1.
Project Details
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? :
No
1.
Project Details
i. Proposal No. :
IA/JH/IND/57731/2010
ii. MoEFCC File No. :
J-11011/492/2010-IA-II (I)
iii.Short narrative of the project:
IA/JH/IND/5317/2010
iv. Project Sector :
Industrial Projects-1
v. Company/Proponent :
DIVINE ALLOY AND POWER COMPANY LIMITED
vi.Details of State of the project
Details of State of the project
S.no.
State Name
District Name
Tehsil Name
1.
Jharkhand
Saraikela Khar
No Data
vii. Uploaded EC Compliance report by rigional office of MoEFCC:
NIL
viii. Certified Monitoring report by RoMoEF:
Annexure-Uploaded Monitoring report
ix.Date of TOR Granted
13 Apr 2010
x.TOR letter issued by Ministry:
Annexure-TOR letter
ix.Date of Submission for EC:
22 Jul 2016
x.Project Type:
Expansion
2.
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP:
Annexure-EIA/EMP
ii.Risk Assessment:
Annexure-Risk Assessment
iii.Public Hearing:
Annexure-Public Hearing
iv. Date of Public Hearing:
05 Nov 2012
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC:
None
vi. Uploaded Cover Letter:
Annexure-Cover Letter
vii.Remarks:
NIL
3.
Additional Detail Sought
Additional Detail Sought
Sno.
ADS Letter
Remarks
Date of ADS
1.
NA
Based on the presentation made and discussions held, the Committee desired additional information on the following for further consideration of the proposal: i. Title of the project should be revised and submitted. ii. Coal linkage details should be provided. iii. Contour map of the area should be superimposed on the layout map and submitted. iv. Submit the numbers of bag filters installed in the existing plant and proposed for the proposed expansion project. v. The air quality monitoring site map shown during the meeting should be revised and submitted vi. The predicted values for the air quality parameters should be rechecked. vii. Quantitative assessment of equipments to be installed at each source of pollution should be mentioned in tabular format. viii. Water balance stateme
22 Sep 2016
2.
ADS Letter
Reply to the observations made by 10th Reconstituted Expert Appraisal Committee during EAC meeting held on 29th August, 2016 regarding Environmental Clearance for Expansion of M/s Divine Alloys & Power Co. Limitedto Integrated Steel Plant at Village Palgam, Kaushalgarh, Chowka-Kandra Road, P.O. Ghatdulmi, Tehsil Chandil, District SaraikelaKharsawan, Jharkhand
06 Jan 2017
4.
Accredited Consultant Details
i. Accreditation status :
Yes
ii. Accreditation No. :
NABET/EIA/1316/IA001
iii. Name of Consultant:
Vardan Environet
iv. Address :
D-142, Sushant Lok-III, Sector 57 Gurgaon Haryana
v. Mobile No.:
9953147268
vi. Landline No.:
01244291036
vii. Email Id:
divinealloy111@gmail.com
5.
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
i. Name of Applicant :
Rajesh
ii. Designation :
Director
iii. Name of Company(Applicant Name should not be given here) :
DIVINE ALLOY AND POWER COMPANY LIMITED
iv. Address :
Divine House Club Road Ranchi
v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
NIL