1.
Project Details
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? :
No
1.
Project Details
i. Proposal No. :
IA/RJ/MIN/25377/2014
ii. MoEFCC File No. :
J-11015/388/2014-IA-II(M)
iii.Short narrative of the project:
Increase in production of Lime Stone
iv. Project Sector :
Mining Projects
v. Company/Proponent :
MANGALAM CEMENT LIMITED
vi.Details of State of the project
Details of State of the project
S.no.
State Name
District Name
Tehsil Name
1.
Rajasthan
Kota
Ramganj Mandi
vii. Uploaded EC Compliance report by rigional office of MoEFCC:
Annexure-Uploaded EC Compliance report
viii. Certified Monitoring report by RoMoEF:
Annexure-Uploaded Monitoring report
ix.Date of TOR Granted
17 Jun 2015
x.TOR letter issued by Ministry:
Annexure-TOR letter
ix.Date of Submission for EC:
04 Oct 2016
x.Project Type:
Expansion
2.
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP:
Annexure-EIA/EMP
ii.Risk Assessment:
Annexure-Risk Assessment
iii.Public Hearing:
Annexure-Public Hearing
iv. Date of Public Hearing:
06 Apr 2016
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC:
Annexure-Additional Report/Study/Document
vi. Uploaded Cover Letter:
Annexure-Cover Letter
vii.Remarks:
Due to file size limitation, for uploading on MoEF & CC website, we are herewith uploading Final EIA Report and part of approved Mining Plan without Figures, Annexures and Questionare Hard copy of Final EIA Report and Approved Mining Plan will be submitted to MoEF & CC enclosing Figure, Annexures and Questionnaire along with Acceptance
Additional Attachments, if any
S.no.
Attached File
Date of Submission
1.
Authenticated Map and Certificate of CFO
04 Oct 2016
2.
Authenticated Map and Certificate of DFO
04 Oct 2016
3.
Additional Detail Sought
Additional Detail Sought
Sno.
ADS Letter
Remarks
Date of ADS
1.
NA
The Committee deliberated at length the information submitted by PP and deferred the Proposal. The Consultant may also be warned for such type of discrepancies in the application.
09 Nov 2016
2.
ADS Letter
Clarification raised in 11th EAC meeting held during October-24-25, 2016.
23 Jan 2017
3.
NA
The Committee noted that the PP had not obtained NBWL clearance since the start of mining operation under the provisions of the Wildlife (Protection) Act, 1972 and has continued operations till date, hence, the Ministry may first ascertain and take view on whether this is a case of violation under the Wildlife (Protection) Act, 1972. The Committee deliberated on the proposal and deferred it, in view of the suspected violation the Wildlife (Protection) Act, 1972 pending decision from MoEF&CC and absence of approval of conservation plan from Chief Wildlife Warden of the State and update on implementation of conservation plan.
08 Mar 2017
4.
ADS Letter
We are submitting point wise additional information.
20 May 2017
4.
Accredited Consultant Details
i. Accreditation status :
Yes
ii. Accreditation No. :
NABET/EIA/1316/RA002
iii. Name of Consultant:
B. S. Envi-Tech Pvt Ltd.
iv. Address :
B. S. Envi-Tech Pvt Ltd., 4th floor, 'Amity Ville', H.No 12-13-1270/71/73, Tarnaka, Secunderabad - 500 017, Telangana, India
v. Mobile No.:
9848053012
vi. Landline No.:
04049783062
vii. Email Id:
sd.arya@mangalamcement.com
5.
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
i. Name of Applicant :
S S JAIN
ii. Designation :
PRESIDENT
iii. Name of Company(Applicant Name should not be given here) :
MANGALAM CEMENT LIMITED
iv. Address :
P.O.ADITYA NAGAR, MORAK-326520. KOTA Dist. Rajasthan
v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
NIL
Print