   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/TG/IND2/50585/2012    ii. MoEFCC File No. : J-11011/7/2013-IA II (I)    iii.Short narrative of the project: SVR Laboratories Pvt Ltd    iv. Project Sector : Industrial Projects-2    v. Company/Proponent : SVR LABORATORIES PVT LTD
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.TelanganaNalgondaPochampalle
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: NIL viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 29 Apr 2013 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 02 Dec 2016 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 27 Aug 2016   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: None   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAThe EAC has deliberated on the proposal and noted that (i) PP has not provided adequate green belt for the proposed plant. PP need to submit a revised layout plan with 10 metre width green belt development in the peripheral from the boundary of the project (ii) EAC desired that PP may plant 10,000 plants in the nearby village. (iii) Fresh water requirement will be 50 m/day (iv) Cyclone separator followed by bag filter will be provided to boiler and thermic floor heater. (v) PP need to submit the letter of commitment for full utilization of Fly ash to be produced by the proposed project by the Registered Brick Manufacturing Unit. EAC has decided to defer the proposal till the submission of above information/documents. 16 Jan 2017
2. ADS LetterRespected Sir, We herewith submite point wise response to the additional information sought by EAC. 27 Feb 2017
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 143    iii. Name of Consultant: Team Labs and Consultants   iv. Address : Team Labs and Consultants, B-115, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad, Telangana   v. Mobile No.: 9866415966   vi. Landline No.: 04023748555   vii. Email Id: teamlabs@gmail.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : P Nageswara Rao    ii. Designation : Managing Director    iii. Name of Company(Applicant Name should not be given here) : SVR LABORATORIES PVT LTD    iv. Address : SVR Laboratories Pvt Ltd H.No.7-1-307/14/F/52, Jayaprakash Nagar, Sanath Nagar, Hyderabad, Telangana v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL