1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Expansion of molasses based distillery from 30 KLPD to 110 KLPD by Chidanand Basaprabhu Kore Sahakari Sakkare Karkhane Niyamit, Chikodi | (b)Name of the Company / Organisation | CHIDANAND BASAPRABHU KORE SAHAKARI SAKKARE KARKHANE NIYAMIT, CHIKKODI | (c)Registered Address | S. No. 184, 185, 186, 455, 456, 621, 626, 627, 631,Village Nanadi & Kerur,Belgaum,Karnataka-591247 | (d)Legal Status of the Company | Others | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Raveendra R Desai | (b)Designation (Owner/ Partner/ CEO) | MD | (c)Address | S. No. 184, 185, 186, 455, 456, 621, 626, 627, 631,Village Nanadi Kerur,Chikodi,Belgaum,Karnataka-591247 | (d)Pin code | 591247 | (e)E-mail | dk.environ@gmail.com | (f)STD Code. | 833(f)Telephone No. | 267200 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(g) Distilleries
| Minor Activity | 1(d) Thermal Power Plants
| (b)Category | A | (c)Proposal Number | IA/KA/IND2/179926/2000 | (d)Master Proposal Number(Single Window) | SW/179917/2020 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 3 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | S. No.184, 185, 186, 455, 456, 621, 626, 627& 631, | (b)Pincode | 591247 | (c)Bounded Latitudes (North) | | From | | Degree | 16303.45 | Minutes | | Second | | From | | Degree | 163046.38 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 743635.45 | Minutes | | Second | | From | | Degree | 743713.7 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 47L10, 47L11 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 570 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 6 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Karnataka | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-11011/8/2000-IA II(I) | (c)Date of Issue of TOR | 19 Mar 2001 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 21 Oct 2020 | (c)Date of Issue of EC | 08 Feb 2021 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 09 Jul 2020 | Distance of Public Hearing Venue from the Proposed Project : | 0.1 |
| Industrial site-S. No.:184, 185, 186, 455, 456, 621, 626, 627& 631, Village- Nanadi & Kerur | State : | Karnataka | District : | Belgaum | Tehsil : | Chikodi | Village : | Nanadi & Kerur |
| 80 | No issues raised by locals & farmers. Infact, project was
welcomed by residents | Others | Additional Deputy Commissioner & Additional District Magistrate | (2.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 09 Jul 2020 | Distance of Public Hearing Venue from the Proposed Project : | 0.1 |
| Industrial site at 184, 185, 186, 455, 456, 621, 626, 627& 631, Village- Nanadi & Kerur | State : | Karnataka | District : | Belgaum | Tehsil : | Chikodi | Village : | Nanadi & Kerur |
| 80 | No issues raised by locals & farmers. Project is welcomed by residents | Others | Additional Deputy Commissioner & Additional District Magistrate | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Bangalore | (iii)Letter No. | EP/12.1/160/ KAR 408 | (iv)Status of Compliance | Partially Complied | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Jan 22 2020 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | RS/ENA/Ethanol | 30 | 80 | 110 | Kilo Litre per Day(KLD) | | Road | | (2.) | CO2 | 23 | 60 | 83 | Others | MT/D | Road,Others | Cylinders | (3.) | Pressmud | 12000 | 0 | 12000 | Others | MT/Month | Road | Grid | (4.) | Bagasse | 90000 | 0 | 90000 | Others | MT/Month | Road,Conveyor Belt | Grid | (5.) | Sugar | 36000 | 0 | 36000 | Others | MT/Month | Road | Cylinders | (6.) | Electricity | 50 | 0 | 50 | Mega Watt(MW) | | Others | Grid | (7.) | Molasses | 12000 | 0 | 12000 | Others | MT/Month | Road | Grid | (8.) | Compost | 55 | 0 | 55 | Others | MT/D | Road | Grid | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Molasses Distillery | 30 | 80 | 110 | Expansion of distillery from 30 to 110 KLPD | (2.) | Sugar Factory | 10000 TCD | 0 | 10000 TCD | Existing 10000TCD sugar factory | (3.) | Cogeneration | 50 | 0 | 50 | Existing 50 MW cogen plant | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 09 Aug 2018 | (iv)Valid Upto | 30 Jun 2021 | (v)File No. | 13218 | (vi)Application No. | AW 307227 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 102.2 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 45 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.8 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 1.16 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 8880 | (b)Existing quantity of raw material/fuel | 3330 | (c)Total quantity of raw material/fuel | 12210 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Sugar cane | 300000 | Others | MT/Month | Nearby farms | Road | | 50 | Open Market | | Copy of Linkage | (2.) | Urea | 135 | Others | MT/Month | outside purchase | Road | | 25 | Open Market | | Copy of Linkage | (3.) | Sulfur | 180 | Others | MT/Month | outside purchase | Road | | 30 | Open Market | | Copy of Linkage | (4.) | Lime | 540 | Others | MT/Month | outside purchase | Road | | 15 | Open Market | | Copy of Linkage | (5.) | Bagasse | 90000 | Others | MT/Month | Own sugar factory | Conveyor Belt | | 0.2 | Captive | | Copy of Linkage | (6.) | B/C heavy Molasses | 12210 | Others | MT/Month | Own sugar factory/ outside purchase | Road | | 30 | Open Market | | Copy of Linkage | (7.) | Yeast | 12 | Others | MT/Month | outside purchase | Road | | 5 | Open Market | | Copy of Linkage | (8.) | De-Foaming Oil | 390 | Others | MT/Month | outside purchase | Road | | 25 | Open Market | | Copy of Linkage | (9.) | Oil & Grease | 42 | Others | MT/Month | outside purchase | Road | | 30 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2019 To 31 May 2020 | (b)Season | Pre-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | SO2 | | Micro Gram per Meter Cube | 30.3 | 11.6 | 19.2 | 80 | (2.) | PM10 | | Micro Gram per Meter Cube | 69.07 | 50.6 | 58.9 | 100 | (3.) | NOx | | Micro Gram per Meter Cube | 34.6 | 20.4 | 24.8 | 80 | (4.) | PM2.5 | | Micro Gram per Meter Cube | 30.2 | 11.7 | 20.75 | 60 | (5.) | Others | CO | Mili Gram per Meter Cube | 0.9 | 0.01 | 0.8 | 2 (8 Hr) | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.8 | 7 | 6.5 | 8.5 | (2.) | Chlorides | | | mg/l | | 163.42 | 52.86 | 250 | 250 | (3.) | Heavy Metals | | Zinc | mg/l | | 3.06 | 0.24 | 5 | 5 | (4.) | TDS | | | mg/l | | 556.55 | 248.22 | 500 | 500 | (5.) | Fluoride | | | mg/l | | 0.51 | 0.05 | 1 | 1 | (6.) | TSS | | | mg/l | | 3.71 | 1.72 | 100 | 100 | (7.) | Total Hardness | | | mg/l | | 195.96 | 97 | 200 | 200 | |
14.3. No. of Surface Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | Others | Colour | Others | Hazen | 6 | 2 | A | (2.) | BOD | | mg/l | | 45.88 | 11.46 | E | (3.) | COD | | mg/l | | 149.23 | 26.39 | E | (4.) | DO | | mg/l | | 3.5 | 0.5 | E | (5.) | Others | Fecal coliform | Others | No./100 ml | 662 | 144 | C | (6.) | pH | | NA | | 7.85 | 7.42 | A | (7.) | Others | Total coliform | Others | No./100 ml | 1680 | 320 | C | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 51.7 | 41.5 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 67.5 | 50.5 | 75 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | K(Potassium) | Milliequivalents per 100 Gram | | 0.91 | 0.48 | (2.) | pH | | | 7.81 | 7.35 | (3.) | Electric Conductivity | Others | Micro simens/cm | 2671.8 | 1613.72 | (4.) | N(Nitrogen) | Kilogram per hectare | | 782.36 | 487.12 | (5.) | P(Phosphorus) | Kilogram per hectare | | 135.68 | 71.49 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.44 To 17.25 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.31 To 17.33 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 1672 | 8 | Copy of Permission Letter | Pipeline | | Jack Well | | Belgaum/ C2/15-16/1866 | 28 Apr 2015 | 5320 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Other Effluent- Distillery | 738 | 1000 | In proposed condensate polishing unit | Reuse within the Plant & Recycling | | 738 | | (2.) | Raw Spentwash (Distillery) | 880 | 1000 | Composting for existing spentwash. For remaining -Concentrated in MEE & Incinerated in Boiler. | Others | spentwash ash given to brick/cement manufacturing | 880 | 0 | (3.) | Industrial effluent- sugar & cogen | 740 | 1000 | In existing ETP having primary, secondary & tertiary treatment units. | Green Belt Renewal Plant | | 740 | | (4.) | Domestic Effluent- sugar, cogen & distillery | 38.5 | 40 | In proposed sewage treatment plant | Others | for flushing & gardening | 38.5 | 0 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 2396.5 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 2396.5 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | CPU Sludge (Distillery) | Industrial Waste | | 264 | Tons | 5 | Road | | Others | use as manure | (2.) | ETP Sludge | Industrial Waste | | 105 | Tons | 5 | Road | | Others | use as manure | (3.) | Boiler Ash(coal+spentwash-Distillery) | Bottom Ash | | 15180 | Tons | 5 | Road | | Others | Cement industry/brick manufacturers | (4.) | Boiler Ash(Bagasse- sugar & cogen) | Bottom Ash | | 6525 | Tons | 5 | Road | | Others | Cement industry/brick manufacturers | (5.) | Yeast Sludge (Distillery) | Industrial Waste | | 6270 | Tons | 5 | Road | | Others | use as manure | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 20.35 | 8.8 | 0.04 | 20.40 | 60 | (2.) | NOx | | Microgram per Meter Cube | 24.8 | 8.2 | 0.4 | 25.21 | 80 | (3.) | PM10 | | Microgram per Meter Cube | 59.7 | 8.62 | 0.1 | 59.81 | 100 | (4.) | SO2 | | Microgram per Meter Cube | 18.9 | 8.8 | 0.2 | 19.10 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Proposed 32 TPH incineration boiler | Coal 75 MTPD+spentwash 175 MTPD | 60 | 1.3 | SO2 | | 170 kg/hr | (2.) | Existing 15 TPH boiler (Distillery) | Bagasse- 200 MTPD | 52 | 1.2 | PM10 | | 65 mg/Nm3 | (3.) | Existing 40 TPH boiler | Bagasse-422 MTPD | 52 | 3.4 | PM10 | | 38.3 mg/Nm3 | (4.) | Cogen boiler 125 TPH | Bagasse-1320 MTPD | 70 | 3.9 | PM10 | | 45.2 mg/Nm3 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 13680 | (b)Source | own 50 MW cogen plant | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 2 DG sets- 320 KVA capacity each (1 existing+ 1 pr | (e)Stack Height (in m) | 6 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 70.56 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 70.56 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 15527 | (b)Waste/Barren Land (ha.) | 3828 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 320 | (e)Settlements (ha.) | 1606 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Fallow & scrub land | 10134 | Total (ha.) | 31415.0000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Built Up Area | | 18.18 | Existing + proposed built up area | (2.) | Green belt | | 23.33 | Existing+ Proposed GB | (3.) | Others | Open Space | 29.05 | Total open area | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | No | 0 | There is no presence of WLS in 10Km radius of Project | (2.) | Critically Polluted Area | No | 0 | There is no presence of CPA's in 10 Km radius of Project | (3.) | ESZs | No | 0 | There is no presence of ESZ in 10Km radius of Project | (4.) | Wildlife Corridors | No | 0 | There is no presence of wildlife Corridors in 10 Km radius of Project | (5.) | ESAs | No | 0 | There is no presence of ESAs in 10Km radius of Project | (6.) | NPA | No | 0 | There is no presence of NPA's in 10Km radius of Project | (7.) | Corridors | No | 0 | There is no presence of Corridors in 10 Km radius of Project | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | No | 0 | There is no presence of forest land in 10 Km radius of Project | (2.) | Defence Installations | | No | 0 | There is no presence of defence installations in 10 Km radius of Project | (3.) | Archaeological Sites | | No | 0 | There is no presence of notified archaeological sites in 10 Km radius of Project | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 70.56 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Industry already owned the land | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | | (b)No. of Households | | (c)No. of PDFs (Project Displaced Families) | | (d)No. of PAFs (Project Affected Families) | | (e)Funds Allocated for R&R(in INR) (in Lacs) | | (f)Status of R&R | NA | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Brahminy Kite, Black Kite, Balck shouldered kite, Indian Monitor Lizard | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | Rs. 57 Lac | (iii)Period of Implementation | Period of 2021-2025 | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | River Dudhganga-6.5 Km & Krishna -8 Km | (ii)Direction of Water Bodies in Buffer Area | North West | (iii)Distance of Water Bodies in Buffer Area | 6.5 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 5 | (b)Permanent Employment-During Operation | 6 | (c)Temporary Employment- During Construction | 5 | (d)Temporary Employment- During Operation | 4 | (e)No. of working days | 330 | (f)Total Manpower | 20 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 18.39 | 4.93 | 23.32 | (2.) | Percentage of Total Project Area | 26 | 7 | 33 | (3.) | No. of Plants | 15000 | 20000 | 35000 | (4.) | Funds Allocated | 60 | 100 | 160 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Industry shall adopt the rain water harvesting systems that will improve the ground water table in surrounding area.
Augmentation of existing green belt and plantation of additional trees in the industrial area and its surrounding shall help in improving the aesthetic beauty of the surrounding environment giving a pleasant look and improvising the air quality. Also green belt will help in arresting dust emissions as well as noise. | (2.) | Social | About 625 skilled and 164 unskilled workers are working under existing sugar, cogeneration & distillery unit. Moreover, 20 skilled and unskilled workers will be appointed from local area as well as from outside after commissioning of the project. Preference will be is given to persons from local area thereby creating better employment opportunities | (3.) | Financial | • Due to proposed expansion project, the frequency of the local transportation will increase in this area. This will help shorten the time reaching destination and utilize it for some fruitful productive work.
• Due to distillery expansion project, the industry will meet the national interest of economical growth through sustainable development, as alcohol has been a great source of revenue through excise duty levied by the Government. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Industrial Projects - 3 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1821/RA 0135 | (ii)Name of the EIA Consultant | Equinox Environments India Pvt. Ltd. | (iii)Address | F-11, Namdev Nest, 1160 B, E, Sykes Extension, Opposite Kamla College, Kolhapur 416001 | (iv)Mobile No. | 9657865122 | (v)Landline No. | 0231253123 | (vi)Email Id | projects@equinoxenvi.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 3 | (ix)Validity of Accreditation | 21 Oct 2021 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | NA | 02 Feb 2021 | 2. | NA | Please read the information as sought by the Ministry on 01.02.2021 and submit the copy of transfer of EC which is being handled at Industry 2 Sector. Do not uplaod this information as it is not asked by Industry 3 Sector. You first take the transfer of EC from Ind 2 and upload here in this sector so that EC can be issued. | 02 Feb 2021 | 3. | ADS Reply Letter | NA | 02 Feb 2021 | 4. | ADS Reply Letter | NA | 02 Feb 2021 | 5. | NA | The competent authority in the Ministry has approved the Environmental Clearance proposal of M/s Chidanand Basaprabhu Kore Sahakari Sakkare Karkhane Niyamit, for Expansion of molasses based distillery from 30 KLPD to 110 KLPD, located at S. No. 184, 185, 186, 455, 456, 621, 626, 627, 631,Village NanadiKerur, Chikodi, Belgaum, Karnataka. The authority also directed that EC issued only after transfer of EC is executed.
2. In view of the above the undersigned is directed to request the PP to submit the copy of transfer of EC letter for further necessary action. | 01 Feb 2021 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Raveendra R Desai | Designation | MD | Name of Company (Applicant Name should not be given here) | CHIDANAND BASAPRABHU KORE SAHAKARI SAKKARE KARKHANE NIYAMIT, CHIKKODI | Address | S. No. 184, 185, 186, 455, 456, 621, 626, 627, 631 |
|