EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/KA/RIV/63297/2015    ii. MoEFCC File No. : J-12011/21/2015-I A-1    iii.Short narrative of the project: Veerabhadreshwara LIS    iv. Project Sector : River Valley and Hydroelectric Projects    v. Company/Proponent : KARNATAKA NEERAVARI NIGAM LTD
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.KarnatakaBelgaumRamdurg
2.KarnatakaBagalkotMudhol
 
   vii.Date of TOR Granted 17 Nov 2015 viii.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 20 Mar 2017 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 13 Jan 2017   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NA1. Economic viability of the project should be worked out based on the guidelines issued by CBIP, New Delhi, in April 2002 or so in regard to the planning and design of large lift irrigation schemes. The true (not subsidized) cost of electricity is to be considered for economic analysis. 2. Concept of conjunctive irrigation should also be introduced to derive its benefit for enhancing the command area. 3. Clearance of CWC with respect to Hydrology, Inter State Matter Aspects as per CWC Guidelines “Submission, Appraisal and Acceptance of Irrigation and Multipurpose Projects 2017” should be provided. 4. Data on surface water quality of all the stations should be verified once again with regards to all the seasons. 5. Inventorization of flora and fauna be updated based on IUCN classific 09 May 2017
2. ADS LetterDear sir, Please find enclosed the compliance to EAC observations and it is requested to issue the EC at the earliest. Regards Chief Engineer Irrigation North Zone, KNNL, Belagavi 23 Jun 2017
3.NAThis is with reference to your letter of EC proposal for the Verabhadreshwara Lift Irrigation Scheme Bagalkot District in Karnataka. 2. The following information is to be submitted:- i. Which fish species is the largest (umbrella fish) systems and its requirement of minimum flow during lean season. ii. The proof of firm power linkage document. iii. The cost of green belt development has been reduced, clarification to be provided. 20 Jul 2017
4. ADS LetterPlease find enclosed the Compliance to the observations. It is requested to issue the Environmental Clearance at the earliest since the project is implementing in drought prone areas. Chief Engineer KNNL Irrigation North Zone Belagavi Karnataka 26 Jul 2017
5.NADeferred the proposal for want of additional information. 29 Aug 2017
6. ADS LetterMoEF&CC mandates CWC Clearance for onward issue to Environmental Clearance to the subject project. CWC has published detailed guidelines, wherein, at Para no. 1.2 (Page-No.2), it was mentioned that, Environmental Clearance is one of the pre-requisite for examination of the DPR for issue of CWC clearance. Further, the Technical Advisory Committee (TAC) of CWC will not appraise the project for CWC clearance until submission of Environmental Clearance. In view of the above, it is requesting to issue the Environmental Clearance to the subject project with condition to obtain CWC Clearance. Accordingly, CWC clearance will also be obtained for the project and submitted to the Ministry. Yours faithfully Chief Engineer Irrigation North Zone KNNL, Belagavi Karnataka 06 Sep 2017
7.NAAs clearances from CWC for hydrology and inter-state aspect have not been obtained, the Committee deferred the proposal and advised the PP to obtain the same. 29 Sep 2017
8. ADS LetterDear Sir As per Amendment to EIA Notification dt: 14.08.2018, it is requesting to transfer the file to SEIAA since the project command area is less than 50000 ha. Yours faithfully Chief Engineer KNNL Irrigation North Zone Belgaum Karnataka 11 Sep 2018
9. ADS LetterFind enclosed 12 Nov 2018
10. ADS LetterDear Sir, Due to change in location of jackwell from Chikkur tanda to Chitrabhanukoti and the salient features of the project is also getting altered. In view of this, it is hereby decided to withdraw the proposal and hence kindly do the needful. Regards, Chief Engineer, KNNL, Irrigation North Zone, Belagavi 17 Mar 2021
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 55    iii. Name of Consultant: ENVIRONMENTAL HEALTH AND SAFETY CONSULTANTS PRIVATE LIMITED   iv. Address : 13/2 IST MAIN ROAD RAJAJINAGAR INDUSTRIAL TOWN BANGALORE   v. Mobile No.: 9886599677   vi. Landline No.: 08023012100   vii. Email Id: tubachilis@gmail.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Chief Engineer    ii. Designation : Chief Engineer    iii. Name of Company(Applicant Name should not be given here) : KARNATAKA NEERAVARI NIGAM LTD    iv. Address : 4th floor, coffee board building, Dr. Ambedkar Veedhi, Bangalore v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency