EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/WB/IND/60075/2016    ii. MoEFCC File No. : J-11011/237/2016-IA-II(I)    iii.Short narrative of the project: EXPANSION OF DUCTILE IRON PIPE PLANT FROM 2,00,000 TPA TO 5,50,000 TPA IN PHASE EWISE    iv. Project Sector : Industrial Projects-1    v. Company/Proponent : RASHMI METALIKS LIMITED
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.West BengalWest MedinipurNo Data
2.West BengalWest MedinipurNo Data
3.West BengalWest MedinipurKharagpur - I
4.West BengalWest MedinipurKharagpur - I
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded EC Compliance report viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 31 Jan 2017 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 11 Jan 2018 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 29 Aug 2017   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: None   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
Additional Attachments, if any
S.no. Attached File Date of Submission
1. REPLY TO THE ADS RAISED DATED 22.12.2017(RO_MoEF-BHUBANESWAR Compliance Certificate)11 Jan 2018
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NATherefore, the Committee sought revised EIA report incorporating following: 1. Closure report of all non-compliances of earlier EC conditions reported by RO, MoEFCC 2. Revised table of issues raised during PH, commitment of PP, time bound action plan along with fund provision. 3. Revised ESC programme based on the issues emerged during PH and social impact assessment. The activity shall be for asset creation and capacity building in CAPEX mode. 4. Revised Corporate Environmental Policy addressing the standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions to the board of directors directly; hierarchical system or Administrative order of the company to deal with the environmental issues and 08 Feb 2018
2. ADS LetterRevised EIA Report addressing all the queries raised by EAC Members 28 Feb 2018
3.NATeh reply to ADS was not satisfactory 16 Mar 2018
4. ADS LetterOur reply against the respective points as raised by the Honourable committee members in the 28th & 29th meetings of Reconstituted Expert Appraisal Committee (Industry-1) of Ministry of Environment, Forest and Climate Change (MoEF&CC), Govt. of India dated 7th February, 2018 & 12th March, 2018 respectively. 18 Apr 2018
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : NABET/EIA/1011/010    iii. Name of Consultant: Envirotech East (P) Limited   iv. Address : Bengal Ambuja Commercial Complex UN F13, 1050/1, Survey Park, Kolkata-700 075   v. Mobile No.: 9331026867   vi. Landline No.: 03324188127   vii. Email Id: biswanath@rashmigroup.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : BISWANATH    ii. Designation : GM TECHNICAL & OPERATION    iii. Name of Company(Applicant Name should not be given here) : RASHMI METALIKS LIMITED    iv. Address : Premlata Building, 6th Floor, 39 - Shakespeare Sarani , Kolkata - 700017 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency