APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Expansion of “Proposed In-Situ Development” at Kathputli Colony, Near Shadipur Depot, New Delhi | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/DL/NCP/80303/2018 | Project Cost | 73902 lacs | |
| 2. | |
S. No. in the schedule | 8(b) Townships and Area Development projects.
| Project Sector | INFRA-1 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 380929.71 ha. | | 4. | New/Expansion/Modernization | Expansion | Proposal Number | IA/DL/NCP/80302/2012 | MoEFCC file number(Previous EC) | 620 | Uploaded EC letter | Annexure-Uploaded EC letter | | | 5. | Existing Capacity/Area etc. | 20.06 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | at Kathputli Colony, Near Shadipur Depot, New Delhi | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | at Kathputli Colony, Near Shadipur Depot, New Delhi | Town / Village | at Kathputli Colony, Near Shadipur Depot, New Delhi | State of the project | Delhi | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Delhi | West | Patel Nagar | | 10. | |
Nearest railway station along with distance in kms | Patel Nagar Railway Station, 0.67 km | Nearest airport along with distance in kms | IGI Airport, 9.52 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Kirti Nagar , 0 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | NA | | 13. | Name of the Applicant | Abhinav | | 14. | Registered Address | W4D, 204/5, Keshav Kunj, Carippa Marg, Western Avenue, Sainik Farms, New Delhi-110062 | | 15. | |
Address for correspondance: | Name of the Company | RAHEJA DEVELOPERS LTD. | Name of the Applicant | Abhinav | Designation (Owner/ Partner/ CEO) | DM | Pin code | 110062 | E-mail | rahejadeveloper01@gmail.com | Telephone No. | 011-40611111 | Fax No. | 011- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | NIL | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | No | Proposed development is as per Delhi Master Plan 2021 | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | Tree cutting is involved in this project. There are 79 trees are available on site. Out of which 20 trees will be cut for which permission from Forest Department has been obtained & 59 trees will be retained. Compensatory plantation will be done per norms of Forest Department | 1.3 | Creation of new land uses? | No | No new land use is proposed. The proposed site is for residential development. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Soil testing investigation has already been done. | 1.5 | Construction works? | Yes | The major construction works are given below:
Site Development
Road Development
• Internal roads
Utilities/Services
• Water Supply
• Sewerage
• Drainage
• Rain Water Harvesting Structures and Pits
• Power supply and back up facility,
Buildings
• Remunerative Residential block
• Remunerative Commercial block
• EWS
. | 1.6 | Demolition works? | No | Any type of demolition work is not involved in expansion project. | 1.7 | Temporary sites used for construction works or housing of construction workers? | Yes | Mostly, local labors will be employed. However temporary labor camps will be established for laborers during the construction stage. All the construction activities including storage of raw materials will be confined to the storage spaces earmarked on project site only. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | Above ground building structures will include building of 4B+G/ST/PO+40.
The earthwork involved for foundation and basement. | 1.9 | Underground works including mining or tunnelling? | Yes | Underground works includes excavation of earth for construction of foundation and basement etc. | 1.10 | Reclamation works? | No | Not applicable | 1.11 | Dredging? | No | Not applicable | 1.12 | Offshore structures? | No | Not applicable | 1.13 | Production and manufacturing processes? | No | Not applicable | 1.14 | Facilities for storage of goods or materials? | Yes | Temporary storage facilities will be created during construction phase for storage of construction materials. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Solid Waste
Construction Stage :
The construction stage solid waste will comprise mainly of construction waste. The construction debris generated will be reused within the site for various construction works.
In addition to that there will be generation of small quantity of municipal waste from 280 (175 camp and 105 floating) construction labors. It will be ensured that the generated waste will be sent to nearest designated waste storage bins.
Operation Stage:
Solid waste generation | 1.16 | Facilities for long term housing of operational workers? | No | Not Applicable | 1.17 | New road, rail or sea traffic during construction or operation? | Yes | Road traffic is expected to be increased marginally during construction and operation phases of the project. No significant impact is anticipated on road and rail traffic due to construction of this complex. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Existing road network will be used. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Not Applicable | 1.20 | New or diverted transmission lines or pipelines? | No | Not Applicable | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not Applicable | 1.22 | Stream crossings? | No | Not Applicable | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Main source of water is municipal water supply augmented with the water supply from Delhi Jal Board. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | By considering run off prior to development & run off after development there is some increment in storm water runoff. However runoff generated from the project site during monsoon season will be recharged to ground water aquifer. Network of drainage system developed in the site will be used to collect roof as well as surface runoff. | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | During construction phase transport of personnel as well as construction materials would be required. The personnel would preferably be engaged from nearby areas. Precaution will be taken to reduce the impact of vehicular movement by trying to avoid the vehicular trips during peak hours. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not Applicable | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | Yes | Minor and temporary impacts on environment are anticipated due to the increased traffic | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | Construction phase –
Temporary influx of about 280 labors (175 camp and 105 floating) from the nearby areas is expected.
Operation phase (For complete project) – 18284 persons residential + 9951 persons floating. | 1.29 | Introduction of alien species? | No | Not Applicable | 1.30 | Loss of native species or genetic diversity? | No | Not Applicable | 1.31 | Any other actions? | No | Not Applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | Land use of proposed site is residential as per Delhi Master plan 2021. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Main source of water supply is municipal water supply by Delhi Jal Board. | 2.3 | Minerals (MT) | No | Not Applicable | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | All materials for construction will be arranged by nominated contractors / suppliers. | 2.5 | Forests and timber (source – MT) | Yes | Negligible quantity (only at selected locations) | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Complete project will need 9538 KW of electricity. Developer will provide D.G sets of 5090 KVA for complete project for power backup in case of electricity failure. | 2.7 | Any other natural resources (use appropriate standard units) | No | Not Applicable | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | No storage of hazardous chemicals (as per MSIHC rules) will be made, apart from limited quantity of HSD storage (for DG set operation). | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Suitable drainage and waste management measures will be adopted to restrict stagnation of water & accumulation of waste. This will effectively restrict the reproduction and growth of disease vectors. | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | This is a rehabilitation colony specially for people living in jhuggis. It will raise the living standard of those peoples. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Not Applicable | 3.5 | Any other causes | No | Not Applicable | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | Excavated top soil will be properly stacked; it will be reused as top layer for horticulture development. Remaining soil will be used for site leveling, back filling/filling in raft and road construction. | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Construction Phase:
Municipal solid waste – Total 68.25 kg/day of waste, 52.50 kg/day (from labor camp) and 15.75 kg/day (floating labor)
Operation Phase:
Municipal solid wastes – 12.7 TPD
The solid waste includes paper, card board, plastic cans etc. and kitchen wastes from houses. Recyclable wastes like card boards and plastic cans will be sold to authorized vendors.
Biodegradable waste will be treated in onsite OWC. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Waste oil 7.77 Lts on daily basis from DG sets will be the only hazardous waste generated from the project. This waste oil will be carefully stored in HDPE drums in isolated covered space and sold to recycler authorized by CPCB/SPCB.
Suitable care will be taken to prevent spills/ leaks of used oil from storage. | 4.4 | Other industrial process wastes | No | Not Applicable | 4.5 | Surplus product | No | Not Applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Dried sludge from the STP will be used as manure for horticulture development. Surplus manure will be sold to farmers. | 4.7 | Construction or demolition wastes | Yes | Most of construction waste will be used in building construction. | 4.8 | Redundant machinery or equipment | No | Not Applicable | 4.9 | Contaminated soils or other materials | No | Not Applicable | 4.10 | Agricultural wastes | No | Not Applicable | 4.11 | Other solid wastes | No | Not Applicable | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Emission will be from
Stationary Sources: DG sets
Mobile Sources: Vehicular emissions
CPCB approved DG sets with acoustic canopy will be used only during power failure. | 5.2 | Emissions from production processes | No | Not Applicable | 5.3 | Emissions from materials handling including storage or transport | Yes | Emissions from the vehicles/ machinery used for the construction. | 5.4 | Emissions from construction activities including plant and equipment | Yes | Slight emissions from welding activities and working of construction equipment/ machinery shall be complied with PUC certificate only. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | The project may cause rise in dust levels during construction phase. Precautions would be taken to reduce dust generation during construction phase:
• Use of RMC to reduce material handling & dust generation.
•Tarpaulins will be used to cover trucks carrying debris.
Water sprinkling will be practiced at regular intervals to reduce dust emissions.
Dust generated during operation stage shall be minimal due to vegetated & hard surface. Sewage generated from proposed project will be treated | 5.6 | Emissions from incineration of waste | No | Not Applicable | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not Applicable | 5.8 | Emissions from any other sources | No | Not Applicable | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Noise is expected to be generated during construction phase mainly from operation of heavy machinery, DG sets, and traffic. The indicated noise levels from certain construction plants/equipment are indicated below:
Concrete Mixer - 85 dBA
Generator - 75 dBA
Pumps -90 - 95 dBA
Trucks - 85 – 90 dBA
For control of noise following measures shall be adopted:
Properly maintained equipment with mufflers will be used.
High noise generating | 6.2 | From industrial or similar processes | No | Not Applicable | 6.3 | From construction or demolition | Yes | Noise Pollution Control: Noise pollution will be due to operation of machinery as well as transportation vehicles. Following precautions shall be taken to control noise pollution :
High noise generating construction activities would be carried out only during day time.
Installation, use and maintenance of mufflers on equipment.
Workers working near high noise construction machinery would be supplied with ear muffs/ear plugs. | 6.4 | From blasting or piling | No | Not Applicable | 6.5 | From construction or operational traffic | Yes | Traffic will increase due to the use of vehicles by visitors.
Noise levels due to vehicles will be there. To reduce the noise level green belts and tree shall be there which shall act as good noise absorbers. | 6.6 | From lighting or cooling systems | No | Not Applicable | 6.7 | From any other sources | No | Not Applicable | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | The waste oil generated during operation phase from the DG sets will be collected and separately stored in HDPE drums over concrete floor within the premises before final disposal. All precautionary steps will be taken to avoid spillage It will be directly transferred to authorized recyclers. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | Generated Sewage from the project will be treated in the STP proposed onsite, and recycled within the proposed project facility for flushing, gardening, HVAC & DG cooling. | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | Dust generation during construction phase from earthworks and movement of vehicles was a temporary phenomenon and will have short term impact during construction phase.
Appropriate fugitive dust control measures, including water sprinkling of exposed areas and dust covers for trucks, will be provided to minimize any impacts.
DG exhaust will be discharged at height stipulated by CPCB. Height of stack will be as per CPCB norms. | 7.4 | From any other sources | No | Not Applicable | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | STP will be installed to treat the waste water. Treated effluent will be used for flushing, horticultural purposes, HVAC & DG cooling. | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | During construction phase, no such risk is anticipated. However, the contractors shall comply with the safety procedures, norms and guidelines as applicable) mentioned in the National Building Code of India and Bureau of Indian Standards.
During Operation Phase, all precautionary and safety measures will be taken to minimize any accident hazard. | 8.2 | From any other causes | No | Nil | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | The project site falls in Seismic Zone-IV. The architectural and structural design of buildings will comply earthquake resistant requirement as per code.
Chances of Floods are very less.
Landslides and cloud bursting in the area not reported so far. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | The project will be equipped with dedicated internal road, parking, internal water distribution system, fire fighting system, internal sewage collection network, lighting facilities, solar lighting, and power backup facility.
Increase in water and power demand.
Appropriate infrastructure like, roads, power supply and waste management facility will be developed within the site so that chances of occurrence of any adverse impacts are minimized.
No
Construction materials
No | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not Applicable | 9.3 | Set a precedent for later developments | Yes | This is residential/ Commercial development; there will be generation of employment during construction & operation phase. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | Yes | Impacts on water availability, storm water drainage, availability of electricity, traffic congestion etc. | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | Yes | Central Ridge, 2.84 km/S | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Yamuna River: 8.48 km, E
Drain, 1.45 km, N | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | Yes | Central Ridge, 2.84 km/S | 4 | Inland, coastal, marine or underground waters | No | Not located within 15 km of the proposed project location. | 5 | State, National boundaries | Yes | Delhi- U.P. border, 13.91 km, NE | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | The site does not fall under any route to any pilgrim, tourist or recreational area. | 7 | Defence installations | No | Not located within 15 km of the proposed project location. | 8 | Densely populated or built-up area | No | Density of Surrounding development is as per Delhi Master Plan. | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Manmade community facilities such as, schools, hospitals are planned but are not close to the site. | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | The project site does not fall in the notified areas for control and regulation of ground water. There will be no extraction of ground water from the project site, the fresh water will be sourced from Delhi Jal Board. | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | Nothing specific | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | Yes | The project is located at seismic zone IV according to Indian Standard Seismic Zoning Map. Structural design will be done for this seismic zone as per code.
There are no possibilities of the proposed project site getting flooded as per available records.
Landslides are not applicable as the project site & surrounding land is flat. | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Abhinav | Designation | DM | Name of Company (Applicant Name should not be given here) | RAHEJA DEVELOPERS LTD. | Address | W4D, 204/5, Keshav Kunj, Carippa Marg, Western Avenue, Sainik Farms, New Delhi-110062 |
| |
|