APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Adani Power Rajasthan Limited | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/RJ/THE/24396/2014 | Project Cost | 910000 lacs | |
| 2. | |
S. No. in the schedule | 1(d) Thermal Power Plants
| Project Sector | Thermal Projects | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 1600 MW ha. | | 4. | New/Expansion/Modernization | Expansion | Proposal Number | IA/RJ/THE/10416/2011 | MoEFCC file number(Previous EC) | J-13012/154/2008-IA.II(T) | Uploaded EC letter | Annexure-Uploaded EC letter | | | 5. | Existing Capacity/Area etc. | 1320 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | Yes | d) | Inter-State boundaries and international boundaries | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Kawai, Darha, Kherli, Nimoda and Baldeopura Villages, Atru Tehsil, Baran District, Rajasthan | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file  | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | 128, 129, 130, 131, 136, 137, 138, etc of Baldeopura. 126, 128/687, 129, etc. of Darha. 82, 83, 84, 99, etc. of Nimoda. 17, 18, 356, 357, etc. of Kherli. 1333, 1334, 1335/2182, etc. of Kawai. | Town / Village | Kawai, Darha, Kherli, Nimoda, Baldeopura | State of the project | Rajasthan | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
NIL | | 10. | |
Nearest railway station along with distance in kms | Salpura, 2 km | Nearest airport along with distance in kms | Kota3, 120 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Atru , 6 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | | | 13. | Name of the Applicant | Santosh | | 14. | Registered Address | Adani House, Nr Mithakhali Circle
Navrangpura, Ahmedabad.
Pin- 380009. | | 15. | |
Address for correspondance: | Name of the Company | Adani Power Ltd. | Name of the Applicant | Santosh | Designation (Owner/ Partner/ CEO) | Head - ESG & Environment | Pin code | 380015 | E-mail | santosh.singh1@adani.com | Telephone No. | 79-25557289 | Fax No. | 79-25557401 | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | NIL | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | No | The proposed land is already allotted by the Govt. of Rajasthan and is already under non-agricultural land use. The land is under possession of Adani Power Rajasthan Limited.
The topography will change with construction of Power Plant. | 1.2 | Clearance of existing land, vegetation and buildings? | No | There is no vegetation on the proposed site. | 1.3 | Creation of new land uses? | No | The proposed land is within the plant site and already classified as non-agricultural and for industrial use. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Soil testing for detailed engineering of the foundations. | 1.5 | Construction works? | Yes | Construction of Power Plant and its auxiliary facilities. | 1.6 | Demolition works? | No | Not Applicable | 1.7 | Temporary sites used for construction works or housing of construction workers? | Yes | Temporary sites would be used for housing of construction workers. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | The entire Power Plant will be constructed above ground. There will be some cut and fill and excavations for foundations. | 1.9 | Underground works including mining or tunnelling? | No | Not Applicable | 1.10 | Reclamation works? | No | Not Applicable | 1.11 | Dredging? | No | Not Applicable | 1.12 | Offshore structures? | No | Not Applicable | 1.13 | Production and manufacturing processes? | Yes | Generation of electricity from combustion of coal, through steam turbine and generators. | 1.14 | Facilities for storage of goods or materials? | Yes | Coal Stock Yard for storage of coal.
Storage tanks for LDO/HFO/HSD.
Closed storage yard for chemicals, spare parts, equipment, maintenance, etc. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Ash Disposal System: Ash collection and storage in silos in dry form is proposed for utilization. Lean Slurry Disposal is proposed for evacuation of unutilized ash. The top ash surface shall be covered with thick soil cover during closure of the ash dyke.
The filter backwash water of Pre-Treatment Plant shall be collected and recycled back to the DM system clarifier.
A coal settling pond shall be provided to remove coal particles from coal handling plant waste.
Sewage will be treated in STP. | 1.16 | Facilities for long term housing of operational workers? | No | Residential Complex for Adani Power Rajasthan Limited has already been developed. There is no proposal along with this application. | 1.17 | New road, rail or sea traffic during construction or operation? | Yes | No new facilities are to be created. The existing approach road to the site will be used. New Railway Line for transportation of coal from take-off point on Indian Railways system has already been developed. There will only be increase in traffic. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | No new facilities are to be created. There will only be increase in traffic. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Not Applicable | 1.20 | New or diverted transmission lines or pipelines? | Yes | Construction Power will be drawn from the existing facilities. During operational phase, power is proposed to be supplied at the bus bar of the power plant. There is no transmission line proposed as part of this application.
Additional pipeline will be laid along the existing corridor for water. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not Applicable | 1.22 | Stream crossings? | No | Not Applicable | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Presently, the water allocation for the existing 2x660 MW power plant is 34 MCM/Year. The actual consumption is about 25 MCM/Year.
Water requirement for 2x800 MW power plant will be 29 MCM/Year. Adani Power Rajasthan Limited is making application for additional water allotment of 20 MCM/Year from Parwan River.
Water Requirement will be met by laying additional pipeline from Parwan River, over a distance of 25 km. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | Not significant as the water study report of Parwan River basin indicates sufficient water availability from upstream of Parwan Irrigation Project. | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | Transport of construction materials from nearby sources to construction work area during construction and transport of coal from coal mine stockyard to the plant site during operation. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not Applicable | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not Applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | Since industry attracts both skilled and unskilled labours, influx of people will be there to some extent. | 1.29 | Introduction of alien species? | No | Not Applicable | 1.30 | Loss of native species or genetic diversity? | No | Not Applicable | 1.31 | Any other actions? | No | Not Applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | The land proposed for the project is already allotted by the Govt. of Rajasthan and under non-agricultural land use classification. The land is already with industrial use and in possession of Adani Power Rajasthan Limited. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Water requirement is 79,452 KLD (29 MCM/Year). Water allocation for the existing plant is 34 MCM/Year. The actual consumption is about 25 MCM/Year.
Water requirement for 2x800 MW power plant will be 29 MCM/Year. Adani Power Rajasthan Limited is applying for allotment of 20 MCM/Year from Parwan River.
Competing users are for agricultural uses downstream. Impact will be insignificant as the water study report of Parwan River basin indicates sufficient water availability from upstream. | 2.3 | Minerals (MT) | Yes | Domestic Coal will be used as primary fuel @ 7.14 million Metric tonnes per annum @ 90% PLF (GCV-3800 Kcal/Kg, HR – 2150 Kcal / kwh). In case of shortfall in supply of domestic coal, imported coal is proposed to be used for making up the shortfall. | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Stone, aggregate, soil, sand etc. from nearby area, during construction. Estimated quantities are as below:
Cement- 12,00,000 bags
Reinforcement- 12,000 MT
Aggregates- 120,000 m3 | 2.5 | Forests and timber (source – MT) | No | Not Applicable | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | The project is proposed on 100% domestic coal. Domestic Coal will be used as primary fuel @ 7.14 million Metric tonnes per annum @ 90% PLF (GCV-3800 Kcal/Kg, HR – 2150 Kcal / kwh). In case of shortfall in supply of domestic coal, imported coal is proposed to be used for making up the shortfall.
LDO & HFO/HSD will be used as secondary fuel @ 15000 KL per annum. | 2.7 | Any other natural resources (use appropriate standard units) | No | Not Applicable | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | 1. LDO/HFO/HSD- 15000 KL/Year
2. Chlorine- 675 Tons/Year | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Not Applicable | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | The region is slowly turning into industrial and commercial zone from agricultural and rural economy. The increased industrial and commercial development is expected to have beneficial impact on the local people in terms of employment and ancillary commercial activities. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Hospitals, schools, road etc. are being developed under CSR activity of the Project Proponent. | 3.5 | Any other causes | No | Not Applicable | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | Not Applicable | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | There will be Municipal waste generation only from canteen area. Adani Power Rajasthan Limited has already provided Organic Waste Converter for converting this waste into manure. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Oily waste & sludge will be disposed off as per CPCB/RSPCB/MoEF guidelines. | 4.4 | Other industrial process wastes | Yes | Ash only. | 4.5 | Surplus product | No | Not Applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Treatment Plant Sludge and STP Sludge. | 4.7 | Construction or demolition wastes | Yes | Construction wastes will be separately packed in bags and supplied to recyclers. | 4.8 | Redundant machinery or equipment | No | Not Applicable | 4.9 | Contaminated soils or other materials | No | Not Applicable | 4.10 | Agricultural wastes | No | Not Applicable | 4.11 | Other solid wastes | No | Not Applicable | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Emission of dust and gases like Particulate Matter, NOX, SO2 etc.
ESP, Low NOx burners, 275 m tall stacks and other measures will be taken to limit the emission within the prescribed norms. | 5.2 | Emissions from production processes | Yes | Emission of dust and gases Like PM, NOX, SO2 etc.
One RCC Stacks of 275 m height, with two Steel Flues are proposed for wider dispersion of the pollutants. | 5.3 | Emissions from materials handling including storage or transport | Yes | Not anticipated with usage of dust extraction and suppression system in ash silo, coal transfer point and coal bunkers. Also closed coal conveyors will be used in coal transportation. | 5.4 | Emissions from construction activities including plant and equipment | Yes | Regular water sprinkling will be done at the project to minimize the dust emission during construction phase. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Some dust will be emitted while handling the construction materials like cement or bricks. | 5.6 | Emissions from incineration of waste | No | Not Applicable | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not Applicable | 5.8 | Emissions from any other sources | No | Not Applicable | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Noise would be generated generally from steam turbine, generator, compressors, pumps, fans, coal handling plant etc. but all the equipment will be designed and if required acoustic materials will be provided to have the noise level not to exceed the values as stipulated in CPCB/RSPCB/MoEF norms. | 6.2 | From industrial or similar processes | Yes | Noise would be generated during transportation of material / machine. | 6.3 | From construction or demolition | Yes | Some noise would be generated during construction phase but it will be limited to the site only. | 6.4 | From blasting or piling | Yes | Blasting may be required for excavation of foundations, as the area has rocky outcrop. However, this will be limited to the early stage of construction as well as limited in extent. | 6.5 | From construction or operational traffic | Yes | During construction and coal transportation traffic. | 6.6 | From lighting or cooling systems | Yes | Indirect process cooling, direct water spraying. | 6.7 | From any other sources | No | Not Applicable | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | Not Applicable | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | Plant will follow the minimum discharge concept and only treated effluent meeting the statutory standards shall be discharged. | 7.3 | By deposition of pollutants emitted to air into the land or into water | Yes | Installing ESP and other air pollution control equipment will minimize the impact. Similarly COC maximization along with reuse will generate minimum discharge. ETP will be designed to meet stipulated standards. Only treated effluent will be discharged. So there will be no significant impact. | 7.4 | From any other sources | No | Not Applicable | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | Yes | Minimum impact on land and water due to state of art technology. Mostly treated pollutants will be released from plant premises. | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | An assessment of conceptual design will be conducted to minimize the risk of fire at the coal stockyard, LDO & HFO/HSD storage tank, chlorine gas leaks from the pipeline/ tonner, breaching of ash pond due to failure of ash pond bund. | 8.2 | From any other causes | No | Not Applicable | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | Not Applicable. However, at the time of construction work, the regulations for the Seismic Zone-II will be taken into consideration for design and setting up the project. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | Roads, infrastructure and housing development in the surrounding area.
The project will also undertake local community development under its CSR plan focusing on Education, Health & Sanitation, Livelihood development and Rural Infrastructure Development. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | Yes | It would be an industrially planned area and have positive impact on the socio-economic environment. | 9.3 | Set a precedent for later developments | Yes | Development of power plant will have later downstream development. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | Not Applicable | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | Yes | Reserve Forest at a distance of 1.0 km in E direction.
Protected Forest-8.5 km in NE. | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | No | Not Applicable | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | Not Applicable | 4 | Inland, coastal, marine or underground waters | Yes | Andheri River- 1.0 km
Parbati River- 6.5 km | 5 | State, National boundaries | Yes | Rajasthan- Madhya Pradesh Boundary- 7.0 km | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | Not Applicable | 7 | Defence installations | No | Not Applicable | 8 | Densely populated or built-up area | Yes | Atru- 6.0 km | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Primary Health Centres and Schools in Salewara and Atru- 2.0 to 6.0 km | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | Not Applicable | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | Not Applicable | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | Not Applicable | | (IV) | Proposed Terms of Reference for EIA studies | | Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Annexure-EC Letter | 04 Sep 2014 | 2. | NA | Your proposal has been examined. While examining the Form-I submitted by you it is noticed that the Annexure at S.No. 11 is not enclosed. You are requested to kindly attach the same and resubmit for further consideration. | 04 Sep 2014 | | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Santosh | Designation | Head - ESG & Environment | Name of Company (Applicant Name should not be given here) | Adani Power Ltd. | Address | Adani House, Nr Mithakhali Circle