1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/RJ/IND/60653/2016    ii. MoEFCC File No. : J-11011/243/2016-IA-II(I)    iii.Short narrative of the project: Proposed Expansion of Integrated Cement Plant – Clinker, Cement, CPP and WHRB.    iv. Project Sector : Industrial Projects-1    v. Company/Proponent : JK CEMENT LTD KANPUR
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.RajasthanchittorgarhNimbahera
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded EC Compliance report viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 31 Jan 2017 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 02 Nov 2017 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 30 Jun 2017   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
Additional Attachments, if any
S.no. Attached File Date of Submission
1. Annexure - Notification in Support EC Not applicable02 Nov 2017
2. Annexure- Authenticated DFO received letter02 Nov 2017
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAThe committee observed that the existing plant is operating with consent to operate from the state pollution control board. The project project proponent informed that the plant was established before 1994 notification and subsequently expanded with consent to establishment with an investment less than 50 Crores and also established captive power plant with an investment of 80 Crs as a standalone project. 23.0 After detailed deliberations, the committee sought following information for further consideration of the proposal; 1. Detailed note on justification for not obtaining prior environmental clearance for the existing facilities including CPP under EIA Notification; and 2. Production of cement plant and power generation shall be submitted year wise against the consented capacity sin 05 Jan 2018
2. ADS LetterADS sought by EAC (Industry-I)during its meeting held on 05/01/2018 has been complied and uploded 17 Jan 2018
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 41    iii. Name of Consultant: ENKAY ENVIRO SERVICES PVT. LTD   iv. Address : #92, Heera Nagar-A, Near Shalimar Bagh, Ajmer Road, Jaipur   v. Mobile No.: 9314363996   vi. Landline No.: 01412353996   vii. Email Id: sk.rathore@jkcement.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Sushil    ii. Designation : President (O) & Unit Head    iii. Name of Company(Applicant Name should not be given here) : JK CEMENT LTD KANPUR    iv. Address : Kamla Tower v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency