1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/MH/NCP/60414/2016    ii. MoEFCC File No. : 21-8/2017-IA-III    iii.Short narrative of the project: Expansion of “VICINIA” Residential project Plot Bearing CTS No. 15A,15C,15D,15E &15F Chandivali, Kurla, Mumbai Maharashtra by M/s. Forbes And Company Ltd., Mumbai    iv. Project Sector : INFRA-1    v. Company/Proponent : SHAHPOORJI PALLONJI AND COMPANY PRIVATE LIMITED
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.MaharashtraMumbai (Suburban)Kurla
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: NIL viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted N/A ix.Date of Submission for EC: 03 Jan 2017 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 31 Dec 1978   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: this is a category B project. EC letter and forms have been submitted in upload additional report category. you can find the EC letter along with form 1 and 1 A
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAAfter detailed deliberation, the Committee sought following additional information: (i) Certified compliance report issued by the Regional Office on the environmental conditions stipulated in the earlier EC issued by the MoEF CC. (ii) Action plan to prevent nearby lakes (i.e. Chandivali lake (0.5 Km) and Powai Lake (0.95 Km)) from water pollution from the proposed project. (iii) Detailed energy conservation measures to be taken (all points mentioned in the proposal such as orientation to support reduced heat gain, use of ASHRAE 90.1, use of ECBC compliant envelope measures to be supported through drawings and details in the proposal. The proposal was deferred till the desired information is submitted. The above information shall be provided with the uploading of minutes on the website 07 Mar 2017
2. ADS LetterSubmission of compliance as per MoM of 14th EAC meeting for Expansion of VICINIA” Residential project Plot Bearing CTS No. 15A,15C,15D,15E &15F Chandivali, Kurla, Mumbai, Maharashtra. By M/s. Forbes And Company Ltd. 17 Mar 2017
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 46    iii. Name of Consultant: EAEPL   iv. Address : Enviro Analysts and Engineers Private Limited. B-1003,Enviro House,10th floor| Western Edge-II, W.E Highway|Borivali(E),Mumbai-400066   v. Mobile No.: 9321619749   vi. Landline No.: 91-22 2854 1647   vii. Email Id: spre.environmental@gmail.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Subodh    ii. Designation : liasion    iii. Name of Company(Applicant Name should not be given here) : SHAHPOORJI PALLONJI AND COMPANY PRIVATE LIMITED    iv. Address : SP Centre, 41/44, Minoo Desai Marg, Colaba, Mumbai 400005 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL