EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/CG/IND2/59931/2016    ii. MoEFCC File No. : J- 11011/341/2016-IA.II(I)    iii.Short narrative of the project: Proposed LPG Bottling Plant at Korba, Chhattisgarh by M/s Indian Oil Corporation Ltd.    iv. Project Sector : Industrial Projects-2    v. Company/Proponent : INDIAN OIL CORPORATION LIMITED
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.ChhattisgarhKorbaKatghora
2.ChhattisgarhKorbaKatghora
 
   vii.Date of TOR Granted 15 Mar 2017 viii.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 24 Apr 2017 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 31 Jan 2017   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: -
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAEAC after detailed deliberation has deferred the proposal for want of following additional information: 1. Number of trees to be cut, area and number of trees to be planted. 2. Number of trucks to be passing (in & out) and details of traffic management. 3. Details of fire hazardous management and the details in 3D model. 4. Comprehensive safety and risk assessment plan. 5. Details of pipeline for transport of materials and measures to control/detect leakage and accident/causality management plan. 6. Scientific reason for the acidific nature of the soil and assurance that due to the proposed project, the nature of soil and ground water will not get affected. 7. Revised layout plan with 10 m wide green belt with trees and 33% of area as green area with trees. 8. At least 2.5% of th 11 May 2017
2. ADS LetterDear sir, PFA ADS reply of 23rd EAC meeting (Infra 2) for your further action. 28 Jun 2017
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : QCI- NABET Certificate No. NABET/EIA/1417/SA0011.    iii. Name of Consultant: ULTRATECH   iv. Address : Saudamini commercial complex, building C3, 2nd floor, Paud road Kothrud Pune 38   v. Mobile No.: 9765982552   vi. Landline No.: 02025286106   vii. Email Id: bharati@ultratech.in
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Mr Umesh    ii. Designation : DGM (LPG)    iii. Name of Company(Applicant Name should not be given here) : INDIAN OIL CORPORATION LIMITED    iv. Address : Indian Oil Corpotation Limited Indian Oil Bhavan 16 arera Hills,Jail road Bhopal v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
Print