APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Application for Amendment in Existing EC for Proposed Expansion of Styrene Acrylonitrile co-polymer (SAN) plant from 1,20,000 MTA to 1,60,000 MT/Annum and Transfer of EC from M/s. INEOS ABS (India) Limited to M/s. Ineos Styrolution India Limited at Halol-Kalol Road, Taluka-Kalol, District Panchmahal, State Gujarat by M/s. INEOS Styrolution India Limited
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/GJ/IND2/84448/2018
Project Cost 12300 lacs
2.
S. No. in the schedule5(e) Petrochemical based processing (processes other than cracking &
Project Sector Industrial Projects - 2
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled Old Name of Industry: M/s. INEOS ABS (India) Limited New Name of Industry: M/s. Ineos Styrolution India Limited Certificate of incorporation pursuant to change of name is attached as Annexure 3. Existing Products: SAN: 1,20,000 MTPA ABS Sheet: 2400 MTPA Proposed Capacity: SAN: 40,000 MTPA ABS Sheet: 0 MTPA After proposed expansion: SAN: 1,60,000 MTPA ABS Sheet will be deleted in proposed expansion. Plot area will be 48857 m2 after proposed expansion (4.88 ha) ha.
4.
New/Expansion/ModernizationExpansion
Proposal NumberIA/GJ/IND2/84423/2010
MoEFCC file number(Previous EC)J-11011/133/2010-IA II (I)
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 4.8857 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the project17,18/1, 18/2 & 20, 4060, Katol Village, Kalol Taluka, Gujarat State
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.17,18/1, 18/2 & 20, 4060
Town / VillageKatol Village
State of the projectGujarat
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)GujaratPanchmahalKalol
10.
Nearest railway station along with distance in kms Derol, 3.6 km
Nearest airport along with distance in kms Vadodara, 38 km
11. Nearest Town/City/District Headquarters along with distance in kms Kalol , 1.45 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Katol Village Panchayat
13. Name of the Applicant Parvez
14. Registered Address 5th Floor, OHM House - II, OHM Business Park,
15.
Address for correspondance:
Name of the Company INEOS STYROLUTION INDIA LIMITED
Name of the Applicant Parvez
Designation (Owner/ Partner/ CEO) PlantManager
Pin code 389330
E-mail parvez.bata@styrenix.com
Telephone No. 02676-228405
Fax No. 02676-
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes Landuse The unit is located in non-notified Industrial Estate. The unit is planning to do expansion in production capacity with debottlenecking in existing process. Additional land is purchased for greenbelt and raw material storage facility. Due to addition of land for expansion there will be change in landuse pattern from agriculture to industrial. Total plot area after expansion will be 48857 m2. Site Layout Map is attached as Annexure 6
1.2 Clearance of existing land, vegetation and buildings? No The existing & additional land earmarked does not have any vegetation, building and therefore do not require any clearance work.
1.3 Creation of new land uses? Yes Additional land will be used for industrial purpose and greenbelt.
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Soil investigation will be done before construction phase
1.5 Construction works? Yes There will be construction of finish goods and raw material storage facility.
1.6 Demolition works? Yes Demolition will be done for existing hazardous waste storage area, ware house facility.
1.7 Temporary sites used for construction works or housing of construction workers? No As far as possible efforts will be made to hire local workers not requiring overnight stay at the site. In any case, basic facilities such as rest shelters and sanitation facilities will be provided at project site for all workers.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Soil excavation will be required for finish goods and raw material storage facility.
1.9 Underground works including mining or tunnelling? No Underground work will not be required.
1.10 Reclamation works? No No Reclamation works will be required
1.11 Dredging? No No dredging works will be required
1.12 Offshore structures? No Not applicable
1.13 Production and manufacturing processes? No There will be no change in topography, land use, water bodies etc. due to proposed manufacturing activity. Manufacturing process is given vide Annexure 7
1.14 Facilities for storage of goods or materials? Yes There will be no change in topography & water bodies. Minor change land use due to construction of storage of raw materials and finish products. Storage of Raw Material is given in Annexure 8
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Liquid Wastes 30 KLD sewage will be disposed off in soak pit. 91 KLD industrial wastewater will be treated in existing 120 m3 of ETP. Details of wastewater generation are given in Annexure 9 Tentative details of ETP are given in Annexure 10 Hazardous & Solid Wastes Hazardous & Solid wastes will be managed as described in Annexure 13
1.16 Facilities for long term housing of operational workers? No Employees will be hired from nearby city & towns
1.17 New road, rail or sea traffic during construction or operation? Yes a. Road Traffic Existing 30 and additional road trips 20 will be generated for movement of raw material and finished goods transfer during operation phase. The existing road has adequate carrying capacity. Existing infrastructure facility will be used for traffic movement. b. Rail Traffic There will not be any additional rail traffic due to proposed activity during construction and operational phase. c. Sea Traffic There may not be any additional sea traffic due to proposed activity during
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No The area is well equipped with the commercial infrastructure including approach roads, by-pass roads, over bridges and electricity etc. Around 9 – 6 meter wide internal roads are planned within the plant premises. No additional transport infrastructure is required to set up the project.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No It is not required to close or divert existing transport routes and infrastructure.
1.20 New or diverted transmission lines or pipelines? No Not envisaged
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No No change in hydrology of water courses / aquifers are envisaged since the adequate mitigation measures including rain water harvesting and storm water management proposed.
1.22 Stream crossings? No -
1.23 Abstraction or transfers of water from ground or surface waters? No 508 KLD water will be source from borewell. Water Consumption Break-up is given vide Annexure 9
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No There will not be any change in water bodies or land surface affecting drainage or run-off for the site. If required suitable storm water drains will be provided.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes All transportation of material and people for construction will be done by road. Personnel Construction workers: ~500 (for a few months only when construction takes place) Permanent Employment: Existing: 100 persons (Permanent) + 72 persons (Contractual) Additional: 15 persons (Permanent) Materials Increased material transfer will occur due to enhanced raw material and product shipments and also during construction.
1.26 Long-term dismantling or decommissioning or restoration works? No Proposed project does not involve any long term dismantling or decommissioning or restoration works.
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No Not applicable
1.28 Influx of people to an area in either temporarily or permanently? No It is anticipated that about ~500 persons will be deployed at the site for the purpose of construction activities and 48 persons will be engaged additionally operations expansion commence. This is not deemed as an ‘influx’ and will not impact the demographic profile of the study area.
1.29 Introduction of alien species? No Not Anticipated
1.30 Loss of native species or genetic diversity? No Not Anticipated
1.31 Any other actions? No -
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No Existing: 40977 m2 Proposed: 7879 m2 Total: 48,857 m2 8327 m2 land is agricultural land and will be converted for industrial purpose.
2.2 Water (expected source & competing users) unit: KLD Yes 508 KLD fresh water will be source from borewell. Water Consumption details are given in Annexure 9.
2.3 Minerals (MT) No Not applicable
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Construction materials like cement, stone aggregates and sand with water will be sourced from nearby areas.
2.5 Forests and timber (source – MT) No Not applicable
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Power supply from Grid: Source: Madhya Gujarat Vij Company Ltd (MGCVL) Existing: Demand in kVA= 2200 Proposed Expansion: Demand in kVA= 300 After Proposed Expansion: Demand in kVA= 2500 Standby Power: Existing: 3 nos. of capacity of 1000 kVA, 1010* kVA & 1250 kVA *capacity will be upgraded from 1010 kVA to 1500 kVA After Proposed Expansion 3 nos. of capacity of 1000 kVA, 1500 kVA & 1250 kVA Fuel sourcing and consumption details are given in Annexure 11
2.7 Any other natural resources (use appropriate standard units) No Not anticipated
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes The following listed chemical will be used in processes. • Styrene • Acrylonitrile • Toluene Use, storage, transportation and handling of all these chemicals will be done carefully by qualified and trained persons and in conformance with the MSIHC Rules 1989, as amended till date.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No -
3.3 Affect the welfare of people e.g. by changing living conditions? Yes The project will substantially direct and indirect employment opportunities associated with the construction and operation of the plant.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Not anticipated
3.5 Any other causes No None identified
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No Top soil will be used for gardening and overburden generated during excavation will be reused for low lying area of project premises.
4.2 Municipal waste (domestic and or commercial wastes) Yes Non-Hazardous waste will be generated in the facility on a yearly basis which are listed below: 1. Wooden scrap/ broken pallet 2. Metal scrap 3. Paper waste 4. Poly bag/plastic waste 5. Powder bag/ gunny bag 6. Miscellaneous garbage 7. Canteen waste
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Hazardous waste generation quantity to be generated are given in Annexure 13 Membership Certificate/s from an authorized TSDF/recycler for Hazardous waste management will be procured prior to commencement of production/operations at site.
4.4 Other industrial process wastes Yes Already covered in Annexure 13
4.5 Surplus product Yes Production will be done as per plan based on market demand. The off specification product or returned product will be worked off and reuse.
4.6 Sewage sludge or other sludge from effluent treatment Yes Sludge from ETP will be disposed of as land filling through TSDF
4.7 Construction or demolition wastes Yes The construction waste shall consist of cement bags, metal waste, concrete waste, etc. and shall be disposed suitably in safe manner.
4.8 Redundant machinery or equipment No --
4.9 Contaminated soils or other materials No All storage tanks are inside dyke wall. Impervious floor are provided in manufacturing area.
4.10 Agricultural wastes No --
4.11 Other solid wastes Yes Solid waste like packaging material, bag and container will be sold to recycler.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Construction During construction phase, emissions will primarily from vehicles, construction equipment using diesel and similar fuels. These emissions will typically be sporadic and short duration. Operation Stacks details and air pollution control measures are given in Annexure 11 Adequate stack height will be provided for all flue gas stacks in order to disperse the flue gases effectively. The ambient air quality will be maintained as per GPCB/CPCB norms. Stack emission quality will be mai
5.2 Emissions from production processes Yes Details of process vents are given in Annexure 12
5.3 Emissions from materials handling including storage or transport Yes Construction Material handling during construction will primarily cover: Movement of construction materials and handling of equipment required to be installed as part of the project requirements. These will result in dust emissions for which a suitable air pollution management plan will be prepared. Operations No emission during material handling & transportation.
5.4 Emissions from construction activities including plant and equipment Yes Dust emission will be envisaged from handling of construction materials and from operation of construction machineries and vehicles. Appropriate control measures like water sprinkling in approach road, covering of construction material would be undertaken during the construction phase.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Dusting will be envisaged during construction phase
5.6 Emissions from incineration of waste No Incinerator is removed
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No No waste will be burnt in open air.
5.8 Emissions from any other sources No There will be no emission from any other sources.
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Noise will be generated from operation of DG Set, Boiler and air compressor and fume extraction system etc. DG set will be used only during power failure. Adequate acoustic measures and necessary PPEs will be provided to exposed employees.
6.2 From industrial or similar processes No Majority of operations in the unit is not producing any objectionable noise. DG Sets along with acoustic enclosures is used only during power failure. However, cumulative noise levels will be kept within permissible limits at plant boundary.
6.3 From construction or demolition Yes During construction phase, noise will be generated due to erection of equipments for a short duration of time. This includes movement of heavy earth moving and construction equipments such as excavators, loaders, cranes and others.
6.4 From blasting or piling Yes Piling is envisaged as part of the construction process.
6.5 From construction or operational traffic Yes Construction Traffic Noise and Vibration: Construction traffic would generate noise and vibration from trucks and vehicles, earth moving machinery and lifting equipment such as cranes. Minor noise would be generated from passenger vehicles which is normal. Operational Noise and Vibration: Operational noise and vibration from traffic would essentially include from trucks bringing raw materials and carrying finished products. Minor noise would be generated from passenger vehicles which is norma
6.6 From lighting or cooling systems Yes Minor noise will be generated from operation of cooling towers
6.7 From any other sources No Not identified
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No These will not affect the water or land because of appropriate flooring & presence of spill control procedures. Moreover, all of the Hazardous wastes will be disposed off as per guidance of State Pollution Control Board to authorized recyclers or TSDF sites.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes Effluents generated will be treated in ETP and treated effluent will be used for gardening. After proposed expansion the same practice will be continued.
7.3 By deposition of pollutants emitted to air into the land or into water No Ground level concentration shall be well within the NAAQM standard prescribed by GPCB.
7.4 From any other sources No None identified/expected
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No There will not be long term built-up of pollutants. Treated wastewater from ETP will be conformed to norms by GPCB.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes Spillage of Acrylonitrile, styrene and Toluene can cause following hazardous to human health Acrylonitrile is very hazardous with skin contact, ingestion and inhalation. Styrene is very hazardous in case of eye contact (irritant) and hazardous in case of skin contact Toluene is flammable substance. Fire: Main raw materials for the production of SAN are Acrylonitrile, Styrene and toluene, which are flammable in nature. Spillage of these chemicals may cause fire. Explosions: Acrylonitrile
8.2 From any other causes Yes Common risks in factories such as: • Electric Shock, Hit by Objects, Fall / Slips, Hot Work such as Welding and Cutting
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? Yes The project area lies in the seismic intensity Zone III, which is classified as moderate damage risk zone.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
No -
9.2 Lead to after-use of the site, which could have an impact on the environment No -
9.3 Set a precedent for later developments No -
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No The proposed expansion project will be set up in a systematic manner and will have cumulative positive impact on the socio economic aspect of the area.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes Heritage Site Distance in km Direction Champaner World Heritage Site 14.83 SSE
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Water body Distance in km Direction Katol Pond 1.43 NE Barola Pond 0.86 WSW
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No None
4 Inland, coastal, marine or underground waters Yes Village Pond Distance in km Dir Goma River 0.20 E Karad River 1.77 S
5 State, National boundaries Yes No state or national boundaries within 10 Km from project site boundary.
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes Area Distance in km SH-87 Adjacent to project site NH-5 Adjacent to project site
7 Defence installations No --
8 Densely populated or built-up area Yes Area Distance in km Dir Halol 10.95 SSE Kalol 1.45 NE
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Area Distance in km Dir Halol 10.95 SSE Kalol 1.45 NE
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No --
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No --
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects Yes Earthquake: The site falls in Seismic Zone III (Moderate)
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAThe correction have been made as per the instruction received 06 Nov 2018
2.NAPlease also submit a proposal for transfer of the EC in the name of the new company. 05 Nov 2018
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantParvez
DesignationPlantManager
Name of Company (Applicant Name should not be given here)INEOS STYROLUTION INDIA LIMITED
Address5th Floor, OHM House - II, OHM Business Park,
Print