Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Bhavisha Industries
(b)Name of the Company / Organisation M/S. BHAVISHA INDUSTRIES
(c)Registered Address Plot No. 1705, 3rd Phase, GIDC Estate, Vapi - 396191, Dist. Valsad, Gujarat,,Valsad,Gujarat-396191
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Kishor Shrinivas Gupte
(b)Designation (Owner/ Partner/ CEO) GM
(c)Address Plot No. 1705, 3rd Phase, GIDC Estate, Vapi - 396191, Dist. Valsad, Gujarat,,Pardi,Valsad,Gujarat-396191
(d)Pin code 396191
(e)E-mail shailesh@gpcpl.net
(f)STD Code. 0(f)Telephone No. 2431587
(g)Fax No. 0000000
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category B1
   Reason for Applying at Ministry general
(c)Proposal Number IA/GJ/IND2/180046/2019
(d)Master Proposal Number(Single Window) SW/180035/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 3
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. M/s. Bhavisha Industries Plot No. 1705, Phase - I
(b)Pincode 396195
(c)Bounded Latitudes (North)
From
Degree 2253867.90
Minutes
Second
From
Degree 2253925.99
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 285563.76
Minutes
Second
From
Degree 285684.15
Minutes
Second
(e)Survey of India Topo Sheet No. 46d-15, 46H-3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 31
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 2.06
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number SIA/GJ/8401/2019
(b)Date of Apply of TOR 16 Jan 2019
(c)Date of Issue of TOR / Standard ToR 10 Apr 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? No
(c)Reason The proposed new project is located in the Notified Industrial area of Vapi GIDC, which was established before 2006.
(d)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)PEG Based Polycarboxylate Ether liquid50 KL6 Nos.
(2.)D.G Set250 KVA x 1, 500 KVA x 1--
(3.)Hot Air Generator25 lakhx 1--
(4.)Sulphuric Acid25 KL1 Nos.
(5.)Oleum 23%15 KL2 Nos.
(6.)Formaldehyde25 KL2 Nos.
(7.)Caustic Soda Lye40 KL2 Nos.
(8.)Naphthalene based dispersing agent liquid40 KL x 4 Nos,60 KL x 4 Nos, 30 KL x 1 No40 KL x 4 Nos,60 KL x 4 Nos, 30 KL x 1 No
(9.)Sulphonator8 KL2 Nos.
(10.)Lead Bonded Reactor16 KL4 Nos.
(11.)Glass Lined16 KL x 3 Nos., 12.5 KL x 1 No.16 KL x 3 Nos., 12.5 KL x 1 No.
(12.)PP Neutralizer25 KL2 Nos.
(13.)SS Mixer30 KL x 1 Nos., 10 KL x 1 Nos., 5 KL x 2 Nos.20 KL x 1 Nos., 15 KL x 1 Nos., 5 KL x 1 Nos.
(14.)SS Reactor10 KL x 4 Nos., 8 KL x 2 Nos.,5 KL x 2 Nos.2.5 KL * 2 Nos.
(15.)Spray Dryer1000 kg/Hr x 2,500 kg/Hr. X 1--
(16.)Ribbon Blender5 KL x 1, 3 KL x 1,1 KL x 1--
(17.)Boiler2000 Kg/H X 3--
(18.)PP Vessel20 KL x 2 Nos., 30 KL x 3 Nos.20 KL x 2 Nos., 30 KL x 3 Nos.
(19.)MS Mixer25 KL x 3 Nos., 15 KL x 3 Nos., 10 KL x 1 Nos.25 KL x 3 Nos., 15 KL x 3 Nos., 10 KL x 1 Nos.
(20.)Air Compressor7.5 HP x 2--
(21.)Chilling Plant120 TR x 2--
(22.)Phenol30 KL1 Nos.
(23.)Phenol based Disp. Agent liquid30 KL3 Nos.
(24.)Thermopack10 lakh K.calx 1--
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Dispersing Agents72000Tons per AnnumRoad
(2.)Leather Chemicals6000Tons per AnnumRoad
(3.)Biaxial oriented polypropylene (BOPP) Self Adhesive3600Tons per AnnumRoad
(4.)Waterproofing polymer3600Tons per AnnumRoad
(5.)PEG Based Polycarboxylate Ether (Liquid & Powder)36000Tons per AnnumRoad
(6.)Admixture for Concrete and Dyes Industries (Non-EC Product)36000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. --
(vi)Application No. --
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 12.3094
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.595
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.4925
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.316
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 40
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 40
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Ammonia49.2Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(2.)Acetic acid41.52Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(3.)Acrylic acid1152Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(4.)Butyl Acrylate2811.6Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(5.)retarder2160Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(6.)Adipic Acid68.4Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(7.)formaldehyde12693.24Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(8.)Pthalic Anhydride34.2Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(9.)Sodium ligno sulphate342Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(10.)Caustic Lye.17361.72Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(11.)Fumaric acid34.2Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(12.)G Salt2069.28Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(13.)Chlorinated Paraffin369.12Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(14.)Hypochlorite23.28Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(15.)Potassium per sulphate134.4Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(16.)Sulfuric Acid23106.48Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(17.)Sodium Sulphate2133.56Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(18.)Hydrated Lime / quicklime744Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(19.)Methacrylic acid592.44Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(20.)EDTA77.58Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(21.)n Butanol1440Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(22.)PEG21600Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(23.)Naphthalene13838.76Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(24.)Oleum-23%5187.6Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(25.)Soda ash209.28Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(26.)Styrene9.00Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
(27.)Phenol4317.48Tons per AnnumManufacturerRoad125 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2019 To 31 Dec 2019
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube23.0010.0020.7380 per 24 Hr
(2.)NOxMicro Gram per Meter Cube37.0013.0030.3280 per 24 Hr
(3.)PM10Micro Gram per Meter Cube127.0053.0094.77100 per 24 Hr
(4.)PM2.5Micro Gram per Meter Cube63.0015.0043.2560 per 24 Hr
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.97.86.58.5
(2.)OthersTotal Alkalinitymg/l306.3214.42000
(3.)TDSmg/l6264445002000
(4.)Total Hardnessmg/l373.6261.4200600
(5.)OthersSulphate as SO4-2mg/l28.519.1200400
(6.)Fluoridemg/l0.40.211.5
(7.)Chloridesmg/l99.761.62501000
(8.)OthersTurbidityOthersNTU0.10.115
(9.)OthersMagnesiummg/l39.222.530100
(10.)OthersNitratemg/l8.13.14545
(11.)TSSmg/l0000
(12.)Heavy MetalsLeadmg/l0000.1
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l96.812.2E
(2.)pHNA8.257.19A
(3.)DOmg/l5.501.13E
(4.)BODmg/l275D
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))68.5446.0475
(2.)Leq(Night)A-weighted decibels(dB(A))62.4438.7870
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.296.65
(2.)N(Nitrogen)Milligram per Kilogram284.1105.0
(3.)P(Phosphorus)Milligram per Kilogram32.2315.05
(4.)K(Potassium)Milligram per Kilogram217.354.8
(5.)Electric ConductivityMillisiemens per Centimetre269.88125.28
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 3 To 9
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.5 To 2
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersGIDC Pipeline210.500 Not Appliacble PipelineOthersGIDC Pipeline04.02.201904 Jan 2019215
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic2.000To septic tank to Disinfection system & Holding Tank & the disinfected sewage to be reused for gardening.Green Belt Renewal Plant2.00
(2.)Industrial5.6010.00ETPOthersTo Spray dryer05.60
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 7.6
(b)Total Discharged Water (Kilolitre per Day) 5.6
(c)Total Reused Water (Kilolitre per Day) 2
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Discarded Durm/Liners/Bags/CarboysHazardous Waste (as per Hazardous and Other Waste Management rules 2016)125.00Tons25RoadAuthorized Recyclers
(2.)Used Filter ClothsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1.00Tons130.00RoadCo-Processing
(3.)Scrubber BleedoffHazardous Waste (as per Hazardous and Other Waste Management rules 2016)290.00Tons0RoadOthersTo be managed with other wastewater using ETP.
(4.)ETP WasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)15.00Tons130.00RoadTreatment, Storage and Disposal Facility(TSDF)
(5.)Spent/Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.09Kilolitre25RoadAuthorized Recyclers
(6.)Process wasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)400.00Tons130RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube17.5401.5619.1080/24 Hr
(2.)NOxMicrogram per Meter Cube25.92016.7242.6580/24 Hr
(3.)PM2.5Microgram per Meter Cube41.8300.0741.9160/24 Hr
(4.)PM10Microgram per Meter Cube100.1702.48102.66100/24 Hr
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Steam BoilerNatural Gas150.30PM100.00002
(2.)Steam BoilerNatural Gas150.30SO20.00002
(3.)DG SetDiesel110.35SO20.0277
(4.)Steam BoilerNatural Gas150.30NOx0.00002
(5.)ThermopackNatural Gas150.40PM100.00004
(6.)DG SetDiesel110.25PM100.0297
(7.)Hot Air GeneratorNatural Gas150.30PM100.0027
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 600
(b)Source DGVCL(Gujarat Electric Board)
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 200 KVA x 1 no, 500 KVA x 1 no
(e)Stack Height (in m) 11
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0.6213
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 0.6213
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 25781
(b)Waste/Barren Land (ha.) 2021
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1681
(e)Settlements (ha.) 4959
(f)Industrial (ha.) 2538
(g)Forest (ha.) 579
(h)Mangroves (ha.) 61
(i)Marine Area (ha.) 0
(j)Others (ha.) : mudflat, Rock Out Crop 297
    Total (ha.) 37917.0000
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area0.28334-
(2.)Green belt0.121-
(3.)OthersParking & Open Area0.21696-
Total (ha.) 0.6213
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESZsNot within the study area0-
(2.)Critically Polluted AreaVapi0Project Site In GIDC Vapi
(3.)WLSNot within the study area0-
(4.)CorridorsNot within the study area0-
(5.)NPANot within the study area0-
(6.)ESAsNot within the study area0-
(7.)Wildlife CorridorsNot within the study area0-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNear Morai6.25-
(2.)Defence InstallationsNot within study area0-
(3.)Archaeological SitesNot within study area0-
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.62
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired -
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Common Indian monitor and Common Peafowl
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made -
(iii)Period of Implementation Continuous
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Rati Nadi
(ii)Direction of Water Bodies in Buffer Area Select
(iii)Distance of Water Bodies in Buffer Area 2.06
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 312
(f)Total Manpower 100.00
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.12
(b)Percentage of Total Project Area 19.31
(c)No. of Plants to be Planted 182
(d)Funds Allocated for Plantation 325000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialCompany has planned to spend Rs.9.85 Lakhs/Annum for CSR activities. Which will result in development or improvement of many public amenities/facilities of the area. This CSR activities will also be helpful to improve quality of life as well as improvement of Health, Education and skill of local people. Employment to 100 people from local area. In addition to this, indirect employment will also have similar benefits. These together will be considerably helpful in increase of per capita income of
(2.)EnvironmentalThe adequate greenbelt will be developed at the periphery of plant premises as well as in some open area within the premises which admeasures 1202 Sq. Mt. (19 % of total plot area). Additional Plantation for additional greenbelt within premises on side of road building (approx. 1-1.5 Mt belt) will be done which will significantly increase the total effective greenbelt area.
(3.)FinancialCompany will pay the taxes & other levies, which will be considerably beneficial to the Government Exchequer. The proposed products are well established and acceptable in the international markets. Hence the proposed project will significantly help the country’s economic by supplying the products against the very high demand replacing supply from imported materials
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Industrial Projects - 3
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 28
(ii)Name of the EIA Consultant Unistar Environment & Research Labs Pvt. Ltd.
(iii)Address C-24White House, Near GIDC Office, Vapi –396195
(iv)Mobile No. 9909946373
(v)Landline No. 0260243561
(vi)Email Id unistar@uerl.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 3
(ix)Validity of Accreditation 03 Jan 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantKishor Shrinivas Gupte
DesignationGM
Name of Company (Applicant Name should not be given here)M/S. BHAVISHA INDUSTRIES
AddressPlot No. 1705, 3rd Phase, GIDC Estate, Vapi - 396191, Dist. Valsad, Gujarat