APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Expansion of Dyes Intermediates by COLORBAND DYESTUFF (P) LIMITED.
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/GJ/IND2/112826/2019
Project Cost 584.13 lacs
2.
S. No. in the schedule5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Project Sector Industrial Projects - 2
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 20.9 TPM ha.
4.
New/Expansion/ModernizationExpansion
Proposal NumberIA/GJ/IND2/112825/2017
MoEFCC file number(Previous EC)AWH-95338
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 0.0583 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectPlot No: J-2317, Phase: III, Notified Industrial Area, GIDC, Vapi - 396195 Tal.: Pardi, Dist.: Valsad, Gujarat
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.Plot No: J-2317
Town / VillageGIDC Vapi
State of the projectGujarat
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)GujaratValsadPardi
10.
Nearest railway station along with distance in kms Vapi Railway station, 4.24 km
Nearest airport along with distance in kms Surat Airport, 85.10 km
11. Nearest Town/City/District Headquarters along with distance in kms Vapi , 5.16 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) GIDC Vapi, Ta-Pardi, Dist-Valsad
13. Name of the Applicant Hareshwar
14. Registered Address Plot No.-J 2327, Phase III, Notified Industrial Area, GIDC Vapi, Ta: Pardi
15.
Address for correspondance:
Name of the Company COLORBAND DYESTUFF P LTD
Name of the Applicant Hareshwar
Designation (Owner/ Partner/ CEO) Director
Pin code 396195
E-mail ram@colorbandindia.com
Telephone No. 022-40186666
Fax No. 022-
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . NIL
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No The company has existing plots for the proposed expansion project. There will be no change in land use, land cover or topography due to Construction, operation or decommissioning of the Project as the project is to be located in GIDC Vapi, a notified industrial area.
1.2 Clearance of existing land, vegetation and buildings? No Not applicable.
1.3 Creation of new land uses? No No any
1.4 Pre-construction investigations e.g. bore houses, soil testing? No Already done during construction of existing unit
1.5 Construction works? Yes Minor Construction activity will be undertaken for the proposed expansion project.
1.6 Demolition works? No There will be no demolition, underground, reclamation or dredging work. No temporary sites for construction work or housing of construction workers will be developed as local labour will be employed.
1.7 Temporary sites used for construction works or housing of construction workers? No No temporary sites for construction work or housing of construction workers will be developed as local labour will be employed.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations No No temporary sites for construction work or housing of construction workers will be developed as local labour will be employed.
1.9 Underground works including mining or tunnelling? No No temporary sites for construction work or housing of construction workers will be developed as local labour will be employed.
1.10 Reclamation works? No There will be no demolition, underground, reclamation or dredging work.
1.11 Dredging? No There will be no demolition, underground, reclamation or dredging work.
1.12 Offshore structures? No No temporary sites for construction work or housing of construction workers will be developed as local labour will be employed.
1.13 Production and manufacturing processes? Yes Manufacturing of dye Intermediates.
1.14 Facilities for storage of goods or materials? Yes The raw materials are/will be stored in a raw material storage area and hazardous chemicals are/will be stored separately.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes • Total industrial effluent generation will be 5.94 KLD. Out of which 2.44 KLD of concentrated effluent is segregated and sent to CMEE of M/S VGEL, Vapi and balance 3.5 KLD of normal effluent is treated in primary followed by tertiary ETP and discharge into underground effluent drainage line to CETP Vapi.
1.16 Facilities for long term housing of operational workers? No Workers from the local/nearby areas will be employed.
1.17 New road, rail or sea traffic during construction or operation? No No new road, rail or sea traffic during construction or operation
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No No New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No No closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements
1.20 New or diverted transmission lines or pipelines? No No New or diverted transmission lines or pipelines
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No No Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers
1.22 Stream crossings? No No Any
1.23 Abstraction or transfers of water from ground or surface waters? No Water requirement will be met from GIDC Water supply Vapi.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No No Any
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes We shall hire personnel from local / nearby area only and the construction material will be obtained preferably from local traders and will be transported via roads. The sources of raw materials and machinery for operation will vary based on market driven forces, which will be transported via roads.
1.26 Long-term dismantling or decommissioning or restoration works? No No
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No No any
1.28 Influx of people to an area in either temporarily or permanently? No Not applicable.
1.29 Introduction of alien species? No No
1.30 Loss of native species or genetic diversity? No Not applicable
1.31 Any other actions? No No
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No The proposed project will be accommodated in the existing plot belongs to notified industrial estate.
2.2 Water (expected source & competing users) unit: KLD Yes Existing: 6.81 KLD Proposed: 5.07 KLD Total: 11.88 KLD Source: GIDC water Supply
2.3 Minerals (MT) No Not Applicable
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes From local Suppliers
2.5 Forests and timber (source – MT) No No Any
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Total Fuel after expansion: • Natural Gas - 145 SCM/h • HSD for D.G. Set – 7 kg/h Power: Power requirement of 400 kVA (Existing 63 kVA + proposed 337 kVA) will be sourced from Dakshin Gujarat Vij Co. Ltd (DGVCL).
2.7 Any other natural resources (use appropriate standard units) No No other natural resource will be used.
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes Handling of Hazardous substances will be done as per the Manufacture, Storage and Import of Hazardous Chemical rules, 1989, as amended to date.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No No any
3.3 Affect the welfare of people e.g. by changing living conditions? No The project site is located in a notified industrial zone which is surrounded by cluster of industries, thus there will be no change in the living condition of the people in the nearby vicinity.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Project site is in GIDC Vapi, notified Industrial area. People will not affect due to project activity.
3.5 Any other causes No No any
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No Not applicable.
4.2 Municipal waste (domestic and or commercial wastes) Yes The commercial waste generated from administration building will be sold to scrap vendors. Domestic waste water (1 KLD) will be disposed off through Septic Tank/Soak pit.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes • Waste from ETP - 2.0 TPA - Dispose off into TSDF, Vapi, BEIL Ankleshvar • Discarded containers - 2.0 TPA - Return to raw material supplier or Sell to authorized recycler • Used oil - 0.01 TPA - Sell to authorized recycler • HCl (30%) from Scrubber - 31.3 TPA - In-house Recycle in process of DBPT • Bleed liquor from Scrubber mainly mixture of sodium sulphate, bi sulphite and sodium bromide- 40.89 TPA- Sent to CMEE of M/S VGEL • Spent solvent (toluene) - 26.44 TPA-
4.4 Other industrial process wastes Yes Same as Above
4.5 Surplus product No No any
4.6 Sewage sludge or other sludge from effluent treatment Yes ETP Sludge 2.0 TPA - Dispose off into TSDF, Vapi, BEIL Ankleshvar
4.7 Construction or demolition wastes Yes Construction wastes will be sold to authorized vender.
4.8 Redundant machinery or equipment No No any
4.9 Contaminated soils or other materials No No any
4.10 Agricultural wastes No No any
4.11 Other solid wastes No No any
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Flue Gas emission: PM<150 mg/Nm3 ,SO2<100 ppm, NOx<50 Adequate height of chimney and SMF is/will be provided.
5.2 Emissions from production processes Yes There will be generation of SO2, HBr, Br2 and HCl gases generated from the process of Group C products only. To scrub SO2, HCl, HBr, Br2 gases two stage water followed alkali scrubber will be provided. Also 11 meters height of vent will be provided.
5.3 Emissions from materials handling including storage or transport Yes Fugitive Emission will be controlled during Storage and handling of materials. Proper care shall be done to control.
5.4 Emissions from construction activities including plant and equipment Yes Fugitive emission will be generated during construction activity for short period. Proper mitigation measures will be adopted to control air pollution.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes It will be control by using proper good handling practices.
5.6 Emissions from incineration of waste No No incinerator is/will be used for the unit.
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Construction debris will be disposed off separately or will be sold out to recycler or authorized vender. No open burning of waste will be permitted.
5.8 Emissions from any other sources No No any
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes There will noise emission from plant machinery, it will be controlled at source by regular maintenance programme, acoustic enclosure where ever needed and usage of PPEs to minimize exposure to noise
6.2 From industrial or similar processes Yes There is noise emission from plant machinery, it will be controlled at source by regular maintenance programme, acoustic enclosure where ever needed and usage of PPEs to minimize exposure to noise
6.3 From construction or demolition Yes Construction activities will be allowed only during day time to achieve the prescribed norms of noise.
6.4 From blasting or piling No Not Applicable
6.5 From construction or operational traffic Yes Noise due to vehicular movement, construction equipmentsand machineries will be well within the prescribed norms.
6.6 From lighting or cooling systems No Noise due to cooling system will be controlled at source by regular maintenance programme, acoustic enclosure where ever needed and usage of PPEs to minimize exposure to noise
6.7 From any other sources No No any
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials Yes Hazardous materials will be stored in an isolated area and all proper steps will be followed to prevent accidents.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes • Total industrial effluent generation will be 5.94 KLD. Out of which 2.44 KLD of concentrated effluent is segregated and sent to CMEE of M/S VGEL, Vapi and balance 3.5 KLD of normal effluent is treated in primary followed by tertiary ETP and discharge into underground effluent drainage line to CETP Vapi.
7.3 By deposition of pollutants emitted to air into the land or into water Yes The emission from utility section will be controlled with help of Adequate Stack height. The emission from Production section will be controlled with help of Adequate two stage water followed alkali scrubber having 11 m height of vent.
7.4 From any other sources No No Any
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No No Any
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes Hazardous chemicals and waste is/will be stored in an isolated area and all proper steps is/will be followed to prevent accidents.
8.2 From any other causes No No any other causes
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No No any
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
No Project location is GIDC Vapi which have well supporting infrastructure like highways, power supply, CETP etc. Hence there will be no need of extra development.
9.2 Lead to after-use of the site, which could have an impact on the environment No No any
9.3 Set a precedent for later developments No No any
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects Yes The unit belongs to an area where other pharmaceutical, pesticide and chemical industries are in operation in a close proximity. Pollution load of this industrial cluster may lead to cumulative negative impacts on surrounding. However, the unit belongs to a notified industrial area of GIDC Vapi
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No None within 10 km radius.
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No None within 10 km radius.
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No None within 10 km radius.
4 Inland, coastal, marine or underground waters No None within 10 km radius.
5 State, National boundaries No • Daman & Diu - Approx. 5.97 km, West direction • D&NH – Approx. 8.52 km, South direction
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes • Daman & Diu - Approx. 5.97 km, West direction • D&NH – Approx. 8.52 km, South direction
7 Defence installations No None within 10 km radius.
8 Densely populated or built-up area Yes Vapi – 5.16 km W
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes • Genius Play School – 2.69 km, W direction • Vital Health Care Pvt. Ltd. – 2.22 km, NW direction
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Yes Daman Ganga river- 5.01 km, SW direction
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No The unit belongs to Vapi GIDC notified industrial area.
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No No any
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
Additional Attachments, if any
Attached File
Existing CC&A
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantHareshwar
DesignationDirector
Name of Company (Applicant Name should not be given here)COLORBAND DYESTUFF P LTD
AddressPlot No.-J 2327, Phase III, Notified Industrial Area, GIDC Vapi, Ta: Pardi
Print