EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/HR/NCP/26556/2015    ii. MoEFCC File No. : 21-36/2015-IA-III    iii.Short narrative of the project: Industrial estate (phase-II), Barwala    iv. Project Sector : New Construction Projects and Industrial Estates    v. Company/Proponent : HARYANA STATE INDUSTRIAL & INFRASTRUCTURE DEVELOPMENT CO. LTD.
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.HaryanaPanchkulaPanchkula
 
   vii.Date of TOR Granted 18 Jun 2015 viii.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 11 Jan 2017 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 07 Oct 2016   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: Hardcopy of the Final EIA/EMP report od IE, Barwala Phsae II will be submitted once the Acknowledgement slip is recieved
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAThe project was considered by the EAC in its meeting held in April, 2017 which may be seen at http://environmentclearance.nic.in. The proposal was deferred for want of inputs as stated in para 3.7.2 of the minutes. 05 Jun 2017
2. ADS LetterADS reply -Barwala,HSIIDC (Para- 3.7.2) 18 Jun 2018
3.NAEAC deferred the proposal and sought following information for further consideration of the proposal: (i) Copies of consents for Phase-1. (ii) Water balance for the proposed project. (iii) Green belt development plan. (iv) NOC from CGWA to be obtained. Impact assessment of ground water profile due to GW abstraction to be prepared and submitted to the EAC. (v) Detailed presentation be made to the queries queries raised in earlier EAC meetings vis-à-vis groundwater clearance 08 Aug 2018
4. ADS LetterADS Reply Barwala HSIIDC 10 Apr 2019
5.NAPlease submit Form2 application with all details 12 Apr 2019
6. ADS LetterPlease find attached Form 2 along with Reply dated 10.04.2019 30 Aug 2019
7.NA

Accredited Consultant Details

   i. Accreditation status : Yes    ii. Accreditation No. : NABET/EIA/RA083/076    iii. Name of Consultant: Grass Roots Research and Creations India (P) Ltd   iv. Address : F: 374-375, Sector - 63, Noida - 201301, UP   v. Mobile No.: 8377904041   vi. Landline No.: 01204044630   vii. Email Id: barwalahsiidc@gmail.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Rohit    ii. Designation : Manager    iii. Name of Company(Applicant Name should not be given here) : HARYANA STATE INDUSTRIAL & INFRASTRUCTURE DEVELOPMENT CO. LTD.    iv. Address : Haryana State Industrial & Infrastructure Development Corporation Limited (HSIIDC) plot no.-C-13-14, Sector-6, Panchkula, Haryana v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL