APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s AYM Syntex Limited
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/DN/IND2/51548/2016
Project Cost 13800.00 lacs
2.
S. No. in the schedule5(d) Manmade fibres manufacturing
Project Sector Industrial Projects - 2
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled Synthetic Filament Yarns @ 150000 TPA and POY Master Batches (Colour) @ 600 TPA ha.
4.
New/Expansion/ModernizationNew
5. Existing Capacity/Area etc.  ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify Yes
d) Inter-State boundaries and international boundaries
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectDadra And Nagar Haveli
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.at Survey No. 394/P, Industrial Zone, Village: Saily, Silvassa-396 230 (U.T. of Dadra & Nagar Haveli) since 1994-95.
Town / VillageSilvassa
State of the projectDadra and Nagar Haveli
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)Dadra and Nagar HaveliSilvassaNo Data
(2.)Dadra and Nagar HaveliDadra and Nagar HaveliDadra and Nagar Haveli
10.
Nearest railway station along with distance in kms Vapi, 12.30 km
Nearest airport along with distance in kms Mumbai, 150 km
11. Nearest Town/City/District Headquarters along with distance in kms Silvassa , 5.0 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given)
13. Name of the Applicant Saha
14. Registered Address Survey No. 394/P, Village-Saily, Silvassa, U.T. Of Dadra and Nagar Haveli
15.
Address for correspondance:
Name of the Company AYM SYNTEX LIMITED
Name of the Applicant Saha
Designation (Owner/ Partner/ CEO) Senior Vice president
Pin code 396230
E-mail sam@aymgroup.com
Telephone No. 0260-2640596
Fax No. 0260-2640362
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . NIL
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No Since the proposed expansion project is within the existing unit, hence no additional land is required.
1.2 Clearance of existing land, vegetation and buildings? No As no additional land is required for the proposed project, since it is to be developed within the existing developed site only.
1.3 Creation of new land uses? No As the proposed project is within existing industrial zone.
1.4 Pre-construction investigations e.g. bore houses, soil testing? No As there is no additional land required. Project is in the existing developed site only.
1.5 Construction works? No Construction work will be done as per the requirement of proposed project.
1.6 Demolition works? No Already developed land for Industrial purpose hence demolition not required.
1.7 Temporary sites used for construction works or housing of construction workers? No No temporary sites for construction work or housing of construction workers will be developed as local labour will be employed
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations No There will be no any ground buildings, structures or earthworks including linear structures, cut and fill or excavations
1.9 Underground works including mining or tunnelling? No There will be no demolition, underground, reclamation or dredging work.
1.10 Reclamation works? No There will be no demolition, underground, reclamation or dredging work.
1.11 Dredging? No There will be no demolition, underground, reclamation or dredging work.
1.12 Offshore structures? No Not applicable
1.13 Production and manufacturing processes? Yes Pls. refer Project Feasibility Report.
1.14 Facilities for storage of goods or materials? Yes The raw materials will be stored in raw material storage area.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? No • Existing ETP has been instated and finally treated effluent will be used for plantation /gardening purpose. • Hazardous solid waste will be disposed off to the TSDF site of GEPIL site, Silvassa.
1.16 Facilities for long term housing of operational workers? No Workers from the local/near-by areas will be employed.
1.17 New road, rail or sea traffic during construction or operation? No --
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No --
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No --
1.20 New or diverted transmission lines or pipelines? No --
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No --
1.22 Stream crossings? Yes Water requirement will be fulfilled through Irrigation canal (Surface water source).
1.23 Abstraction or transfers of water from ground or surface waters? No --
1.24 Changes in water bodies or the land surface affecting drainage or run-off? Yes We shall hire persons from local / nearby area only and the construction material will be obtained preferably from local traders. The sources of raw materials will vary based on market driven forces, which will be transported via roads. All the major plant & machinery will be imported.
1.25 Transport of personnel or materials for construction, operation or decommissioning? No --
1.26 Long-term dismantling or decommissioning or restoration works? No --
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No --
1.28 Influx of people to an area in either temporarily or permanently? No --
1.29 Introduction of alien species? No --
1.30 Loss of native species or genetic diversity? No --
1.31 Any other actions? No --
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No The proposed expansion project will be accommodated in the existing plots belongs to notified industrial estate.
2.2 Water (expected source & competing users) unit: KLD Yes Source : Irrigation Canal Please Refer Project Pre-Feasibility Report.
2.3 Minerals (MT) No --
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) No Existing set up will be utilized.
2.5 Forests and timber (source – MT) No --
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Please Refer Project Pre-Feasibility Report.
2.7 Any other natural resources (use appropriate standard units) No --
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No --
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No --
3.3 Affect the welfare of people e.g. by changing living conditions? No The proposed site is surrounded by cluster of industries, thus there will be no change in the living condition of the people in the nearby area.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No --
3.5 Any other causes No --
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No --
4.2 Municipal waste (domestic and or commercial wastes) Yes The commercial waste generated from administration building will be sold to scrap vendors.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Please Refer Project Pre-Feasibility Report.
4.4 Other industrial process wastes Yes Please Refer Project Pre-Feasibility Report.
4.5 Surplus product No --
4.6 Sewage sludge or other sludge from effluent treatment Yes Please Refer Project Pre-Feasibility Report.
4.7 Construction or demolition wastes No --
4.8 Redundant machinery or equipment No --
4.9 Contaminated soils or other materials No --
4.10 Agricultural wastes No --
4.11 Other solid wastes No --
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Please Refer Project Pre-Feasibility Report.
5.2 Emissions from production processes No --
5.3 Emissions from materials handling including storage or transport No --
5.4 Emissions from construction activities including plant and equipment No --
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Dusting will be generated during the transportation of goods and materials. Dusting will subsided by spraying of water.
5.6 Emissions from incineration of waste No --
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No --
5.8 Emissions from any other sources No --
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Noise will be generated from operation of equipment and it will be below the statutory norms.
6.2 From industrial or similar processes Yes Noise will be generated from industrial process and it will be below the statutory norms.
6.3 From construction or demolition Yes Noise Level at different sources is expected to be coming below acceptable limit.
6.4 From blasting or piling No --
6.5 From construction or operational traffic No --
6.6 From lighting or cooling systems No --
6.7 From any other sources No --
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No --
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No --
7.3 By deposition of pollutants emitted to air into the land or into water Yes The emissions from utility section will be controlled with help of adequate chimney height. Moreover, there will be no process gas emissions from the proposed manufacturing process.
7.4 From any other sources No --
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No --
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No --
8.2 From any other causes No --
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No --
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
No Supporting infrastructure like roads, power grids already exist. Existing modified waste water treatment plant has been installed. Local labour will be utilized.
9.2 Lead to after-use of the site, which could have an impact on the environment No Not foreseen
9.3 Set a precedent for later developments No Not foreseen
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects Yes The unit belongs to an area where other industries are in operation in a close proximity. Pollution load of this industrial cluster may lead to cumulative negative impacts on surrounding.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes Dadra and Nagar Haveli Wildlife Sanctuary ~ 3 Km
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes • Damanganga Reservoir - 4.6 Km • Patches of Reserved forests - 2.5 Km • Vasona Lian safari - 7.0 Km • Satmalia Deer Park - 6.2 Km
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No --
4 Inland, coastal, marine or underground waters Yes Damanganga Reservoir - 4.6 Km
5 State, National boundaries Yes Gujarat State - 3.55 Km Maharastra State - 6.50 Km
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes NH 8B - 13 Km SH 18A - 0.5 Km
7 Defence installations No --
8 Densely populated or built-up area Yes Silvassa - 4 Km
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Primary, Secondary schools & Hospitals - Between 5 to 10 km
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Yes • Groundwater resources - None • Surface resources: River Damanganga - 6.5 Km • Forestry: Patches of Reserves forests- 1.5 -2.5 Km • Agriculture: agricultural activities in nearby villages- 2-4 Km • Tourism: Gardens & monuments- 2-5 Km
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No --
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No • The project site falls under Zone 3 as per the Seismic zone map of India, which is a moderate risk zone. • No subsidence, landslides, erosion or extreme climatic conditions observed in the past.
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantSaha
DesignationSenior Vice president
Name of Company (Applicant Name should not be given here)AYM SYNTEX LIMITED
AddressSurvey No. 394/P, Village-Saily, Silvassa, U.T. Of Dadra and Nagar Haveli
Print