EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/PB/IND/61921/2015    ii. MoEFCC File No. : J-11011/196/2014-IA.II(I)    iii.Short narrative of the project: Satia Industries LTD    iv. Project Sector : Industrial Projects-1    v. Company/Proponent : SATIA INDUSTRIES LTD
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.PunjabShri Muktsar SahibShri Muktsar Sahib
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: NIL viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 22 Jun 2016 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 21 Jan 2017 x.Project Type: Modernization
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 19 Oct 2016   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: None   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAAfter detailed deliberations, the committee desired the following information for further consideration of the proposal: i. Contingency plan for disposal of wastewater in monsoon season. ii. Action plan for recycling, reuse and reduce the wastewater specified by PP. iii. Details of bleaching sequence. iv. The quantity of the primary and secondary sludge generation and the method of disposal. v. Quantified assessment of impacts, mitigation measures and monitoring. vi. The project proponent shall reassess the quantity of water required for the pant and provide a revised water balance statement. vii. Enterprise Social Commitment based on Public Hearing issues and item-wise details along with time bound action plan. viii. Socio-economic development activities including skill deve 21 Mar 2017
2. ADS LetterWe have incorporated all information asked by committee members in EIAEMP report and same is uploaded for your kind perusal. 17 May 2017
3.NAThe project proponent has submitted the reply to ADS on 17th May 2017. The project proponent along with EIA consultant made presentation on the reply to ADS. The committee satisfied with the details submitted for point No. (i) to (vi) and observed that the details against point no (vii) and (viii) are not satisfactory. The non-compliances were not closed by Regional officer of MoEFCC. The committee desired that the PP shall obtain certificate from the regional office to the effect that the action plan for closure of non-compliances is acceptable. Therefore, the proposal is deferred till the certificate is submitted to the ministry. 15 Sep 2017
4.NAThe project proponent has submitted the reply to ADS on 17th May 2017. The project proponent along with EIA consultant made presentation on the reply to ADS. The committee satisfied with the details submitted for point No. (i) to (vi) and observed that the details against point no (vii) and (viii) are not satisfactory. The non-compliances were not closed by Regional officer of MoEFCC. The committee desired that the PP shall obtain certificate from the regional office to the effect that the action plan for closure of non-compliances is acceptable. Therefore, the proposal is deferred till the certificate is submitted to the ministry 21 Sep 2017
5. ADS LetterWith reference to our EC presentation held on 11.09.2017 and Additional Details Sought (ADS) on 22.09.2017, the committee asked us to provide additional information after detailed deliberations. We have incorporated all information asked by committee members. Please find enclosed herewith our point-wise reply 18 Nov 2017
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : NABET/EIA/1417/SA2002    iii. Name of Consultant: ECO CHEM SALES & SERVICES   iv. Address : Office Floor, Ashoka Pavilon-A, New Civil Road, Surat- 395 001   v. Mobile No.: 9824156296   vi. Landline No.: +91-261-2231630   vii. Email Id: rsshah06@yahoo.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Ajay    ii. Designation : M.B.B.S    iii. Name of Company(Applicant Name should not be given here) : SATIA INDUSTRIES LTD    iv. Address : Satia industries limited, Vill: Rupana, Dist: Muktsar v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL