EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/MH/CMIN/62601/2008    ii. MoEFCC File No. : J-11015/165/2009-IA.II(M)    iii.Short narrative of the project: DURGAPUR EXTENSION DEEP OC    iv. Project Sector : Coal Mining    v. Company/Proponent : Western Coalfields Limited
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.MaharashtraChandrapurChandrapur
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded EC Compliance report viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 12 Jun 2008 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 17 Feb 2017 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 30 Oct 2009   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: None   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1. ADS Letter6.17.4 The Committee, after detailed deliberations, observed that the proposal does involve increase in land area from 1186.54 ha to 1597.50 ha even if the production capacity remains at 3 MTPA. The Committee further opined that although the fresh public hearing may not be required but there is a need to examine the compliance status of earlier EC conditions. The proposal was, therefore, deferred. 05 Jun 2017
2. ADS LetterAs directed by EAC in its 6th Meeting held on 22-02-2017 for EC of Durgapur Extension Deep OC Phase – II , a request has been made to RO, MoEF & CC, Nagpur vide letter dated 18-04-2017 enclosing latest compliance report of existing EC conditions in respect of Durgapur OC Expansion Project for conducting inspection and issuance of Compliance certificate. Subsequently, RO, MoEF & CC, Nagpur has issued a 10 point query vide letter no. 3-158/2012(ENV)/1786 dated 12-05-2017 which was received in this office on 22/05/2017. Reply to the query of RO, MoEF & CC, Nagpur is being prepared for onward submission to RO, MoEF & CC, Nagpur. 08 Jun 2017
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : NABET No/EIA/WCL/2015-16/DEC/24/01    iii. Name of Consultant: CENTRAL MINE PLANNING & DESIGN INSTITUTE LIMITED   iv. Address : Kasturba Nagar, Jaripatka, Nagpur - 440 014   v. Mobile No.: 8275970074   vi. Landline No.: 07122642134   vii. Email Id: wclenv@yahoo.in
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : KAUSHIK    ii. Designation : G.M (MINING)/ ENVIRONMENT.    iii. Name of Company(Applicant Name should not be given here) : Western Coalfields Limited    iv. Address : Coal Estate Civil lines, Nagpur-440001 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL
Print