Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Holistic Development of Surat Airport including extension of Terminal Building, Apron and construction of Parallel Taxi Track, at Surat Airport, Surat (Gujarat)
(b)Name of the Company / Organisation AIRPORT AUTHORITY OF INDIA,SURAT
(c)Registered Address On Magdalla-Dumas Road, Surat,,Surat,Gujarat-395007
(d)Legal Status of the Company Central Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant BARUN KUMAR BHATTACHARYA
(b)Designation (Owner/ Partner/ CEO) AGM
(c)Address CORPORATE HEAD QUARTERS, ENGG. WING, B-BLOCK, 3RD FLOOR, RAJIV GANDHI BHAWAN, SAFDARJUNG AIRPORT, NEW DELHI,,Connaught Place,New Delhi,Delhi-11003
(d)Pin code 11003
(e)E-mail suratterminal@gmail.com
(f)STD Code. 261(f)Telephone No. 24632950
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(a) Air ports
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/MIS/178386/2006
(d)Master Proposal Number(Single Window) SW/178383/2020
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Various Khasra
(b)Pincode 394550
(c)Bounded Latitudes (North)
From
Degree 2155658
Minutes
Second
From
Degree 2175439
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72434393
Minutes
Second
From
Degree 72454371
Minutes
Second
(e)Survey of India Topo Sheet No. 46C/12, 46C/16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 9
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 2.7
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number F.No.10-16/2019-1A-III
(c)Date of Issue of TOR 10 Jan 2007
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 10 Oct 2020
(c)Date of Issue of EC 05 Jan 2021
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :05 Dec 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :07 Jan 2020
Distance of Public Hearing Venue from the Proposed Project :0
Airports Authority of lndia, Surat Airport, Main Entry Gate, Magdalla -Dumas Road, Surat, Dist. Surat (Gujarat)
State :Gujarat
District :Surat
Tehsil :Surat City
Village :Magdalla-Dumas Road
102Employment, Environment management, CERDistrict Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. F.No. 8-10/2007(Env)/635
(iv)Status of Compliance Partially Complied
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jun 18 2020 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Extension of terminal Building84741777626250Otherssquare metreOthersNot applicable
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Apron5 bays18 bays23 bays
(2.)Taxiway2 Nos. 23 x 200 MParallel taxi track : 30x2906 M2 Nos 23 x 200 M; PTT – 30 x 2906 M
(3.)Extension of terminal Building8474 sqm17776 sqm26250 sqm
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 26 Nov 2019
(iv)Valid Upto 30 Sep 2024
(v)File No. AWH-105381
(vi)Application No. 168562
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 353.25
(b) Funds Allocated for Environment Management (Capital) (in Crores) 2.05
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.3
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.009
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Not Applicable since there is no production/ manufacturing process involved0OthersNA0OthersNA0 OthersNACopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 02 Mar 2019 To 30 May 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube35.618.53580
(2.)OthersCOMicro Gram per Meter Cube15308301502.44000
(3.)PM2.5Micro Gram per Meter Cube58.435.958.460
(4.)SO2Micro Gram per Meter Cube17.58.717.580
(5.)PM10Micro Gram per Meter Cube128.1076.8120.9100
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l0000
(2.)OthersTotal alkanlinitymg/l570310200600
(3.)Total Hardnessmg/l374219200600
(4.)Heavy MetalsLeadmg/l000.010.01
(5.)Heavy MetalsCadmiummg/l0000
(6.)Chloridesmg/l5943782501000
(7.)Fluoridemg/l0.850.6811.5
(8.)pHNA7.887.197.58.5
(9.)TDSmg/l0000
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l3728E
(2.)BODmg/l118.9E
(3.)DOmg/l6.15.8B
(4.)pHmg/l7.947.85A
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))68.738.465
(2.)Leq(Night)A-weighted decibels(dB(A))56.838.455
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Kilogram per hectare00
(2.)pH8.237.68
(3.)K(Potassium)Kilogram per hectare00
(4.)N(Nitrogen)Kilogram per hectare00
(5.)Electric ConductivityMillisiemens per Centimetre345196
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMunicipal supply30110Copy of Permission LetterPipelineOthersPipelineSWZ/OUT/H/30 Mar 2003301
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic488500MBBR based STPOthersrecycle for greenbelt, flushing & HVAC cooling4880
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 488
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 488
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Domestic WasteMunicipal Solid Waste516Tons10RoadOthersMunicipal Corporation
(2.)Construction wasteConstruction & Demolition Waste1503Tons10RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube33.30.127.8461.1580
(2.)PM10Microgram per Meter Cube121.60.10.06121.7100
(3.)SO2Microgram per Meter Cube17.50.13.5421.180
(4.)Others(Specify)COMicrogram per Meter Cube13100.129.92134080
(5.)PM2.5Microgram per Meter Cube58.40.10.158.660
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetHSD302.5PM100.03 g/s
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 4494
(b)Source Dakshin Gujarat Vij Company Limited
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 500x2, 1000x1, 2500x2
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 317.42
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 317.42
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 317.42
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NA 0
    Total (ha.) 317.4200
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersAirport317.42Land already handed over to AAI by Govt of Gujarat
Total (ha.) 317.42
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNone0none in 10 km radius
(2.)ESZsNone0none in 10 km radius
(3.)CorridorsNone0none in 10 km radius
(4.)Wildlife CorridorsNone0none in 10 km radius
(5.)WLSNone0none in 10 km radius
(6.)Critically Polluted AreaNone0none in 10 km radius
(7.)NPANone0none in 10 km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNone0none in 10 km radius
(2.)Defence InstallationsNone0none in 10 km radius
(3.)Archaeological SitesNone0none in 10 km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Complete
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Indian Peafowl
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 250000
(iii)Period of Implementation 3 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Tapi river
(ii)Direction of Water Bodies in Buffer Area North West
(iii)Distance of Water Bodies in Buffer Area 2.7
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 250
(c)Temporary Employment- During Construction 200
(d)Temporary Employment- During Operation 0
(e)No. of working days 365
(f)Total Manpower 450
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Percentage of Total Project Area3174237300761047499
(2.)Percentage of Total Project Area102333
(3.)No. of Plants10001000011000
(4.)Funds Allocated25000015000001750000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialThe project will boost economic growth benefiting the whole region through the generation of both direct and indirect economic value. The construction and operation of airport will generate direct employment opportunity, indirectly contributed jobs through supply chain, enhance induced impact through tourism. Thus the project will prove beneficial to the area. CER activities will also help improve socio-economic conditions in the nearby areas.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 17.8
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 1
(d)Total plot area (sqm) 106770
(e)Total built up area (sqm) 26250
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 56
(b)Capacity 746749
(c)No. of Recharge Pits 0
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 700
5.
Energy Saving Measures:
(a)Source/Mode Solar PV Plant
(b)Percentage 5
(c)Quantity 250
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area No adverse impact envisaged on water bodies and dr
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/IA0026/Rev 01
(ii)Name of the EIA Consultant Gaurang Environmental Solutions Pvt. Ltd.
(iii)Address #102, SNG, Shri Ratna Apartment, near Tambi Petrol Pump, Bani Park,Peetal factory, Jhotwara road, Jaipur-302016
(iv)Mobile No. 9782074776
(v)Landline No. 141242911
(vi)Email Id gaurangenviro@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 13 Oct 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantBARUN KUMAR BHATTACHARYA
DesignationAGM
Name of Company (Applicant Name should not be given here)AIRPORT AUTHORITY OF INDIA,SURAT
AddressOn Magdalla-Dumas Road, Surat