1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/GJ/IND2/57040/2015    ii. MoEFCC File No. : J-11011/203/2015-IA-II (I)    iii.Short narrative of the project: Cedar Decor Pvt Ltd.    iv. Project Sector : Industrial Projects-2    v. Company/Proponent : M/S. CEDAR DECOR PVT LTD.
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.GujaratMahesanaKadi
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: NIL viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 13 Oct 2015 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 14 Jul 2016 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 31 May 2016   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: None   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: we have uploaded sign copy of TOR in Additional details.
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAAfter deliberations, the Committee sought the following additional information: (i) Revised water balance with recycle and reuse to reduce fresh water requirement by adopting 3 Rs method to be submitted. Recheck the boiler water requirement. (ii) Enterprise Social Commitment (ESC) (@ 5% of project cost) based on local needs to be drawn alongwith action plan with financial and physical breakup/details. (iii) Rain water harvesting to be done. The proposal was deferred till the desired information is submitted. The above information shall be provided with the uploading of minutes on the website. 24 Oct 2016
2. ADS LetterWE HAVE UPLOADED REQUIRED DETAILS ASK BY THE COMMITTEE MEMBERS. 06 Dec 2016
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 16    iii. Name of Consultant: BHAGWATI ENVIRO CARE PVT LTD.   iv. Address : 28,29,30, parmeshwar Estate II, Phase I, GIDC Estate, Vatva, Ahmedabad, Gujarat.   v. Mobile No.: 9824051541   vi. Landline No.: 07940083051   vii. Email Id: stharad@cedarindia.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Bijaykumar    ii. Designation : Director    iii. Name of Company(Applicant Name should not be given here) : M/S. CEDAR DECOR PVT LTD.    iv. Address : 65/p, Ankhol Patia, kadi Road, Ta - Kadi, Dist - Mehsana, Gujarat v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL