EC Report
1.
Project Details
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? :
Yes
Type of Violation :
Expanded the production beyond the limit of EC.
Details of Violation :
GPCB has filled a violation case 2819/2013 dated 11/02/2017 which is resolved by Chief Judicial Magistrate Porbandar on dated 11/02/2017
Upload document of Damage Assessment Report :
Annexure-Damage Assessment Report
Upload document of Remediation Plan and Natural & Community augmentation plan :
Annexure-Damage Assessment Report
Upload TOR Letter(if issued earlier) :
None
Upload EC Letter(if issued earlier) :
None
1.
Project Details
i. Proposal No. :
IA/GJ/MIN/31635/2012
ii. MoEFCC File No. :
J-11015/277/2012-IA. II (M)
iii.Short narrative of the project:
Expansion of Palakhada Mining project from 9029 TPA to 76, 520 TPA (ROM) of Laterite by M/s Saurashtra Minerals Pvt. Ltd located at village Palakhada, Tehsil and district Porbandar, Gujarat (90.5279 h
iv. Project Sector :
Mining Projects
v. Company/Proponent :
SAURASHTRA MINERALS PVT LTD
vi.Details of State of the project
Details of State of the project
S.no.
State Name
District Name
Tehsil Name
1.
Gujarat
Porbandar
Porbandar
vii. Uploaded EC Compliance report by rigional office of MoEFCC:
Annexure-Uploaded EC Compliance report
viii. Certified Monitoring report by RoMoEF:
Annexure-Uploaded Monitoring report
ix.Date of TOR Granted
15 Dec 2014
x.TOR letter issued by Ministry:
Annexure-TOR letter
ix.Date of Submission for EC:
20 May 2017
x.Project Type:
Expansion
2.
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP:
Annexure-EIA/EMP
ii.Risk Assessment:
Annexure-Risk Assessment
iii.Public Hearing:
Annexure-Public Hearing
iv. Date of Public Hearing:
28 Jan 2016
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC:
Annexure-Additional Report/Study/Document
vi. Uploaded Cover Letter:
Annexure-Cover Letter
vii.Remarks:
EC presentation was done twice in the Non coal mining committee and during 2nd EC presentation committee has asked to submit some additional documents which has been submitted and here also attached as Annexure- Additional document desired by EAC for your reference
3.
Additional Detail Sought:
NIL
4.
Accredited Consultant Details
i. Accreditation status :
Yes
ii. Accreditation No. :
NABET/EIA/1619/RA 0042
iii. Name of Consultant:
KADAM ENVIRONMENT CONSULTANTS
iv. Address :
871/B/3 GIDC MAKARPURA VADODARA
v. Mobile No.:
9687606223
vi. Landline No.:
02653001000
vii. Email Id:
kadam@kadamenviro.com
5.
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
i. Name of Applicant :
Bhargav
ii. Designation :
Director
iii. Name of Company(Applicant Name should not be given here) :
SAURASHTRA MINERALS PVT LTD
iv. Address :
M/s Saurashtra Minerals Pvt. Ltd.
v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency