EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/RJ/MIN/57552/2016    ii. MoEFCC File No. : J-11015/179/2016-IA-II(M)    iii.Short narrative of the project: PANDRU QUARTZ & FELDSPAR MINE    iv. Project Sector : Mining Projects    v. Company/Proponent : S B MINERAL ENTERPRISES
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.RajasthanBhilwaraAsind
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded EC Compliance report viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 09 Sep 2016 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 04 Sep 2017 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 29 Mar 2017   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: Proposal is being submitted for Final EC submission. All statuary requirements are met. TOR is complied with all relevant annexure. There is no Eco-sensitive area in 10 km study area. DFO authenticated flora and fauna list has been obtained.
Additional Attachments, if any
S.no. Attached File Date of Submission
1. Annexure - Authenticated Past Production Record06 Jul 2017
2. Annexure - Lease Validity Upto 26.05.204206 Jul 2017
3. Annexure - Cover Letter and previous EC letter16 Aug 2017
4. Annexure - District Survey Report04 Sep 2017
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAThe Committee deliberated on the proposal and noted that the proposal contains multiple issues which include revision of plans w.r.t. waste generation in mine and its management over entire life of mine, green belt development and plantation, identification of plant species, R&R plan and conservation plan for peafowl. The PP is also required to revise and furnish detailed break-up of Project cost, EMP Cost and ESC budget as deliberated in preceding paragraphs and furnish No Forest land certificate. The Committee noted that all issues rose during the EAC deliberations need to be addressed before making further appraisal. PP is also required to submit the Consent to operate obtained from the State Pollution Control Board since start of mining operations in the lease area. In view of the abov 01 Nov 2017
2. ADS LetterDear Sir Greetings! Kindly find enclosed the point-wise query reply. Kindly consider the same and accord us the environment clearance. 03 May 2018
3.NALatest Compliance Report from RO Lucknow is awaited.PP in april 2018 submitted the status of Compliance report to RO Lucknow, hoowover this proposal was appraised by EAC in october, 2017, Ub view of this PP need to submit the Certified Compliance report. 12 Jun 2018
4. ADS LetterDear Sir Greetings! Kindly find herewith the enclosed Certified Compliance Report by IRO, MOEF&CC, Jaipur. Kindly consider the same and accord us the environment clearance. 24 Mar 2023
5.NASir, The Project Proponent is requested to provide the following: (i) The Project Proponent needs to justify why there is a huge delay in submission of ADS reply, (ii) Valid Mining Plan as on date, (iii) Copy of lease deed execution for the period upto 26.05.2042 and (iv). District Survey Report approved by the SEIAA as per Ministry’s Notification S.O.3611(E) dated 25.07.2018 and in accordance with the order of Hon’ble Supreme Court dated 10.11.2021 in Civil Appeal Nos. 3661-3662 of 2020 titled as State of Bihar V/s Pawan Kumar. 31 Mar 2023
6. ADS LetterRespected Sir, please find point wise reply of ADS. 21 Apr 2023
7.NASir, The Ministry has examined the reply of the Project Proponent in detail and noted that the Project Proponent has submitted the information after 4 years & 9 months. The Ministry has observed that the baseline data was carried out during October - December, 2016 and is 7 years old. The Ministry also noted that the Project Proponent has submitted the past production data for the period upto 31.10.2016. Hence, the Project Proponent is requested to revalidate the baseline data for one month and shall submit the comparison of data for both the seasons along with the lab reports, certified past production data from the Dept. of Mines and Geology as on date and District Survey Report approved by the SEIAA as per Ministry’s Notification S.O.3611(E) dated 25.07.2018 and in accordance with the order of Hon’ble Supreme Court dated 10.11.2021 in Civil Appeal Nos. 3661-3662 of 2020 titled as State of Bihar V/s Pawan Kumar. 16 May 2023
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 42 as per April 2017 List    iii. Name of Consultant: ENKAY ENVIRO SERVICES PVT. LTD.   iv. Address : #92, HEERA NAGAR -A, NEAR SHALIMAR BAGH, AJMER ROAD, JAIPUR   v. Mobile No.: 9314363996   vi. Landline No.: 01412354997   vii. Email Id: sbmineral086@gmail.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : S B MINERAL ENTERPRISES    ii. Designation : NIL    iii. Name of Company(Applicant Name should not be given here) : S B MINERAL ENTERPRISES    iv. Address : 22/B-22, OPPOSITE NRI COLONY, HALDI GHATI MARG, PRATAP NAGAR v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
Print