EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/WB/IND/20395/2013    ii. MoEFCC File No. : J-11011/327/2013-IA-II (I)    iii.Short narrative of the project: Proposed expansion of Steel Plant along with installation of Cement Grinding Unit.    iv. Project Sector : Industrial Projects-1    v. Company/Proponent : M/s Shyam Sel & Power Ltd.
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.West BengalBarddhamanJamuria
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded EC Compliance report viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 05 Feb 2014 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 25 Sep 2017 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 14 Aug 2015   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: None   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
Additional Attachments, if any
S.no. Attached File Date of Submission
1. EC compliance report from RO MoEFCC25 Sep 2017
2. REPLY TO ESSESNTIAL DETAILS SOUGHT BY MS25 Sep 2017
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAAfter detailed deliberations the committee observed the following: i. PP has changed the configuration of the plant without prior approval of the ministry. This PP has clarified that their EC is still valid and they have already applied for the amendment. ii. The EIA prepared for the expansion project does not include these changes in the configurations. Hence the base status of the status is not clear; iii. BLD is of more than 3 year old iv. ToR numbers 28, 34, 37(i to xi), 42, 46, 47, 49, 61 were not complied v. Structure of the EIA/EMP is not as per the generic structure envisaged EIA Notification and the contents are generic and not project specific. 24.0 Therefore, the revised EIA/EMP to be submitted after validating the BLD with fresh data for one month to be collected hencefor 17 Nov 2017
2. ADS LetterNA 23 Jun 2018
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : NABET/EIA/1011/010    iii. Name of Consultant: Envirotech East Private Limited   iv. Address : Bengal Ambuja Commercial Complex, UN F13, 1050/1, Survey Park, Kolkata-700075   v. Mobile No.: 9331026867   vi. Landline No.: 03324188127   vii. Email Id: amitdebnath@shyamgroup.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Prashant    ii. Designation : Executive Assistant to MD    iii. Name of Company(Applicant Name should not be given here) : SHYAM SEL AND POWER LIMITED    iv. Address : S S Chamber, 5 CR Avenue, Kolkata-700072 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency