1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Development/Redevelopment of Common Central Secretariat Buildings and Central Conference Centre along with Prime Minister’s Residence, SPG Building and Vice President's Enclave, New Delhi | (b)Name of the Company / Organisation | CENTRAL PUBLIC WORKS DEPARTMENT | (c)Registered Address | Central Vista Project Division-1, CPWD, A-201, IP Bhawan, IP Estate New Delhi,,New Delhi,Delhi-110001 | (d)Legal Status of the Company | Central Government | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Ashwani Mittal | (b)Designation (Owner/ Partner/ CEO) | Executive Engineer | (c)Address | Central Vista Project Division-1, CPWD, A-201, IP Bhawan, IP Estate New Delhi,,Connaught Place,New Delhi,Delhi-110001 | (d)Pin code | 110001 | (e)E-mail | ashwani.mittal@gov.in | (f)STD Code. | 0(f)Telephone No. | | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 8(b) Townships and Area Development projects.
| Minor Activity | | (b)Category | B1 | Reason for Applying at Ministry | SEIAA | (c)Proposal Number | IA/DL/MIS/206262/2020 | (d)Master Proposal Number(Single Window) | SW/206237/2021 | (e)EAC concerned (for category A Projects only) | INFRA-2 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Plot No. 137, 120, 22A, 22B, 22C, 23D, 23C, 23B, 1 | (b)Pincode | 110001 | (c)Bounded Latitudes (North) | | From | | Degree | 28.6108 | Minutes | | Second | | From | | Degree | 28.6147 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 77.1997 | Minutes | | Second | | From | | Degree | 77.2269 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | H43X2, H43X6 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 220 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 2.71 | (j)Seismic Zone | 4 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Delhi | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | F. No. 21-105/2020-IA-III | (c)Date of Issue of TOR | 04 Jan 2021 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 27 Mar 2021 | (c)Date of Issue of EC | 31 May 2021 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | Since it is a 8(b)- Townships and Area Development projects hence public hearing is not applicable | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Lucknow | (iii)Letter No. | NA | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Jan 4 2021 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Built up Area | 458820 | 1262680 | 1721500 | Others | sq.m | Road,Rail | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Built up Area | 458820 | 1262680 | 1721500 | | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 04 Jan 2021 | (iv)Valid Upto | 04 Jan 2021 | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 13450 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 113.91 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 5 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 16.89 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 15520 | (b)Existing quantity of raw material/fuel | 0 | (c)Total quantity of raw material/fuel | 15520 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | HSD | 15520 | Others | Litre per hour | Nearby Areas | Road | | 10 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2020 To 30 Dec 2020 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 481 | 93 | 357 | 100 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 398 | 48 | 269 | 60 | (3.) | SO2 | | Micro Gram per Meter Cube | 26.5 | 8.2 | 20 | 80 | (4.) | NOx | | Micro Gram per Meter Cube | 123.5 | 25.2 | 92 | 80 | (5.) | Others | Ozone | Micro Gram per Meter Cube | 62.5 | 2.3 | 43 | 100 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.74 | 7.01 | 6.5 | 8.5 | (2.) | TDS | | | mg/l | | 2444 | 420 | 500 | 2000 | (3.) | Total Hardness | | | mg/l | | 1000 | 340 | 200 | 600 | (4.) | Heavy Metals | | Nickel | mg/l | | 0.02 | 0.0 | 0.02 | 0.0 | (5.) | TSS | | | mg/l | | 2 | 0 | 0 | 2 | (6.) | Others | Total Alkalinity | | mg/l | | 190 | 40 | 200 | 600 | (7.) | Fluoride | | | mg/l | | 1.07 | 0.06 | 1 | 1.5 | (8.) | Chlorides | | | mg/l | | 606 | 64 | 250 | 1000 | |
14.3. No. of Surface Water monitoring locations : 09 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | BOD | | mg/l | | 60 | 6 | E | (2.) | pH | | NA | | 8.41 | 6.97 | E | (3.) | DO | | mg/l | | 5.8 | 0.2 | E | (4.) | COD | | mg/l | | 180 | 18 | E | (5.) | Others | Sulphate | mg/l | | 1401 | 64 | E | |
14.4. No. of Ambient Noise monitoring locations : 11 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 67 | 49 | 65 (Commercial) | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 66 | 43 | 55 (Commercial) | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | Electric Conductivity | Others | dS/cm | 656 | 347 | (2.) | K(Potassium) | Others | g/kg | 1853 | 266 | (3.) | N(Nitrogen) | Others | % | 0.83 | 0.02 | (4.) | P(Phosphorus) | Others | kg/ha | 197 | 66 | (5.) | pH | Others | - | 7.62 | 6.55 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 25 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 25 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | NDMC through Delhi Jal Board | 2609 | 5 | Copy of Permission Letter | modeOthers | NDMC supply | Others | NA | No.D/ 176 /EE(WS) | 17 Feb 2021 | 2609 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Sewage | 3928 | 4100 | MBR | Reuse within the Plant & Recycling | | 3928 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 3928 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 3928 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Biodegradable Waste | Municipal Solid Waste | | 5924 | Tons | 0 | Others | Internal raod | Others | Composting using OWC | (2.) | Non-biodegradable Waste | Municipal Solid Waste | | 7240 | Tons | 5 | Others | Authorized vehicle | Others | NDMC/ Sold to authorized recyclers | (3.) | Inert Waste | Municipal Solid Waste | | 1496 | Tons | 5 | Others | Authorized vehicle | Others | NDMC/ Sanitary landfill site | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 139 | 0 | 0 | 139 | 60 | (2.) | PM10 | | Microgram per Meter Cube | 219 | 0.5 | 6.4 | 225.4 | 100 | (3.) | SO2 | | Microgram per Meter Cube | 16.3 | 0.5 | 0.06 | 16.36 | 80 | (4.) | NOx | | Microgram per Meter Cube | 68.5 | 0.5 | 0.07 | 68.57 | 80 | (5.) | Others(Specify) | CO | Microgram per Meter Cube | 1.19 | 0.5 | 0.14 | 1.33 | 4 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DG sets (2500 kVA)-8 Nos. CCS 4,5,9 & CCC | 4160 | 42 | 0.5 | SO2 | | 0.003 gm/sec | (2.) | DG sets (2500 kVA)-8 Nos. CCS 4,5,9 & CCC | 4160 | 42 | 0.5 | NOx | | 0.0015 gm/sec | (3.) | DG sets (2000 kVA)-26 Nos. (CCS 1-10) | 10140 | 42 | 0.5 | PM10 | | 75 mg/Nm3 | (4.) | DG sets (2000 kVA)-26 Nos. (CCS 1-10) | 10140 | 42 | 0.5 | NOx | | 0.0013 gm/sec | (5.) | DG sets (2000 kVA)-26 Nos. (CCS 1-10) | 10140 | 42 | 0.5 | Others | HC | 0.18 gm/sec | (6.) | DG sets (1500 kVA)-4 Nos. (VPE, PMR, SPG, CCS 10) | 1220 | 33 | 0.4 | PM10 | | 75 mg/Nm3 | (7.) | DG sets (1500 kVA)-4 Nos. (VPE, PMR, SPG, CCS 10) | 1220 | 33 | 0.4 | SO2 | | 0.002 gm/sec | (8.) | DG sets (1500 kVA)-4 Nos. (VPE, PMR, SPG, CCS 10) | 1220 | 33 | 0.4 | Others | HC | 0.10 gm/sec | (9.) | DG Sets (1500 kVA)-4 Nos. (VPE, PMR, SPG, CCS10) | 1220 | 33 | 0.4 | Others | CO | 150 mg/Nm3 | (10.) | DG sets (2500 kVA)-8 Nos. CCS 4,5,9 & CCC | 4160 | 42 | 0.5 | Others | HC | 0.21 gm/sec | (11.) | DG sets (2500 kVA)-8 Nos. CCS 4,5,9 & CCC | 4160 | 42 | 0.5 | Others | CO | 150 mg/Nm3 | (12.) | DG sets (2000 kVA)-26 Nos. (CCS 1-10) | 10140 | 42 | 0.5 | Others | CO | 150 mg/Nm3 | (13.) | DG sets (1500 kVA)-4 Nos. (VPE, PMR, SPG, CCS 10) | 1220 | 33 | 0.4 | NOx | | 0.0007 gm/sec | (14.) | DG sets (2500 kVA)-8 Nos. CCS 4,5,9 & CCC | 4160 | 42 | 0.5 | PM10 | | 75 mg/Nm3 | (15.) | DG sets (2000 kVA)-26 Nos. (CCS 1-10) | 10140 | 42 | 0.5 | SO2 | | 0.002 gm/sec | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 81555 | (b)Source | NDMC | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 2,500 kVA x 8; 2,000 kVA x 26 & 1,500 kVA x 4 | (e)Stack Height (in m) | 42 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 50.63 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 50.63 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 1667 | (b)Waste/Barren Land (ha.) | 1807 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 1567 | (e)Settlements (ha.) | 24377 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 1137 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Vegetation cover & other land | 13255 | Total (ha.) | 43810.0000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Others | Township and Area development | 50.63 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | NPA | Okhla Bird Sanctuary | 8.58 | Bird Sanctuary | (2.) | Critically Polluted Area | Najafgarh Drain | 7.24 | -- | (3.) | ESZs | Okhla Bird Sanctuary | 8.58 | ESZ & IBA | (4.) | Wildlife Corridors | None | 0 | - | (5.) | ESAs | None | 0 | - | (6.) | WLS | Okhla Bird Sanctuary | 8.58 | ESZ & IBA | (7.) | Corridors | None | 0 | - | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Northern Ridge | 5.79 | North direction | (2.) | Archaeological Sites | | Jantar Mantar | 1.2 | NNE direction | (3.) | Defence Installations | | Vayu Bhawan | 0.24 | W direction | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | | (b)No. of Households | | (c)No. of PDFs (Project Displaced Families) | | (d)No. of PAFs (Project Affected Families) | | (e)Funds Allocated for R&R(in INR) (in Lacs) | | (f)Status of R&R | NA | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | 30 species from study area | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Yamuna River | (ii)Direction of Water Bodies in Buffer Area | East | (iii)Distance of Water Bodies in Buffer Area | 2.71 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 0 | (c)Temporary Employment- During Construction | 46700 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 365 | (f)Total Manpower | 46700 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 41009 | 40211 | 81220 | (2.) | Percentage of Total Project Area | 8.09 | 7.94 | 16.03 | (3.) | No. of Plants | 1412 | 1753 | 3165 | (4.) | Funds Allocated | 0 | 123450000 | 123450000 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | The Common Central Secretariat will consolidate all ministries of the Government of India and improve productivity and efficiency of administration. The Central Conference Centre will cater to their conferencing needs. These will also be connected by a people mover to the Delhi Metro. Modern and secure residential facilities for the Vice President and the Prime Minister will be equipped with all necessary spaces and infrastructure, including the Special Protection Group. | (2.) | Environmental | Landscape/greenbelt development, traffic decongestion, provision of STP, OWC, safety aspects including fire-fighting system, maximum use of treated waste water, well-designed network of storm water drains, rain water harvesting system etc. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For INFRA-2 |
|
1. | Details of Building Construction: | (a)Maximum Height of the Building (Meters) | 40 | (b)Total No. of Flats to be Build | 0 | (c)No. of Buildings | 54 | (d)Total plot area (sqm) | 506402.82 | (e)Total built up area (sqm) | 1721500 | |
|
2. | Foreshore Facilities and/or Marine Disposal: | (a)Whether Project Involves Foreshore Activities and/or marine Disposal? | No | |
|
3. | Rain Water Harvesting: | (a)No. of Storage | 8 | (b)Capacity | 3050 | (c)No. of Recharge Pits | 0 | (d)Capacity | 0 | |
|
4. | Parking: | (a)Details of 4 Wheeler/ 2 Wheeler Parking | 14095 ECS | |
|
5. | Energy Saving Measures: | (a)Source/Mode | Solar water heating and lighting and by following | (b)Percentage | 7 | (c)Quantity | 0 | |
|
|
7. Type of Industries to be established with Industrial Estate as per their category A/B |
---|
S. No. | Type of Industry | No. of Units | Category A/B |
---|
NIL | |
8. | Length of the alignment | N/A | |
|
9. | Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass | Details Not Applicable | |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | Yes | (b)Name of the Court | Supreme Court of India | (c)Case No. | Attached | (d)Orders/Directions of the court ,if any and its relevance with the proposed project | Details are provided in attached document. | (e)Case Details | Attached | (f)Uploaded Court Order | Copy of Court Order | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1922/RA 0138 | (ii)Name of the EIA Consultant | Kadam Environmental Consultants | (iii)Address | 871/B/3, GIDC Makarpura, Vadodara, India – 390 010 | (iv)Mobile No. | 9016706466 | (v)Landline No. | 0265613100 | (vi)Email Id | kadam@kadamenviro.com | (vii)Category of Accreditation | B | (viii)Sector of Accreditation | INFRA-2 | (ix)Validity of Accreditation | 22 May 2022 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Ashwani Mittal | Designation | Executive Engineer | Name of Company (Applicant Name should not be given here) | CENTRAL PUBLIC WORKS DEPARTMENT | Address | Central Vista Project Division-1, CPWD, A-201, IP Bhawan, IP Estate New Delhi |
|