EC Report
1.
Project Details
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? :
No
1.
Project Details
i. Proposal No. :
IA/HR/NCP/26556/2015
ii. MoEFCC File No. :
21-36/2015-IA-III
iii.Short narrative of the project:
Industrial estate (phase-II), Barwala
iv. Project Sector :
New Construction Projects and Industrial Estates
v. Company/Proponent :
HARYANA STATE INDUSTRIAL & INFRASTRUCTURE DEVELOPMENT CO. LTD.
vi.Details of State of the project
Details of State of the project
S.no.
State Name
District Name
Tehsil Name
1.
Haryana
Panchkula
Panchkula
vii.Date of TOR Granted
18 Jun 2015
viii.TOR letter issued by Ministry:
Annexure-TOR letter
ix.Date of Submission for EC:
11 Jan 2017
x.Project Type:
New
2.
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP:
Annexure-EIA/EMP
ii.Risk Assessment:
Annexure-Risk Assessment
iii.Public Hearing:
Annexure-Public Hearing
iv. Date of Public Hearing:
07 Oct 2016
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC:
Annexure-Additional Report/Study/Document
vi. Uploaded Cover Letter:
Annexure-Cover Letter
vii.Remarks:
Hardcopy of the Final EIA/EMP report od IE, Barwala Phsae II will be submitted once the Acknowledgement slip is recieved
3.
Additional Detail Sought
Additional Detail Sought
Sno.
ADS Letter
Remarks
Date of ADS
1.
NA
The project was considered by the EAC in its meeting held in April, 2017 which may be seen at http://environmentclearance.nic.in. The proposal was deferred for want of inputs as stated in para 3.7.2 of the minutes.
05 Jun 2017
2.
ADS Letter
ADS reply -Barwala,HSIIDC (Para- 3.7.2)
18 Jun 2018
3.
NA
EAC deferred the proposal and sought following information for further consideration of the proposal: (i) Copies of consents for Phase-1. (ii) Water balance for the proposed project. (iii) Green belt development plan. (iv) NOC from CGWA to be obtained. Impact assessment of ground water profile due to GW abstraction to be prepared and submitted to the EAC. (v) Detailed presentation be made to the queries queries raised in earlier EAC meetings vis-à-vis groundwater clearance
08 Aug 2018
4.
ADS Letter
ADS Reply Barwala HSIIDC
10 Apr 2019
5.
NA
Please submit Form2 application with all details
12 Apr 2019
6.
ADS Letter
Please find attached Form 2 along with Reply dated 10.04.2019
30 Aug 2019
7.
NA
Accredited Consultant Details
i. Accreditation status :
Yes
ii. Accreditation No. :
NABET/EIA/RA083/076
iii. Name of Consultant:
Grass Roots Research and Creations India (P) Ltd
iv. Address :
F: 374-375, Sector - 63, Noida - 201301, UP
v. Mobile No.:
8377904041
vi. Landline No.:
01204044630
vii. Email Id:
barwalahsiidc@gmail.com
5.
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
i. Name of Applicant :
Rohit
ii. Designation :
Manager
iii. Name of Company(Applicant Name should not be given here) :
HARYANA STATE INDUSTRIAL & INFRASTRUCTURE DEVELOPMENT CO. LTD.
iv. Address :
Haryana State Industrial & Infrastructure Development Corporation Limited (HSIIDC) plot no.-C-13-14, Sector-6, Panchkula, Haryana
v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
NIL