APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Development of Commercial Building as LP-1B-03 at Gateway District of Aerocity, IGI Airport, New Delhi
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/DL/NCP/76088/2018
Project Cost ..... lacs
2.
S. No. in the schedule8(b) Townships and Area Development projects.
Project Sector INFRA-1
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled Proposed Built up area: 4,29,214 sq m ha.
4.
New/Expansion/ModernizationNew
5. Existing Capacity/Area etc. 00 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectAt Plot No. LP-1B-03, Gateway District, Aerocity, Indira Gandhi International Airport, New Delhi
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.Plot No. LP-1B-03
Town / VillageNA
State of the projectDelhi
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)DelhiSouth WestDelhi Cantonment.
10.
Nearest railway station along with distance in kms Delhi Cantonment, 3.8 km
Nearest airport along with distance in kms Indira Gandhi International Airport, 0.6 km
11. Nearest Town/City/District Headquarters along with distance in kms Within Delhi , 0 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) South Delhi Municipal Corporation
13. Name of the Applicant Aman
14. Registered Address New Udaan Bhawan, opp. Terminal 3, Indira Gandhi International Airport, New Delhi
15.
Address for correspondance:
Name of the Company DELHI INTERNATIONAL AIRPORT LIMITED
Name of the Applicant Aman
Designation (Owner/ Partner/ CEO) CEO
Pin code 110037
E-mail rekibuddin.ahmed2@gmrgroup.in
Telephone No. 011-47197251
Fax No. 011-
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No As per approved Master Plan for Delhi - 2021 (Approved by Delhi Development Authority vide Resolution No. 142/2006 dated 19th January, 2007), the project area is demarcated as "AIRPORT". As per the Airport Master Plan, the Project Site is designated as "Commercial Zone".
1.2 Clearance of existing land, vegetation and buildings? Yes The project site consists of mainly shrubs, bushes and grasses and requires clearance prior to start of construction. Tree survey of entire area is ongoing and the outcome of the survey will decide if any tree needs to be relocated/cut. The project site is devoid of any existing building.
1.3 Creation of new land uses? No As per approved Master Plan for Delhi - 2021 (Approved by Delhi Development Authority vide Resolution No. 142/2006 dated 19th January, 2007), the project area is demarcated as "AIRPORT". As per the Airport Master Plan, the Project Site is designated as "Commercial Zone".
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Soil investigation has been carried out.
1.5 Construction works? Yes The major construction works are given below: Site Development Road Development • Internal roads Utilities/Services • Water Supply • Sewerage • Drainage • Rain Water Harvesting Structures and Pits • Power supply and back up facility • Waste management facility Buildings • Commercial • Parking Provisions
1.6 Demolition works? No Not applicable.
1.7 Temporary sites used for construction works or housing of construction workers? Yes Storage of construction materials will be confined within the project site and at designated place. Small area within the proposed project site will be utilized for project office temporarily. No separate housing facilities for construction workers are envisaged.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Above ground building structures will include building for commercial activity. The earthwork is involved for foundation, construction of basements and laying of underground services etc. Excavated soil will be used for site leveling, back filling/filling and road construction. Top 200 mm layer of soil be used for landscaping/horticulture development work.
1.9 Underground works including mining or tunnelling? No Not applicable.
1.10 Reclamation works? No Not involved.
1.11 Dredging? No Not involved.
1.12 Offshore structures? No Not involved.
1.13 Production and manufacturing processes? No This is a commercial activity project.
1.14 Facilities for storage of goods or materials? Yes Temporary storage facilities will be created during construction phase for storage of construction materials.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Solid Waste Construction Stage : Solid waste will comprise mainly of construction waste. The construction waste will be reused within the site for various constructions filling work. In addition to that there will be generation of small quantity of municipal waste from construction labors. It will be ensured that the generated waste will be handled as per solid waste management rules 2016. Operation Stage: Solid waste generation from the facility will be approximately 5.54 TPD including
1.16 Facilities for long term housing of operational workers? No Not applicable
1.17 New road, rail or sea traffic during construction or operation? No Not applicable.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Not applicable.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Not applicable.
1.20 New or diverted transmission lines or pipelines? No Not applicable.
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No Not applicable.
1.22 Stream crossings? No Not applicable.
1.23 Abstraction or transfers of water from ground or surface waters? No Not Envisaged.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No There will be no change in water bodies, as there are no water bodies in the nearby vicinity of the proposed project activity.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes During construction phase transportation of personnel as well as construction materials will be involved.
1.26 Long-term dismantling or decommissioning or restoration works? No Not applicable
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No Not applicable
1.28 Influx of people to an area in either temporarily or permanently? Yes Construction phase – Temporary influx from the nearby areas is expected. The project will generate direct and indirect employment opportunities for the local population during both the construction and operation phases.
1.29 Introduction of alien species? No Not applicable.
1.30 Loss of native species or genetic diversity? Yes The vegetation within the project site consists of shrubs, bushes and grass which will be cleared prior to start of construction activity. Tree survey of entire area is ongoing and the outcome of the survey will decide if any tree needs to be relocated/cut.
1.31 Any other actions? No None
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No The proposed project site is undeveloped commercial land.
2.2 Water (expected source & competing users) unit: KLD Yes Water demand will be met from Delhi Jal Board (DJB). Treated water from STP installed at Site will be used for irrigation, flushing and HVAC purpose.
2.3 Minerals (MT) No Not applicable
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Construction materials such as Cement, Steel, Bricks, Stone aggregates, and Sand would be required for the project. These will be preferably procured from local reputed licensed vendors.
2.5 Forests and timber (source – MT) Yes Limited use of timber will be done and it will be restricted to selected locations.
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Power for the proposed project will be supplied by BSES Rajdhani. Maximum power Demand for the proposed project is 16000 kVA. DG sets 3000 KVA will be used as power backup during power failure. HSD (ultra low sulphur variety as per availability) fuel will be used for DG sets.
2.7 Any other natural resources (use appropriate standard units) No Not Applicable.
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes During construction & operation stage hazardous materials such as – Paints, oils & lubricants will be used. Waste generated from these materials will be managed in accordance with “The Hazardous Waste Management, Handling & Transboundary Movement (Amendment) Rules, 2016".
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Not applicable.
3.3 Affect the welfare of people e.g. by changing living conditions? No Proposed project and development activities will enhance employment opportunities of local people.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Not applicable.
3.5 Any other causes No Not applicable.
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No The excavated soil will be used for site leveling, back filling/filling in raft and road construction. There would not be surplus earth.
4.2 Municipal waste (domestic and or commercial wastes) Yes Operation Phase: The project is expected to generate Municipal solid wastes – 5.54 TPD during its operation phase. It will be ensured that the generated wastes are handled as per solid waste management rules 2016. Solid waste generated from the commercial building and other areas will be collected in Twin bin systems for segregation at sources. Recyclable wastes will be sold to vendors and non- recyclable wastes will be disposed through authorized agency to municipal waste disposal site.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes It is estimated that waste oil from DG sets will be the only hazardous waste generated from the project. Hazardous waste generated on site will be managed as per Hazardous and other wastes (management and transboundary movement) rules, 2016 and handed over to authorized recyclers.
4.4 Other industrial process wastes No Not applicable
4.5 Surplus product No Not applicable
4.6 Sewage sludge or other sludge from effluent treatment Yes It is estimated that 595.22 kg/day of sewage sludge will be generated which will be used as manure for plants and surplus manure will be sold to the farmers/ nursery.
4.7 Construction or demolition wastes Yes Construction Work: Excavated soil will be used for back filling. Other construction waste like bricks, concrete etc will be used in pavement & road works/manholes, cinder filling etc. Gunny bags if any, cardboards will be sent to authorize recycler. The inert waste will be sent to land fill site. For any type of C&D waste- Construction & Demolition Waste Management Rules, 2016 will be followed.
4.8 Redundant machinery or equipment No Not applicable
4.9 Contaminated soils or other materials No Not applicable
4.10 Agricultural wastes No Not applicable
4.11 Other solid wastes No Not applicable
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Emission will be from ? Stationary Sources: DG sets of 3000 KVA ? Mobile Sources: Vehicular emissions CPCB approved DG sets with acoustic canopy will be used only during power failure.
5.2 Emissions from production processes No Not applicable
5.3 Emissions from materials handling including storage or transport Yes Dust emission due to material handling and loading - unloading of fine materials like sand, cement activities is envisaged during construction phase of the project. These will be controlled by good housekeeping, sprinkling water in the dust prone areas, providing paved roads and proper fencing. Adequate camouflaging will be done at the construction sites.
5.4 Emissions from construction activities including plant and equipment Yes Mostly particulate matter is envisaged during construction activities which will be restricted to site area. However regular sprinkling of water, restriction on speed of vehicles measures will be taken to mitigate impact.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Mostly particulate matter is envisaged during construction activities which will be restricted to site area. The project may cause rise in dust levels during construction phase. Precautions would be taken to reduce dust generation during construction phase: • RMC use will reduce the handling of cement, sand and concrete thus dust emission will be minimized. • Tarpaulins will be used to cover trucks carrying materials. • Water sprinkling will be practiced at regular intervals to reduce dust em
5.6 Emissions from incineration of waste No Not applicable
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Not envisaged.
5.8 Emissions from any other sources No Not envisaged.
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Noise is expected to be generated during construction phase mainly from operation of heavy machinery, DG sets, and traffic. For control of noise following measures shall be adopted: • Properly maintained equipment with mufflers will be used. • High noise generating construction activities would be carried out only during day time. In order to reduce impact workers working near high noise construction machinery would be issued ear muffs/ear plugs. Duration of operation & tim
6.2 From industrial or similar processes No Not applicable as this is Commercial development project.
6.3 From construction or demolition Yes Construction activities generate noise but these will be limited to construction site only
6.4 From blasting or piling No Blasting & piling work is not involved in the project.
6.5 From construction or operational traffic Yes Construction Phase Noise will be generated due to vehicular movement for supply of building materials and other construction activities. But duration & intensity will be less. Construction activity will not be carried out during night time as far as possible Operation Phase Noise will be generated due to vehicular movement Traffic management plan is targeted to regulate speed & ensure smooth movement of vehicles within the project site to reduce noise levels. Vegetated surfaces & plantation
6.6 From lighting or cooling systems No Nil.
6.7 From any other sources No Not Applicable.
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No During construction & operation stage hazardous materials such as – Paints, oils & lubricants will be used. Generated hazardous waste will be managed as per Hazardous Waste Management, Handling & Transboundary Movement (Amendment) Rules, 2016". Spillage if any will be collected in a pit through a garland drain built for this purpose. The pit will have a provision of oil & grease separator.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No Sewage will be generated from the project which will be treated in the STP proposed onsite. Treated water from STP shall be and recycled for reuse for flushing & HVAC.
7.3 By deposition of pollutants emitted to air into the land or into water No Emission of pollutants in the form of particulate matters, SOx, NOx, CO, HC etc. will be from the operation of DG sets Adequate stack height will be provided as per CPCB norms to disperse pollutants effectively. DG sets will be used only in case of power failure. Dust generation during construction phase from earthworks and movement of vehicles is a temporary phenomenon and will have short term impact during construction phase. Appropriate fugitive dust control measures, including
7.4 From any other sources No Nil
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Long term built up of pollutants is not envisaged.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No During construction phase, no such risk is anticipated. However, the contractors shall comply with the safety procedures, norms and guidelines as applicable) mentioned in the National Building Code of India and Bureau of Indian Standards. During Operation Phase, all precautionary and safety measures will be taken to minimize any accident hazard.
8.2 From any other causes No Nil
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No The area has no history of natural disasters such as Floods, landslides, cloudburst etc. The site lies in Seismic Zone IV. The construction will be carried out as per the guidelines prescribed for Seismic Zone IV. All the civil structures will be seismically resistant and designed in accordance with provisions recommended related IS codes: IS 4326: 1993 IS 1893 (Part I),2002
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes Effective utility management programs will be followed. All basic infrastructure facilities will be developed for the proposed project. No Proposed project will further have positive impact on locality through direct and indirect economic benefits. No
9.2 Lead to after-use of the site, which could have an impact on the environment No No
9.3 Set a precedent for later developments No Not envisaged.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No Not envisaged.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes Rashtrapati Bhawan: 10.3 Km NE Parliament House: 11.1 Km NE India Gate: 12.3 Km NE Qutub Minar: 6.6 Km SE National Zoological Park: 13.3 Km NE
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Yamuna River: 14.2 KM NE Najafgarh Drain: 9 KM NW Forest Central Ridge Reserve Forest: 10.04 Km NE Pusa Hill Forest: 10.09 Km NE Southern Ridge Forest: 9.85 Km NE Rajokri Protected Forest: 3.32 Km SE
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration Yes Asola Wild Life Sanctuary: 14.73 Km SE
4 Inland, coastal, marine or underground waters No Nil
5 State, National boundaries Yes Delhi Haryana border is at 5.4 km SW
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes NH-48: 0.23 KM SE NH-2: 13.5 KM E NH-24: 13.8 KM NE NH-236: 6.6 KM SE NH-10: 13.4 KM N Nearest Railway Station: New Delhi Railway Station: 13.5 KM NE Airport: Indira Gandhi International Airport: Adjacent to IGI Airport
7 Defence installations Yes National Defense Collage: 10.96 Km NE Air Force station and cantonment area : 14.27 Km SE
8 Densely populated or built-up area Yes Density of surrounding development is as per master plan
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Manmade community facilities such as, schools, places of places of worship exist, but are not close to the site. These installations will not have any impact due to construction of proposed project.
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No Nil.
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No Nothing specific
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects Yes The project is located at Seismic Zone-IV according to Indian Standard Seismic Zoning Map. Structural design will be done for this seismic zone as per code. There are no possibilities of the proposed project site getting flooded and landslides as per available records.
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantAman
DesignationCEO
Name of Company (Applicant Name should not be given here)DELHI INTERNATIONAL AIRPORT LIMITED
AddressNew Udaan Bhawan, opp. Terminal 3, Indira Gandhi International Airport, New Delhi
Print