Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Chandra Life Sciences Pvt Ltd
(b)Name of the Company / Organisation MS CHANDRA LIFE SCIENCES PVTLTD
(c)Registered Address Plot No. 200, KIADB Industrial area, Kolhar Village, Nizampur Hobli, Bidar Taluk & District, Karnataka,,Bidar,Karnataka-585402
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sathyanarayana Bandi
(b)Designation (Owner/ Partner/ CEO) MD
(c)Address Plot No. 200, KIADB Industrial area, Kolhar Village, Nizampur Hobli, Bidar Taluk and District, Karnataka,,Bidar,Bidar,Karnataka-585402
(d)Pin code 585402
(e)E-mail chandrasciences4ec1@gmail.com
(f)STD Code. 80(f)Telephone No. 26576577
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category B2
   Reason for Applying at Ministry SEIAA
(c)Proposal Number IA/KA/IND2/176713/2020
(d)Master Proposal Number(Single Window) SW/176703/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 3
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 200
(b)Pincode 585402
(c)Bounded Latitudes (North)
From
Degree 17.908724
Minutes
Second
From
Degree 17.909895
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 77.455052
Minutes
Second
From
Degree 77.456492
Minutes
Second
(e)Survey of India Topo Sheet No. 56G/5,6,9,10
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 502
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number 123
(b)Date of Apply of TOR 17 Aug 2020
(c)Date of Issue of TOR / Standard ToR 09 Sep 2020
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Not applicable, B2 category
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)bulk drugs and intermediates manufacturing unitGF+1UF
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Area - 24,300 Sqm169.5OthersTPMRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 25.95
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.58
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.165
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.29
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 7500
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 7500
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Coal as a Fuel for Boiler7500Tons per Annumlocal vendorRoad30 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 18 Sep 2020 To 21 Sep 2020
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube57.6457.6457.64100
(2.)SO2Micro Gram per Meter Cube9.459.459.4580
(3.)PM2.5Micro Gram per Meter Cube19.6119.6119.6160
(4.)NOxMicro Gram per Meter Cube37.5837.5837.5880
    14.2.     No. of Ground Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l11611620600
(2.)Fluoridemg/l0.10.111.5
(3.)Chloridesmg/l40.240.22501000
(4.)TSSmg/l0000
(5.)pHNA7.217.216.58.5
(6.)TDSmg/l3943945002000
    14.3.     No. of Surface Water monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l00A
(2.)BODmg/l00A
(3.)pHNA00A
(4.)DOmg/l00A
    14.4.     No. of Ambient Noise monitoring locations : 1
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))645875
(2.)Leq(Night)A-weighted decibels(dB(A))605470
    14.5.     No. of Soil Sample Monitored locations : 1
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Milligram per Kilogram0.020.02
(2.)P(Phosphorus)Milligram per Kilogram42.442.4
(3.)K(Potassium)Milligram per Kilogram64.564.5
(4.)pH7.37.3
(5.)Electric ConductivityOthersmicrosiemens per centimeter0.180.18
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 0
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 0
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersKIADB81.90Copy of Permission LettermodeOtherstankerOthersmode016 Jul 201481.9
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)industrial effluent and domestic sewage62.5110MEE of 55 KLD and Biological treatment plant of 55 KLD capacityReuse within the Plant & Recycling62.5
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 62.5
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 62.5
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)process residue and wasteIndustrial Waste633Tons30RoadCo-Processing
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube5700.6457.65100
(2.)SO2Microgram per Meter Cube900.459.4680
(3.)NOxMicrogram per Meter Cube3700.5837.5980
(4.)PM2.5Microgram per Meter Cube1900.6119.6260
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Boilercoal/Briquettes300.3NOx0.76 g/s
(2.)DG setHSD70.3SO20.474ppm
(3.)DG setHSD70.3PM100.06 mg/Nm3
(4.)Boilercoal/Briquettes300.3SO20.37 g/s
(5.)Boilercoal/Briquettes300.3PM100.081 g/s
(6.)DG setHSD70.3NOx2.216 ppm
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 240
(b)Source GESCOM
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 380 kva x 1
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 2.43
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 2.43
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 2.43
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : none 0
    Total (ha.) 2.4300
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant1.034
(2.)Green belt0.9234
(3.)Othersdriveway and paved area0.4726
Total (ha.) 2.43
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANone0None
(2.)ESAsn0None
(3.)CorridorsNone0None
(4.)Wildlife CorridorsNone0None
(5.)Critically Polluted AreaNone0None
(6.)WLSNone0None
(7.)ESZsNone0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsBidar air force0.5East direction
(2.)Archaeological SitesNone0None
(3.)ForestNone0None
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 180
(c)Temporary Employment- During Construction 20
(d)Temporary Employment- During Operation 0
(e)No. of working days 7
(f)Total Manpower 200
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.92
(b)Percentage of Total Project Area 37.86
(c)No. of Plants to be Planted 0
(d)Funds Allocated for Plantation 0.15
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment opportunity
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Industrial Projects - 3
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/IA0056
(ii)Name of the EIA Consultant AM ENVIRO ENGINEERS
(iii)Address No. 14/1, 2nd Floor, HARIKRUPA, Pattalamma Temple Street, Basavanagudi, Bengaluru - 560 004
(iv)Mobile No. 9916675089
(v)Landline No. 26576577
(vi)Email Id amee.operations@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 3
(ix)Validity of Accreditation 23 Dec 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA(i) Based on the information submitted by PP it is Category B2 project, PP submitted this application at Central Level due to general condition. The Notification dated 27.03.2020 is only for API not for intermediates. If the proposal is for API & Intermediate, please apply for TOR. Please check your proposal once again. (ii) This is an expansion proposal accordingly, the PP shall submit the certified compliance report to the conditions of CTO from the SPCB. (iii) All old CTOs to be uploaded to verify the violation, if any done by PP. (iv) Details of earlier production capacity needs to be authenticated and uploaded to check the violation, if any. (v) It is mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be submitted. It is also mentioned that after acceptance the Proposal, proposal can not be revise. Therefore, PP/Consultant is requested to kindly do needful accordingly. 29 Oct 2020
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSathyanarayana Bandi
DesignationMD
Name of Company (Applicant Name should not be given here)MS CHANDRA LIFE SCIENCES PVTLTD
AddressPlot No. 200, KIADB Industrial area, Kolhar Village, Nizampur Hobli, Bidar Taluk & District, Karnataka