EC Report
1.
Project Details
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? :
No
1.
Project Details
i. Proposal No. :
IA/UP/IND/59480/2011
ii. MoEFCC File No. :
J-11015/188/2011-IA. II(M)
iii.Short narrative of the project:
Aswan Silica Sand Beneficiation Plant
iv. Project Sector :
Industrial Projects-1
v. Company/Proponent :
Santhosh Mendon
vi.Details of State of the project
Details of State of the project
S.no.
State Name
District Name
Tehsil Name
1.
Uttar Pradesh
PRAYAGRAJ
Bara
vii.Date of TOR Granted
21 Sep 2011
viii.TOR letter issued by Ministry:
Annexure-TOR letter
ix.Date of Submission for EC:
06 Oct 2016
x.Project Type:
New
2.
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP:
Annexure-EIA/EMP
ii.Risk Assessment:
Annexure-Risk Assessment
iii.Public Hearing:
Annexure-Public Hearing
iv. Date of Public Hearing:
08 Jul 2013
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC:
Annexure-Additional Report/Study/Document
vi. Uploaded Cover Letter:
Annexure-Cover Letter
vii.Remarks:
NIL
3.
Additional Detail Sought
Additional Detail Sought
Sno.
ADS Letter
Remarks
Date of ADS
1.
NA
Based on the presentation made and discussions held, the Committee desired following information for further consideration of the project. i. Revised layout plan along with the proper indexing, showing green belt, waste disposal area etc should be submitted. ii. Detailed intermediate and final plan for disposal of waste generated in the form of clay, should be submitted. iii. Revised water balance should be submitted. iv. In view of higher PM in the ambient air, a plan to control ambient air quality should be submitted along with suggested mitigative measures. v. Risk Analysis Report should be submitted. vi. Detailed Comprehensive Environment Management Plan along with timelines and budget should be submitted. vii. In respect of SPM, Particla size analysis of <75 micron partic
28 Nov 2016
2.
ADS Letter
Dear Sir, We are hereby submitting point-wise reply, based on the MoM of the EAC meeting of 27th October 2016. We hope that the project would be appraised in the upcoming EAC meeting in December 2016 and our project can be granted EC. We request you to fast track the project in lieu of the project been already recommended by EAC on Non-Coal Mining as earlier this was part of a mining proposal.
13 Dec 2016
3.
NA
After detailed deliberation, it has been observed by the Committee that the ambient air quality of the area, especially the PM10 levels have already crossed the permissible limits. Therefore, the PP has to conduct a study for ‘post measures AAQ assessment’. The proposal shall be further considered once the detailed analysis of the present scenario vis-a-vis measures proposed to control the emissions generated from the project are worked out and presented before the committee along with the detailed EMP report. The PP will also provide the following information to be considered by the EAC for appraisal of the project. a) A report from the MNIT, Allahabad about the feasibility of use of clay waste generated from the beneficiation plant, as building material. b) Estimates of total length
10 Jan 2017
4.
ADS Letter
Dear Sir, We are hereby providing the reply towards the queries raised by you in the ADS raised on 10.01.2017. e hope that this would suffice to the requirement and we would be appraised in the upcoming EAC meeting as this is an old project which is being reconsideration again and was recommended for EC in 2014 by EAC non-coal mining MOEF&CC Regards Santhosh Mendon, PP
08 Feb 2017
4.
Accredited Consultant Details
i. Accreditation status :
Yes
ii. Accreditation No. :
List A, S. No.103 (Rev.45, Sept.27,2016
iii. Name of Consultant:
M/s Perfact Enviro Solutions Pvt. Ltd.
iv. Address :
501-507, 5th Floor, NN Mall, Mangalam Palace Sector 3, Rohini, New Delhi
v. Mobile No.:
9818346370
vi. Landline No.:
01147528467
vii. Email Id:
mmpl@mmplsand.com
5.
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
i. Name of Applicant :
Santhosh Mendon
ii. Designation :
Executive Director
iii. Name of Company(Applicant Name should not be given here) :
Santhosh Mendon
iv. Address :
Mineral House Hampankatta Mangalore
v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
NIL