1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/AP/MIN/53361/2016    ii. MoEFCC File No. : J-11015/157/2016.IA.II(M)    iii.Short narrative of the project: Mangampet Barytes Extension Project (Project area – 221.89 Ha) of M/S. APMDC Ltd    iv. Project Sector : Mining Projects    v. Company/Proponent : THE ANDHRA PRADESH MINERAL DEVELOPMENT CORPORATION LTD
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.Andhra PradeshKadapaNo Data
 
   vii.Date of TOR Granted 10 Jun 2016 viii.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 09 Jan 2018 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 04 May 2017   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: None   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
Additional Attachments, if any
S.no. Attached File Date of Submission
1. Annexure-document of Mine Plan - part - 114 Sep 2017
2. Annexure-document of Mine Plan - Part - 214 Sep 2017
3. Annexure-document of Mine Plan - Part - 314 Sep 2017
4. A-9 Conservation plan Part 1 of 209 Jan 2018
5. A-9 Conservation plan Part 2 of 209 Jan 2018
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NABased on the discussion held, presentation made and document submitted by proponent the Committee deferred the proposal due to aforementioned reasons and was of view that proposal may only be considered after submission of the following information: a) The mining lease deed/LoI for 221.89 Ha b) Approved mining plan for 221.89 Ha needs to be submitted and EIA/EMP report needs to be revised accordingly. c) Proof of submission of wildlife conservation plan needs to be submitted. d) The activity wise emission rate (clearly defining the quantity of the material to be handled) needs to be mentioned in the EIA report along with Ground Level Concentration of various pollutants, both in worst case scenario and after implementation of the mitigation measure. e) Detailed R&R plan needs to b 10 Mar 2018
2. ADS LetterSubmission of Revised Final EIA/EMP report along with enclosures incorporating the observations of REAC in the 28th meeting held on 27th February, 2018 06 May 2018
3.NABased on the discussion held and documents submitted the Committee deferred the proposal and was of the view that proposal may be considered after submission of the following documents: a) Modified Mining Plan after changing the year-wise production & development planning, direction of movement of the benches and all related plan and section. b) The EIA Report needs to be revised as per the mining plan and extension word should be removed from the EIA Report. c) PP should provide the EMP budget only for the proposed mine. PP should provide the activity wise budget along with timeline for its implementation. d) PP should provide the detailed occupational health surveillance plan. The activity wise budget and time period for its implementation needs to be provided in the EIA rep 22 May 2018
4. ADS LetterSubmission of Revised Final EIA/EMP report (Ver.2) along with Approved Modified Mining Plan incorporating the observations of REAC in the 31st meeting held on 15th May 2018 & Additional Details Sought by MoEF&CC. 31 May 2018
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : S.No.27 in NABET list of ACO    iii. Name of Consultant: Creative Engineers & Consultants   iv. Address : 9/4B, Bharathwajar Street, East Tambaram, Chennai - 600 059   v. Mobile No.: 9444133619   vi. Landline No.: 04422396643   vii. Email Id: hdnagaraja@yahoo.co.in
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Ch V    ii. Designation : Vice Chariman & Managing Director    iii. Name of Company(Applicant Name should not be given here) : THE ANDHRA PRADESH MINERAL DEVELOPMENT CORPORATION LTD    iv. Address : H.No. 6-2-915, 3rd Floor, Rear Block, HMWSSB,Khairatabad, Hyderabad v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
Print