APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | 2 x 660 MW Super Critical Thermal Power Plant at Koradi by MAHAGENCO , Maharashtra | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/MH/THE/102533/2019 | Project Cost | 988200 lacs | |
| 2. | |
S. No. in the schedule | 1(d) Thermal Power Plants
| Project Sector | Thermal Projects | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 1320 MW ha. | | 4. | New/Expansion/Modernization | Expansion | Proposal Number | IA/MH/THE/12041/2007 | MoEFCC file number(Previous EC) | No:J- 13012/87/ 2007-IA II(T) | Uploaded EC letter | Annexure-Uploaded EC letter | | | 5. | Existing Capacity/Area etc. | 2400 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Koradi village | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file  | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | koradi | Town / Village | koradi | State of the project | Maharashtra | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Maharashtra | Nagpur | Kamptee | | 10. | |
Nearest railway station along with distance in kms | Godhni, 5 km | Nearest airport along with distance in kms | Nagpur, 18 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Nagpur , 4 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | village - Koradi , Grampanchayat Koradi | | 13. | Name of the Applicant | Nitin | | 14. | Registered Address | PRAKASHGAD,PLOT NO G-9,SECOND FLOOR,BANDRA(EAST),MUMBAI-400051 | | 15. | |
Address for correspondance: | Name of the Company | Maharashtra State Power Generation Company Limited CIN-U40100MH2005SGC153648 | Name of the Applicant | Nitin | Designation (Owner/ Partner/ CEO) | CGM | Pin code | 400051 | E-mail | cgmenvsafe@mahagenco.in | Telephone No. | 22-26582424 | Fax No. | 22-26477273 | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | No | The identified land is in industrial use. Power plant of 4x120 MW and 1 x 200 MW were operating till 2018. After demolishing of these 5 units a new TPP of 2 x 660 will be installed on the vacant land. there will be no change in land use. | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | Closed 4x120MW unit and 200MW unit and associated structure will be demolished.
A National level Tender will be float for experienced contractor for entire demolition work. The responsibility of demolishing, cleaning, disposal of debris, metal, equipment’s etc in specific manner and leveling of land will be in scope of contractor. This work will be carried out under supervision of Mahagenco. | 1.3 | Creation of new land uses? | No | Proposed coal based thermal power project will be located within existing premises of Koradi TPS. there will no creation of new land use. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | A detailed pre construction investigation , soil testing will be carried out before start of construction of TPP after receipt of EC and Consent of Establishment. | 1.5 | Construction works? | Yes | Construction of Office building, Boiler, Turbine House, Water treatment plant, Cooling Tower, Power Transmission line, Staff quarter etc. are proposed. | 1.6 | Demolition works? | Yes | Closed 4x120MW unit and 200MW unit will be demolished.
A National level Tender will be float for experienced contractor for entire demolition work. The responsibility of demolishing, cleaning, disposal of debris, metal, equipment’s etc in specific manner and leveling of land will be in scope of contractor. This work will be carried out under supervision of MAHAGENCO | 1.7 | Temporary sites used for construction works or housing of construction workers? | Yes | Temporary shed with sanitation facility will be developed for contractual worker. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | Boiler, Turbine House, Cooling Tower, Chimney Power Transmission Greed , etc. | 1.9 | Underground works including mining or tunnelling? | No | Tunneling and mining works are not envisaged. Underground/below surface working pertaining to excavation/earthwork/internal drainage/rainwater harvesting pits. | 1.10 | Reclamation works? | No | | 1.12 | Offshore structures? | No | | 1.13 | Production and manufacturing processes? | Yes | 2 x 660 MW Super Critical Thermal Power Plant for Power Generation. Details are mentioned in PFR. | 1.14 | Facilities for storage of goods or materials? | Yes | The coal stock yard storage area, Raw water reservoir, Ash Pond and silos for fly ash will be provided in the project site. Locations are marked on Plant Lay out Plan. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | ETP and STP are proposed for treatment of industrial effluent and domestic effluent respectively. Fly ash will be stored in ash bund. A fly ash cluster is being developed for utilisation of fly ash from Koradi TPP. Gypsum Generation : 2,19,000 TPA. | 1.16 | Facilities for long term housing of operational workers? | Yes | it is proposed to construct additional staff quarters in existing staff colony | 1.17 | New road, rail or sea traffic during construction or operation? | No | Existing Road network and rail network are adequate to handle traffic load for transportation of staff and transportation of coal. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Existing Road network and rail network are adequate to handle traffic load for transportation of staff and transportation of coal. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | | 1.20 | New or diverted transmission lines or pipelines? | Yes | 400KV transmission line from proposed thermal power unit to connect existing 400KV Switchyard at same premises of thermal power plant. A pipe line from STP of Nagpur city will be laid for transportation of treated sewage water. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not applicable | 1.22 | Stream crossings? | No | Not applicable | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | No Ground Water will be extracted.
Treated waste water from Nagpur Municipal Corporation will be used. The distance of source of water and TPP is 12Km(25.2MCM/annum).Fresh water will be used source from Pench Dam which is at 40Km from project site.(10.8MCM/annum) | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | Not applicable | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | Local labourers will be employed in construction phase. The construction material from local suppliers. personnel for operation phase will use own vehicles and or public transport. | 1.26 | Long-term dismantling or decommissioning or restoration works? | Yes | Existing 4 x120MW and 1x200MW old TPP and old quarters will be dismantled. | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | Yes | Generation of debris, old machineries, equipment.
A National level Tender will be float for experienced contractor for entire demolition work. The responsibility of demolishing, cleaning, disposal of debris, metal, equipment’s etc in specific manner and leveling of land will be in scope of contractor. This work will be carried out under supervision of Mahagenco.
Proper care will be taken to suppressed fugitive emission generation during dismantling work by water sprinkling. | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | Local worker during construction and operation phase .Permanent quarter will be constructed to accommodate about 534 person. | 1.29 | Introduction of alien species? | No | | 1.30 | Loss of native species or genetic diversity? | No | | 1.31 | Any other actions? | No | | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | Proposed coal based thermal power plant will be established in land of closed 4x120MW and 200MW unit and associated structure at existing Korardi TPS. Total 275.39 ha land is identified for proposed project. The land identified for proposed project is earmarked for power plant only. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | a)Total water requirement for proposed thermal power plant is 36 MM3/year.
b)two type of water are proposed for 2x660MW Thermal Power plant.
1)Tertiary treated sewage water from Nagpur Municipal corporation for cooling circuit.(25.2MM3/annum)
2) Water from Pench dam 10.8MM3/annum.The specific water consumption will be as per notification dt 28th june 2018. | 2.3 | Minerals (MT) | Yes | Coal 7.18 Million Tons Per Annum
Source: 3.165MMTPA coal will be available from existing coal linkages of closed unit.
Balance coal @4.015 MMTPA will be source from various mines of M/s WCL
Lime Stone for FGD : 1,46,000 TPA | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Stone, sand, Steel, Cement etc. will be required. Quantity will be finalized after detailed drawing. | 2.5 | Forests and timber (source – MT) | No | Not applicable | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | A power for construction work will be source from existing power plant unit. During operation phase electrical energy from power generation plant will be used for auxiliary consumption. | 2.7 | Any other natural resources (use appropriate standard units) | Yes | LDO 9830Kl/annum
HFO: 19660KL/annum | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | LDO 9830Kl/annum
HFO: 19660KL/annum | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Not envisaged. | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | The proposed coal based power project will provide additional employment opportunity and infrastructure development in the nearby areas. It will improve the living condition of the people in nearby areas. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Not applicable | 3.5 | Any other causes | No | Not applicable | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | not applicable | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Sewage Treatment Plant will be installed at thermal power plant and quarter for treatment of domestic waste. Fly ash will be utilised in upcoming Fly ash cluster. Gypsum will be sold. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Transformer Oil, Machined used oil Sludge during LDO & FO Tank cleaning , sludge from WTP , spent resins. It will be handover to MPCB registered vendors for disposal. | 4.4 | Other industrial process wastes | Yes | Total Ash: 7515TPD(2.48MMTPA)
Fly ash will be sold to cement plant and bottom ash will be disposed in ash pond.
Gypsum from FGD @ 2,19,000 TPA
Fly Ash cluster is proposed in Koradi to utilize fly ash.It will be developed within 18 month. | 4.5 | Surplus product | Yes | Gypsum and Fly ash. | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Sewage sludge from STP will be used as manure for plantation | 4.7 | Construction or demolition wastes | Yes | Construction and demolition waste will be generated during demolishing existing closed units.A National level Tender will be float for experienced contractor for entire demolition work. The responsibility of demolishing, cleaning, disposal of debris, metal, equipment’s etc in specific manner and leveling of land will be in scope of contractor. This work will be carried out under supervision of Mahagenco. | 4.8 | Redundant machinery or equipment | Yes | Old Boiler, Turbine, Generator, motor, pump, Fan etc. will be sold through tender process. | 4.9 | Contaminated soils or other materials | Yes | contaminated soils and other materials may be generated during demolishing process. it will be disposed by environment safe manner. | 4.10 | Agricultural wastes | No | Not applicable | 4.11 | Other solid wastes | Yes | Plastic , scrap , glass , etc during construction and operation of the Plant. | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Emission of Particulate Matter, SO2, NOx.
ESP and Chimney with appropriate height will be provided as per Standards.
FGD will be installed to control SO2. SCR are proposed for controlling NOx.Proper Bag filter and other appropriate equipment’s will be installed at Coal crusher to control emission. Dust suppression will be controlled by installing mist type foggers at CHP, AHP, Rain Gun at Coal stack area, Ash Bund, internal roads to control fugitive emission. | 5.2 | Emissions from production processes | Yes | Emission of Particulate Matter, SO2, NOx.
ESP and Chimney with appropriate height will be provided as per standard.
FGD will be installed to control SO2.
SCR are proposed to installed for control of NOx | 5.3 | Emissions from materials handling including storage or transport | Yes | Fugitive emission is envisaged due to handling of coal and ash. Water Sprinkler will be provided to control the emission. | 5.4 | Emissions from construction activities including plant and equipment | Yes | During Construction phase due to transportation of heavy vehicles, operation of equipments and construction machineries. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Solid waste & Liquid waste are envisaged during construction period | 5.6 | Emissions from incineration of waste | No | Not applicable | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not applicable | 5.8 | Emissions from any other sources | No | Not applicable | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Noise will be generated from turbine , Water pump house, Crusher, Blower and motors. All noise producing equipment will be maintained to achieve noise level as per standard CPCB norms. | 6.2 | From industrial or similar processes | Yes | The noise level generated will be in the range of 70-90 dB (A) at1 m from source. | 6.3 | From construction or demolition | Yes | Due to operation of heavy machineries during demolition and construction work | 6.4 | From blasting or piling | No | Not applicable | 6.5 | From construction or operational traffic | Yes | Due to movement of heavy vehicles. | 6.6 | From lighting or cooling systems | Yes | Noise from water pump and motors.
Boiler house and pipes carrying steam, Steam water condenser. All equipment will be properly insulated. | 6.7 | From any other sources | No | Not applicable | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | Due to storage of LDO, HFO, Diesel etc. Proper care will be taken as per standard process. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | STP will be provided for domestic waste.
ETP will be provided for treatment of effluent from power plant. | 7.3 | By deposition of pollutants emitted to air into the land or into water | Yes | ESP , FGD and SCR with stack as per standards are proposed to minimize the concentration of source emission. | 7.4 | From any other sources | No | Not applicable | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | Yes | Due to malfunction of pollution control devices installed for the purpose. However proper care and maintenance will be undertaken to ensure proper functioning of these equipments. | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | Fire in coal storage area, HFO and LDO Storage tank.
Well design fire hydrant system and firefighting equipment will be provided at required areas. | 8.2 | From any other causes | Yes | Electrification from Transformer Yard, or from Power transmission line.
The entry in this area will be prohibited and monitored by Safety and Operation officer. Permit system will be followed for this area. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | Yes | On-Site DMP will be prepared. Proper precaution will be taken to handle such situation. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | This project will provide additional infrastructure to nearby area under CER and CSR
Possibilities of ancillary industries will be increased.
This project will generate direct and indirect employment for nearby villages. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | Yes | considering the life of power plant about 25-30 years there will be impact on environment if not disposed scientifically | 9.3 | Set a precedent for later developments | Yes | Ancillary industries might be developed as a consequence | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | Yes | cumulative effect is envisaged. The magnitude will be calculate. | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | Not applicable | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | River :
Kanahan River : 4.5 Km (NE)
Pench River : 7.5 Km (E)
Kolar River : 2.0 Km (NE)
Pioli Nadi : 5.5 Km (SE)
Lake :
Gorewada lake : 6.0 Km (SW)
Koradi Lake : 1.0 Km (NW)
Futala Lake : 10.0 Km.(S)
Shukrawari Lake : 10.0 Km.(S)
Ambazari Lake : 12.5 Km. (S) | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | Yes | Gorewada Zoo and Wildlife rescue centre : 6.5 Km (SW)
MansinghDeo WLS :
Existing boundary : 25.5 Km (NE)
Extended boundary : 23.5 Km (NE) | 4 | Inland, coastal, marine or underground waters | No | Not applicable | 5 | State, National boundaries | No | Not applicable | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | Koradi Temple : 0.5 Km. (N)
Dragon Palace : 12 Km (SE)
Waki Tajuddin Darbar : 14.5 Km (NW) | 7 | Defence installations | Yes | Kamthee cantonment : 7.0 Km (E)
Ambazari Ordnance Factory : 16.0 Km. (SW)
Air Force Maintenance Command : 10 Km. (SW) | 8 | Densely populated or built-up area | Yes | Kamthee Town : 9.5 Km (SE)
Nagpur : 4.0Km. (S) | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Koradi Temple : 0.5 Km. (N)
Dragon Palace : 12.0 Km. (SE)
Waki Tajuddin Darbar : 14.5 Km. (NW)
there are number of collages and hospitals in Nagpur city and Kamthee Town. | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | as per point no 2 , in addition to this there are Coal mines of WCL , some mines of manganese , tourist places. | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | Not applicable | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | Not applicable | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | | Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Reply to show cause letter and layout plan Koradi TPS | 12 Feb 2020 | 2. | NA | ok | 10 Dec 2019 | 3. | ADS Reply Letter | Compliance of MoM of the 32nd meeting of the reconstituted Expert Appraisal Committee(EAC) on Environmental Impact Assessment (EIA) of Thermal Power Projects held during 23rd August,2019. | 21 Nov 2019 | 4. | ADS Raise Letter | Please provide the information as per attached letter. | 04 Jul 2019 | | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Nitin | Designation | CGM | Name of Company (Applicant Name should not be given here) | Maharashtra State Power Generation Company Limited CIN-U40100MH2005SGC153648 | Address | PRAKASHGAD,PLOT NO G-9,SECOND FLOOR,BANDRA(EAST),MUMBAI-400051 |
|
|