Project Details
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? :
No
1.
Project Details
i. Proposal No. :
IA/MH/MIN/69565/2009
ii. MoEFCC File No. :
J-11015/262/09-IA.II(M)
iii.Short narrative of the project:
M/s Anand Mine
iv. Project Sector :
Mining Projects
v. Company/Proponent :
ANAND MINES PRODUCTS PVT LTD
vi.Details of State of the project
Details of State of the project
S.no.
State Name
District Name
Tehsil Name
1.
Maharashtra
Kolhapur
Shahuwadi
vii.Date of TOR Granted
09 Nov 2009
viii.TOR letter issued by Ministry:
Annexure-TOR letter
ix.Date of Submission for EC:
18 Sep 2017
x.Project Type:
New
2.
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP:
Annexure-EIA/EMP
ii.Risk Assessment:
Annexure-Risk Assessment
iii.Public Hearing:
Annexure-Public Hearing
iv. Date of Public Hearing:
02 Dec 2010
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC:
Annexure-Additional Report/Study/Document
vi. Uploaded Cover Letter:
Annexure-Cover Letter
vii.Remarks:
NIL
3.
Additional Detail Sought
Additional Detail Sought
Sno.
ADS Letter
Remarks
Date of ADS
1.
NA
In view of the Hon’ble NGT order dated 27.08.2017, the proposal was re-considered in the EAC meeting held during 18-19thSeptember, 2017. The committee noted KML file was not analyzed during the EAC meeting held during 19-21st December, 2012 when the proposal was recommended. Now, based on KML file, the DSS not only showed that the mine lease area was surrounded by Reserve Forest areas but also that there was still Reserve Forest area (14.10 Ha) falling within the mine lease area. The area of KML file submitted by PP is also not matching with the actual lease area. Although, the PP previously submitted the NOC dated 15.12.2012 from Forest Department Kholapaur but the committee was in opinion that a clarification for Forest Compartment number 1051,1052,1054 and 1055 as shown by DSS be obtain
27 Sep 2017
2.
ADS Letter
Additional Information as sought by the REAC of MoEF&CC.
09 Oct 2017
3.
ADS Letter
ai
13 Nov 2017
4.
Accredited Consultant Details
i. Accreditation status :
Yes
ii. Accreditation No. :
S.No 114 Rev No 57, 5th September 2017
iii. Name of Consultant:
Perfact Envirosolutions Pvt Ltd
iv. Address :
5th floor NN Mall Sec-3, Rohini, Delhi
v. Mobile No.:
9818346370
vi. Landline No.:
01149281360
vii. Email Id:
info@perfactgroup.com
5.
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
i. Name of Applicant :
SS
ii. Designation :
AuthorisedSignatory
iii. Name of Company(Applicant Name should not be given here) :
ANAND MINES PRODUCTS PVT LTD
iv. Address :
M/s Anand Mines Products Pvt. Ltd 1472 D ward Shukrawar Peth Kohlapur- 416002 Maharashtra