EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/MH/IND2/35354/2013    ii. MoEFCC File No. : J -11011/211/2010-IA –II    iii.Short narrative of the project: Extension of TOR for proposed expansion of a molasses based Distillery Unit (60 KLPD to 100 KLPD) at post Kisanveer Nagar, Tehsil Wai, Dist: Satara Maharashtra.    iv. Project Sector : Industrial Projects-2    v. Company/Proponent : KISAN VEER SATARA SAHAKARI SAKHAR KARKHANA LTD
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.MaharashtraSataraWai
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: NIL viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 31 Jul 2013 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 29 Nov 2016 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 03 Mar 2016   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: None   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAThe EAC noted that the EIA study has been carried out as per the TOR prescribed by EAC in its 10th meeting held on 31st July, 2013. The EAC after detailed deliberation and after examining the validity of TOR suggested the PP to submit the following: 1. The EAC was of the view that being an expansion project the Certified compliance report is the essential document to establish that all the conditions of the existing EC grant to the project vide letter no. J- 11011/496/2008-IA.II (I) dated 08.12.2008. The EAC suggested the PP to submit the same at the earliest for further consideration of the proposal. 2. Name of Registered Brick Manufacturing Unit to be provided giving commitments for full use of fly ash to be provided by the proposed unit. 3. Layout plan of the plant be revised 16 Jan 2017
2. ADS LetterWe are very much thankful to Expert Appraisal Committee (Industry-2) for appraising our above referred project in its 17th Meeting held on 29.12.2016 (Item no. 17.10.5) As per the minutes of the meeting, we were asked to comply with certain points raised by committee. The point wise reply to the queries raised is enclosed herewith. We hope that reply is in line with your requirement. 06 Apr 2017
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : QCI/NABET/ENV/ACO/16/06/0172 dated 16.06.2016    iii. Name of Consultant: Mahabal Enviro Engineers Pvt. Ltd.   iv. Address : Plot No. F-7, Road No. 21, Wagle Estate, Thane West - 400604, Maharashtra   v. Mobile No.: 9323058368   vi. Landline No.: 02221716389   vii. Email Id: kisanveersatara.dis@gmail.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : N    ii. Designation : I/C. Managing Director    iii. Name of Company(Applicant Name should not be given here) : KISAN VEER SATARA SAHAKARI SAKHAR KARKHANA LTD    iv. Address : P. O. Kisanveernagar, Tal: Wai, Dist: Satara, Maharashtra v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL