APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Iron Ore Beneficiation (1.2 MTPA) at Village - Kunkuni, Tehsil - Kharsia, District - Raigarh, Chhattisgarh by M/s Vedanta Washery & Logistic Solutions Pvt Ltd. | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/CG/IND/100786/2019 | Project Cost | 1200 lacs | |
| 2. | |
S. No. in the schedule | 2(b) Mineral beneficiation
| Project Sector | Industrial Projects - 1 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 1.2 MPTA ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 0 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Village - Kunkuni, Tehsil - Kharsia, District - Raigarh, Chhattisgarh | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | Village-Kunkuni, Tehsil-Kharsia, District-Raigarh, Chhattisgarh | Town / Village | Village-Kunkuni, Tehsil-Kharsia, District-Raigarh, Chhattisgarh | State of the project | Chhattisgarh | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Chhattisgarh | Raigarh | Kharsia | | 10. | |
Nearest railway station along with distance in kms | Robertson Railway Station, 0.50 km | Nearest airport along with distance in kms | Swami Vivekananda International Airport, 170 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Raigarh , 24.4 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Gram Panchayat Kunkuni | | 13. | Name of the Applicant | Surya | | 14. | Registered Address | Robertson SEC Rly at NH-49, Village-kunkuni, Kharsia | | 15. | |
Address for correspondance: | Name of the Company | VEDANTA WASHERY AND LOGISTIC SOLUTIONS PVT LIMITED | Name of the Applicant | Surya | Designation (Owner/ Partner/ CEO) | Director | Pin code | 496661 | E-mail | vedantaironore@gmail.com | Telephone No. | 0120-4044630 | Fax No. | 0120- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | Land acquired for the proposed project is barren and semi-agricultural, more or less plat without many undulations, however the land use of the same will be change for industrial purpose. Total land is in possession of the management. Hence there will not be any change in local land use plan due to the proposed project. | 1.2 | Clearance of existing land, vegetation and buildings? | No | The land earmarked for the proposed project is more or less flat without many undulations, without any buildings and vegetation. Hence no clearance of buildings and vegetation will be required for proposed project. | 1.3 | Creation of new land uses? | Yes | There will be creation of new land use due to construction of proposed Iron ore beneficiation plan. This will be achieved by proper landscaping/ plantation around the boundary walls at suitable patches within the boundary complex. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Soil testing is envisaged for safe design of civil and engineering structures. | 1.5 | Construction works? | Yes | Following construction works will be undertaken within the proposed site of after obtaining the prior Environmental clearance from MoEFCC, GoI, New Delhi & Permission to Establish from Chhattisgarh Environment Conservation Board | 1.6 | Demolition works? | No | The land is free from any structure and, therefore, no demolition work is involved in construction and operation of the washery | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | There is no requirement of temporary for construction workers as the same are easily form the nearly villages. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | Most of the structures in the plant will be above the ground. However excavations will be involved for foundations | 1.9 | Underground works including mining or tunnelling? | No | No underground works is involved as no mining or tunneling activities is proposed. | 1.10 | Reclamation works? | No | No Reclamation works is required. | 1.11 | Dredging? | No | No Dredging activities will be involved. | 1.12 | Offshore structures? | No | No offshore structures are envisaged in the
proposed activity | 1.13 | Production and manufacturing processes? | No | It’s a Iron ore beneficiation plan project. Only washing & grinding will be done. | 1.14 | Facilities for storage of goods or materials? | Yes | All the materials, Finished Goods, Wastes are stored under covered sheds having RCC flooring guarded by Garland Drains. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Closed circuit water system will be adopted in the proposed unit. Hence there will not be any wastewater generation from the process. However only wastewater generated will be sanitary wastewater i.e. 3.0 m3/ day; which will be treated through Septic Tanks followed soak pits. | 1.16 | Facilities for long term housing of operational workers? | No | No Housing facilities or colony is provided in the plant premises. | 1.17 | New road, rail or sea traffic during construction or operation? | Yes | New Railway siding is envisaged for the proposed Iron ore beneficiation plant to be served from Robertson Railway Station. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | Yes | New Railway siding is envisaged for the proposed Iron ore beneficiation plant to be served from Robertson Railway Station. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | No closure or diversion of transport routes or infrastructure is envisaged in the proposed project. | 1.20 | New or diverted transmission lines or pipelines? | No | No new or diversion of transmission line. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | No culverting, realignment are envisaged. There will not be any changes to the hydrology of watercourses or aquifers. | 1.22 | Stream crossings? | No | No stream crossing is involved. | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Water required for the proposed project will be met from Ground water. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | Yes | No changes in water bodies, drainage and land surface are anticipated, as the site is more or less flat without many undulations | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | A few vehicles will be provided for transport of personnel during construction of the plant. Construction materials will be transported in covered trucks. The road is capable of handling the additional vehicular traffic during the operation of the proposed project. New Railway siding is envisaged for the proposed project | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | No such works are envisaged. | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | No such works are envisaged. | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | During construction local people will be involved. During operation of the plant preference will be given to the local people for employment. | 1.29 | Introduction of alien species? | No | No such activity is envisaged | 1.30 | Loss of native species or genetic diversity? | No | As a part of greenbelt development plan native species that are suitable to that soil condition will be developed in consultation with DFO as per CPCB Guidelines. | 1.31 | Any other actions? | No | Not applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | Total land envisaged for the proposed project is 15.630 Hect and same is in possession of management.
33% of the total project area, will be developed with Greenbelt. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Total water for entire project will be 700 KLD.Water required will be sourced from the Ground water. Permission will be obtained from the CGWA for drawl of Ground Water. | 2.3 | Minerals (MT) | Yes | 1.6 MTPA of ROM iron ore will be required per/year | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Construction material (stone, aggregates, and/soil) required for the construction will be purchased from the local market. | 2.5 | Forests and timber (source – MT) | No | Not applicable | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | There is no requirement of any type of fuel for the operation of proposed unit; however Power required for operation of shall be drawn from CSEB Grid. | 2.7 | Any other natural resources (use appropriate standard units) | No | Not applicable | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | None | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | The effluent will be completely recycled. Zero effluent discharge will be maintained. All environmental regulations will be followed in the proposed project. Hence no Water borne diseases are anticipated due to the proposed plant. | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | The Population in surrounding area will get benefited due to infrastructural and community development activities. Further, the proposed project will provide job opportunities. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | The effluent will be completely recycled. Zero effluent discharge will be maintained. All environmental regulations will be followed in the proposed project. Hence no adverse impact on hospitals, children, elderly persons. | 3.5 | Any other causes | No | Not applicable. | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | The dug soil during excavation will be used for filling of low-lying areas. | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Disposed off as per norms | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | No | No such material will be generated | 4.4 | Other industrial process wastes | Yes | Tailing will be generated from the Iron ore beneficiation unit. Tailing will be given to cement plant and ceramic industries. | 4.5 | Surplus product | No | Not Applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Disposed as per norms. | 4.7 | Construction or demolition wastes | Yes | Construction wastes will be disposed off as per guidelines (Construction and Demolition Waste Management Rules, 2016) | 4.8 | Redundant machinery or equipment | No | No redundant machinery will be kept in the premises. | 4.9 | Contaminated soils or other materials | No | There will be no contamination of soil or any other material. | 4.10 | Agricultural wastes | No | No such generation | 4.11 | Other solid wastes | No | No such generation | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | There is no consumption of fossil fuels for production activity; however there will movement of vehicles for inward and outward for transportation of raw materials and finished products. | 5.2 | Emissions from production processes | Yes | Dust laden flue gases from will be passed through Bag Filters and thereafter cleaned gases will be vented in to atmosphere through Stack of adequate height as per norms of CPCB. | 5.3 | Emissions from materials handling including storage or transport | Yes | Dust will be emanated due to loading, unloading of iron ore fines.
Fugitive emission; that will be reduced by deployment of dust extraction system by installing Bag Filters at all the strategic Locations etc. | 5.4 | Emissions from construction activities including plant and equipment | Yes | Some dust emissions will be generated during construction. Water spraying system and dust curtains will be deployed to prevent the dust emanation due to construction Activities. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust will be emanated due to loading, unloading of iron ore fines.
Fugitive emission; that will be reduced by deployment of dust extraction system by installing Bag Filters at all the strategic Locations etc. | 5.6 | Emissions from incineration of waste | No | Not applicable | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not applicable | 5.8 | Emissions from any other sources | No | Not applicable | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | All machinery will be manufactured as per OSHA/MOEFCC guidelines. Flexible rubber plates are provided at the mounting of machines to absorb vibrations as to reduce noise. Earplugs will be provided to workers working in the noise prone areas. Ambient noise levels will be in accordance with MOEF notification dated 14-02-2000 i.e. noise levels will be < 75 dB (A) during daytime and < 70 dB (A) during night time. | 6.2 | From industrial or similar processes | Yes | All machinery will be manufactured as per OSHA/MOEFCC guidelines. Flexible rubber plates are provided at the mounting of machines to absorb vibrations as to reduce noise. Earplugs will be provided to workers working in the noise prone areas. Ambient noise levels will be in accordance with MOEF notification dated 14-02-2000 i.e. noise levels will be < 75 dB (A) during daytime and < 70 dB (A) during night time. | 6.3 | From construction or demolition | Yes | Construction equipment will cause some noise. Earplugs will be provided to construction workers who work near the noise generating equipment. | 6.4 | From blasting or piling | No | No such operations are involved. | 6.5 | From construction or operational traffic | Yes | Vehicles used by construction staff are minimal. The noise levels will be in accordance with MoEFCC notification dated 14-02-2000 & its amendment as on date. | 6.6 | From lighting or cooling systems | No | No heavy noise will be generates by the process. | 6.7 | From any other sources | No | No other source envisaged. | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | Good housekeeping practice will be maintained. This will eliminate any spillages. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | Closed circuit cooling system will be adopted in the proposed project. Sanitary wastewater will be treated in septic tank followed by soak pit. There will be no Effluent discharge outside plant premises and all the generated effluent will be recycled/ reused. Hence we will follow ZERO discharge norms all time throughout the year. | 7.3 | By deposition of pollutants emitted to air into the land or into water | Yes | Generation of dust during the process will be suppressed by water spraying or sprinkling. All the fugitive emission sources will be facilitates with water suppression system. All possible measures will be adopted for abatement of pollution | 7.4 | From any other sources | No | Not applicable | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Not applicable | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | LDO will be stored in MS tanks with Dyke wall arrangement. All the Oil Industry Safety Directorate (OISD) guidelines will be followed. Hence there will not be any thermal impact on outside population due to the proposed Project. | 8.2 | From any other causes | No | Not applicable. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | Not applicable. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| No | No such activities are envisaged. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not Applicable | 9.3 | Set a precedent for later developments | Yes | With the improvement in the socio-economic status of the people in the area, later developments are expected. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | Yes | The effects of other industries in the area will be considered. | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | No such area falls under vicinity. | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Forests in 10 km Area:
Rabo RF -5.4 KM-North
Endu Rf – 8.65 KM- NNW
Bargarh RF – 4.5 KM - NW | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | There is no wildlife sanctuary or national park within 10km are of the site. | 4 | Inland, coastal, marine or underground waters | Yes | Mand River – 2.8 KM – NE
Kurket River – 8.6 KM – NE | 5 | State, National boundaries | No | No State and National border come in the vicinity of the plant. | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | No route comes under the plant area that will be utilized by the public as accesses to recreation or other tourist, pilgrim area. | 7 | Defence installations | No | There is no defense installation within the vicinity. | 8 | Densely populated or built-up area | Yes | Town – Kharsia, 6.25 km towards West. | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Maa Kali Mandir – 2.4 KM – WSW
Academic Brigh Public School – 1.99 KM – WNW
Alok International School – 2 KM – WNW
Sanskar Hospital – 5.8 KM – WSW
Mahatma Gandhi Govt. Collage – 4.2 KM - WSW | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | No such area around the project site. | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | No such area comes under project vicinity. | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | No such area comes under project vicinity. | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Surya | Designation | Director | Name of Company (Applicant Name should not be given here) | VEDANTA WASHERY AND LOGISTIC SOLUTIONS PVT LIMITED | Address | Robertson SEC Rly at NH-49, Village-kunkuni, Kharsia |
| |
|