EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/MH/NCP/60691/2016    ii. MoEFCC File No. : 21-71/2016-IA-III    iii.Short narrative of the project: The Broadway Lavim Developers Private Limited    iv. Project Sector : INFRA-1    v. Company/Proponent : LAVIM DEVELOPERS PRIVATE LIMITED
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.MaharashtraPunePune City
 
   vii.Date of TOR Granted N/A viii.TOR letter issued by Ministry: N/A ix.Date of Submission for EC: 28 Nov 2016 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 28 Nov 2016   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAthe Committee sought following additional information: (i) Certified compliance report issued by the Regional Office, Nagpur on the existing environmental conditions stipulated in environmental clearance. (ii) Give details of the past history of the project related to submission of application at the SEIAA Maharashtra. (iii) Respond to the comments made by the SEAC/SEIAA during the presentations at Maharashtra, based on minutes of SEAC/SEIAA meetings. (iv) Give a conformity status to conditions stipulated in Annexure XIV of the amended EIA notification of 09-12-2016. (v) Since both plots are separated by a road, Pl clarify whether utilities of the both buildings are common or separate. If separate utilities will be provided then give details. (vi) Copy of approved Sanction plan. Approval of the project from High Rise Building Committee of Maharashtra. (vii) Layout plan indicating road, greenbelt, drainage, sewer line, STP, solid waste handling area, rain water harvesting s 16 Jan 2017
2. ADS Letterwe are submitting reply of 12th EAC Infra-2 meeting item no. 11.04.12 for the project proposed project Broadway at Pune by Lavim Developers Pvt. Ltd. 04 Feb 2017
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 17    iii. Name of Consultant: Mahabal Enviro Engineers Pvt. Ltd.   iv. Address : Plot F-7, Road 21, MIDC Wagle Estate, Thane-400604   v. Mobile No.: 9821127972   vi. Landline No.: 28523154   vii. Email Id: mahabal.thane@gmail.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Alok    ii. Designation : DGM    iii. Name of Company(Applicant Name should not be given here) : LAVIM DEVELOPERS PRIVATE LIMITED    iv. Address : Blue ridge, Near Cognizant, Rajiv Gandhi Infotech Park-Phase-I, Hinjewadi, Pune v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL
Print