastructure (mine office, rest shelter etc.) is 0.10 Ha.
• Natural Water Bodies is 8.50 Ha
• Plantation & Greenbelt will be increased up to 23.86 Ha.
• Mineral Storage (Sub-grade/mineral will be 0.50 Ha
• Whereas 155.3968 Ha will remain undisturbed. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Departmental exploration, GMDC has been carried out 15 boreholes in compliance of proposal.
The exploration has been done in last 5 years by aggregating 173 meters drilling. The boreholes were drilled for 5 to 20 m depth. The drilling was done according to surface exposed mineralized zone. This exploration confirmed the mineralization and its continuity. | 1.5 | Construction works? | No | This is existing operative mine all necessary facilities are already available hence, no construction activities involved. | 1.6 | Demolition works? | No | Since it is an existing operative mine and also the land is free from any structure and, therefore, no demolition work is envisaged. | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | This is existing operative mine all necessary facilities are already available hence, no construction activities involved. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | No | No proposed ground work, however excavation activities will be involved during plan period. | 1.9 | Underground works including mining or tunnelling? | No | • It is existing operative Bauxite mineral mine.
• No underground activities involved in the project.
• The mining will be done by open cast semi mechanized method. | 1.10 | Reclamation works? | Yes | • The mining area covering 169.5968 ha shall be gradually developed and exploited for bauxite.
• It is estimated that by the end of 30 years, entire mineable bauxite reserves will be exhausted.
• The voids shall be used for rainwater storage except a low lying part, if any. This accumulated water shall be kept suitably fenced off all around.
• It is proposed to create water storages bodies during the lease period. | 1.11 | Dredging? | No | Not Applicable | 1.12 | Offshore structures? | No | Not Applicable | 1.13 | Production and manufacturing processes? | Yes | • Production capacity 35,000 TPA of Bauxite.
• The mining is being carried out by semi mechanized open cast method involving removal of top soil/Reject/overburden, shallow hole drilling, blasting, mechanized excavation combined with manual sorting.
• Sorted material is directly fed to the user industries. Transportation are carried out by hydraulic excavator, loader and tippers. | 1.14 | Facilities for storage of goods or materials? | Yes | • Marginal quantity of generated soil thus stacked will be used in re-vegetation/plantation schemes.
• Plantation is proposed to be covered under 1.0ha along boundary barrier i.e. boundary line
• Waste generated is proposed to be dumped at earmarked site. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | No | • No toxic effluent or solid waste is generated from the mines; quality of soil in the surrounding areas does not have any adverse impact.
• The marginal quantity of generated topsoil has been scrapped and stacked separately and is being utilized for plantation purpose. The stacking would be for a temporary duration. | 1.16 | Facilities for long term housing of operational workers? | Yes | It is existing operative Bauxite mineral mine. At present following site facilities are available in the ML area.
-A mine office is already present in the lease area for keeping the records and supervision by mines manager.
-A rest shelter for resting of laborers during lunch interval.
–Drinking water facilities
-Canteen facilities
-A first aid to the injured.
-urinals | 1.17 | New road, rail or sea traffic during construction or operation? | No | Not Applicable. Existing facilities will be used. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Not Applicable | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Not Applicable. Existing facilities will be used. | 1.20 | New or diverted transmission lines or pipelines? | No | Not Applicable | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not Applicable | 1.22 | Stream crossings? | No | Not Applicable, All nallahs or streams are seasonal & flow responses to monsoon showers only. | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | The total of about 29 KLD water required for various Domestic, Dust suppression, Green belt and mining operation, Source: Existing public water supply (through tankers). The source of water through existing water supply (tankers). However, in case of ground water utilization prior permission/NOC from CGWA will be obtained. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | There is no changes/disturbance of water course due to mining in past and also in future. As the matter of fact the mining lease area of Bauxite Mine is part of seasonal drains. Wherever required, water diversion channel shall be constructed.
Direct precipitation as well as catchment area water accumulates in drains passing through the ML area. There is no chance of disturbance of water course due to mining in the past and also in the future | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | No | It is existing operative opencast semi-mechanized Bauxite mine in which local manpower already deployed from nearby villages. Thus, no transportation of personnel envisaged. Whereas, tippers of 10 Tonne capacity is used for transportation of minerals as well as waste within the lease area. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | No dismantling works are envisaged during operation of mine. Post mining, mine land shall be duly reclaimed /rehabilitated as per Final Mine Closure Plan. | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not applicable. | 1.28 | Influx of people to an area in either temporarily or permanently? | No | Naredi-Mota-Nandra Bauxite Mine is being supervised and controlled by a team of technically and statutorily qualified personnel apart from the operating staff of skilled, semi-skilled and unskilled categories. Total 61 Manpower already involved mining operation. Thus, no additional influx of people either temporarily or permanently involved. | 1.29 | Introduction of alien species? | No | Not Applicable | 1.30 | Loss of native species or genetic diversity? | No | Not Applicable | 1.31 | Any other actions? | No | Not Applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | Total 169.5968 Ha Lease area comprises of –
1. Govt. land 144.9979 Ha
2. Agriculture land 24.5989 Ha. No forest land involved in the Mine lease area. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | The total of about 29 KLD
Source: Existing water supply through tanker | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | No | It is existing operative mine, no construction activities involved. | 2.5 | Forests and timber (source – MT) | No | Not Applicable | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Electricity- The provision of Solar power has been established at mine site office to meet all essential requirements. Daily power requirement will be 15-20 KW/day Diesel requirement is being fulfilled from nearby diesel filling stations which have been required for machineries, instruments and transportation vehicles like excavators, dumpers, dozers, etc. through contractors. | 2.7 | Any other natural resources (use appropriate standard units) | No | Not Applicable | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | One explosive Van of capacity 860 kg is being used. There will be no major storage of diesel which is being source from nearby diesel filling station. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | No such substances or material is being used which cause changes in occurrence of disease or disease vectors. Proper housekeeping & sanitation is being maintained to keep the work places free from disease causing vectors. Water sprinkling carried out for dust suppression. | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | Following Facilities have been created for the welfare of the employees are:
• Bauxite mining activity is the major source of employment, GMDC has provided sufficient infrastructural resources to the surrounding villages owing to various developmental and welfare activities.
• All villages are well connected by approach roads.
• Water supply, transportation, education and medical facilities are provided by GMDC to nearby villages.
• A well-equipped ambulance is provided to the local commu | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Not envisaged | 3.5 | Any other causes | No | Not applicable | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | Yes | • Alluvium cover is available in the ML area. It is available in form of overburden and inter-burden. The alluvium shall be removed separately and shall be used for plantation purposes.
Waste: About 95798 m3 will be generated during plan period which is dumped separately during the course of mining
• Mineral Sub grade:About 128710 generated during plan period. waste & sub-grade mineral shall be generated. This shall disposed of by means of dumping/stacking covering area 1.0 ha near BP no-9-10 | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Domestic waste generated from mines office is being disposed to soak pit via septic tank. Commercial waste sold/disposed to authorized vendors. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Used oil is being collected and disposed through authorized vendors. | 4.4 | Other industrial process wastes | No | There will be no other industrial process which will generate waste | 4.5 | Surplus product | No | Not Applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | No | No provision of STP, however negligible amount of domestic sludge generated from septic tank after long period which is easily decomposed. | 4.7 | Construction or demolition wastes | No | Not applicable | 4.8 | Redundant machinery or equipment | No | Not applicable | 4.9 | Contaminated soils or other materials | No | Not applicable | 4.10 | Agricultural wastes | No | Not applicable | 4.11 | Other solid wastes | No | Not applicable | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Emissions are generated from operation of HEMMs & transportation vehicles. Care is being taken to keep the emissions below standards by proper maintenance & regular monitoring. | 5.2 | Emissions from production processes | Yes | Particulate Matter emitted during drilling, blasting, Sizing with the help of rock breaker, Manual sorting and grading is being kept below the prescribed limits by adopting mitigating measures such as wet drilling, controlled blasting, water sprinkling on haul roads, development of greenbelt and plantation etc. | 5.3 | Emissions from materials handling including storage or transport | Yes | The loading of material and transportation may lead to generate dust pollutants. However, Systematic & scientific mining activities is being adopted, mine haul roads are sprayed with water to control dust emission.
Periodical maintenance of HEMMs is being done regularly to control emissions. Water sprinkling during loading and unloading of excavated materials is regularly undertaken. | 5.4 | Emissions from construction activities including plant and equipment | No | Not applicable | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust generated during drilling, blasting, loading, unloading, handling and transportation of mined out materials. Wet drilling is being adopted and water spraying is being done to control dust emission while transportation of Ore and overburden. Since it is existing operative mine hence, no construction activities envisaged. There is no possibility of any odour generation. | 5.6 | Emissions from incineration of waste | No | Not Applicable | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not Applicable | 5.8 | Emissions from any other sources | No | Not Applicable | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Noise generated due to mining machineries during mining operation.
Personal Protective Equipment (PPE) like ear muffs/ear plugs is being provided to the workers including operators of mining machinery.
Periodic Noise monitoring is being carried out and report submitted at statutory authorities.
Monthly ambient noise monitoring is being carried out and proper maintenance of noise generating equipment’s is being submitted statutory authorities regularly. | 6.2 | From industrial or similar processes | No | Not Applicable | 6.3 | From construction or demolition | No | Not applicable | 6.4 | From blasting or piling | Yes | Controlled blasting by use of latest blasting techniques is being adopted to keep noise level within permissible limits. Plantation at designated area will serve as a noise barrier and minimize the propagation of noise.
Workers working in close vicinity of machines are provided with personal protective equipment (PPEs). | 6.5 | From construction or operational traffic | Yes | Operation of dumpers/Tippers and other machinery generate noise. Noise level is being maintained within prescribed limits by adopting site specific mitigation measures. | 6.6 | From lighting or cooling systems | No | Not Applicable | 6.7 | From any other sources | No | Not Applicable | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | Not Applicable since no hazardous material involved during mining process except the explosive which stored and handled as per the permission letter of controller of explosive and will not contaminate neither the land nor water bodies. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | Sewage is being treated in Septic tank followed by Soak Pit.
Neither any chemical nor toxic effluents are discharged from the area nor any toxic substance used in the mining or allied activities. | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | All the emissions from the Mine operations are controlled and in compliance with CPCB/SPCB norms | 7.4 | From any other sources | No | Not envisaged. | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Not envisaged. | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | The extent of accident is expected to be nil because of adequate precautions and safety measures such as properly designed blasting by effective stemming and use of optimum charge/delay detonators.
Fire extinguishers shall be provided in all HEMMS explosive magazine, workshop and mine office.
Explosive are handled under the supervision of licensed person. DGMS & Controller of Explosive operational guidelines is followed | 8.2 | From any other causes | No | Not Applicable | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | Seismically, this area is categorized under Zone-V as per IS-1893 (Part-1)-2002. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | GMDC was established in 1963, the company has done lot of activities for the development of society in the area. The activities of the company given in brief:
• Water Resource Management
• Health care program
• Women empowerment
• Education &
• Infrastructure development
• Skill development | 9.2 | Lead to after-use of the site, which could have an impact on the environment | Yes | Post mining, once minerals is excavated, the mined out area shall use for rainwater storage. This accumulated water shall be kept suitably fenced off all around. Thus, water storage bodies will be created.
At the end of lease period 23.86 Ha. land will be under plantation and green belt. | 9.3 | Set a precedent for later developments | Yes | This is an existing operative mine project has set precedence in the area for environmental preservation and socio-economic
improvement. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | There are no other existing or planned projects adjoining to existing Bauxite mine hence, no direct cumulative impact are envisaged. GMDC already adopted site specific mitigation measures in line with existing EC conditions. | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | No | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | No | Wetlands - None within 15 km radius.
Coastal Zone - None within 15 km radius.
Mountains –None within 15 km radius. | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | None within 15 km radius | 4 | Inland, coastal, marine or underground waters | No | None within 15 km radius | 5 | State, National boundaries | No | None within 15 km radius | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | None within 15 km radius | 7 | Defence installations | No | None within 15 km radius | 8 | Densely populated or built-up area | Yes | Naredi - 2.30 Km, SW | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Rural Hospital, Abdasa- 25.30 Km,W
GMDC First Aid Centre- 2.45 Km NE
Temple-Kotada Roha - 5.40 km SE | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | Seasonal Kankavati Nadi - Crossing ML area
• Water body Balachod
Sumrasar Talav - 2.05 km-NW
Nalra River - 2.49 km- WNW
1. • Mothala RF - 6.72 Km-W
2. • Khirsara RF - 9.82 km-E
3. • Jarjok RF - 6.02 km- S
4. • Bhittara RF - 7.02 km S
5. • Makda RF - 7.46 km-SE
6. • Moti Maun RF - 9.2 km SE
7. • Roha RF - 4.2 km -E
8. • Naranpar RF - 1.84 km-NE | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | None within 15 km radius | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | Seismically, this area is categorized under Zone-V as per IS-1893 (Part-1)-2002. | | (IV) | Proposed Terms of Reference for EIA studies | | Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | Eds Reply Letter | The correction have been made as per the instruction received | 16 Mar 2021 | 2. | NA | PP needs to submit the latest certified Compliance report and latest past production details certified by DMG. | 10 Mar 2021 | | Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | ADS Reply of Naredi-Mota-Nandra Bauxite Mining Project (Mine Lease, Area – 169.59 Ha. & Production Capacity 35,000 TPA) | 17 Apr 2019 | 2. | NA | Deferred | 22 Nov 2018 | | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Chirag | Designation | General Manager (Environment) | Name of Company (Applicant Name should not be given here) | GUJARAT MINERAL DEVELOPMENT CORPORATION LIMITED | Address | KHANIJ BHAVAN
132 FEET RING ROAD
NEAR UNIVERSITY RING ROAD
VASTRAPUR AHMEDABAD |
|
|