1.
Project Details
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? :
No
1.
Project Details
i. Proposal No. :
IA/MH/NCP/60824/2016
ii. MoEFCC File No. :
21-5/2017-IA-III
iii.Short narrative of the project:
proposed residential development at S. No. 17/7, 22/2A, 17/6/1(1+2+3), 17/6/2, Kharadi Pune, Maharashtra
iv. Project Sector :
INFRA-1
v. Company/Proponent :
NYATI HOUSING
vi.Details of State of the project
Details of State of the project
S.no.
State Name
District Name
Tehsil Name
1.
Maharashtra
Pune
Haveli
vii. Uploaded EC Compliance report by rigional office of MoEFCC:
NIL
viii. Certified Monitoring report by RoMoEF:
Annexure-Uploaded Monitoring report
ix.Date of TOR Granted
N/A
ix.Date of Submission for EC:
03 Jan 2017
x.Project Type:
Expansion
2.
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP:
Annexure-EIA/EMP
ii.Risk Assessment:
Annexure-Risk Assessment
iii.Public Hearing:
Annexure-Public Hearing
iv. Date of Public Hearing:
08 Nov 2016
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC:
Annexure-Additional Report/Study/Document
vi. Uploaded Cover Letter:
Annexure-Cover Letter
vii.Remarks:
-
Additional Attachments, if any
S.no.
Attached File
Date of Submission
1.
EDS reply regarding previous EC letter
03 Jan 2017
3.
Additional Detail Sought
Additional Detail Sought
Sno.
ADS Letter
Remarks
Date of ADS
1.
NA
After detailed deliberation, the Committee sought following additional information: (i) Certified compliance report issued by the Regional Office on the environmental conditions stipulated in the earlier EC issued by the MoEF CC. (ii) Details of energy conservation measures to be taken (all points mentioned in the proposal such as orientation to support reduced heat gain, use of ASHRAE 90.1, use of ECBC compliant envelope measures to be supported through drawings and details in the proposal The proposal was deferred till the desired information is submitted. The above information shall be provided with the uploading of minutes on the website
07 Mar 2017
2.
ADS Letter
REPLY TO COMPLIANCE RAISED DURING 14TH EAC MEETING 1) Certified compliance report issued by the Regional Office on the environmental conditions stipulated in the earlier EC issued by the MoEF, 2)Details of energy conservation measures.
30 Mar 2017
4.
Accredited Consultant Details
i. Accreditation status :
Yes
ii. Accreditation No. :
NABET/EIA/1417/RA010
iii. Name of Consultant:
Ultra Tech Environment Consultancy and Laboratory
iv. Address :
Saudamini Commercial Complex, Building C-3, 2nd Floor, Right Bhusari Colony, Paud Road Kothrud, Pune - 411 038
v. Mobile No.:
9765982552
vi. Landline No.:
02025286106
vii. Email Id:
expansionkharadi@gmail.com
5.
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
i. Name of Applicant :
Jagdish
ii. Designation :
Executive Director and CEO
iii. Name of Company(Applicant Name should not be given here) :
NYATI HOUSING
iv. Address :
Nyati Unitree, Pune
v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
NIL