1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | OM DIVINE BUILDCON LLP | (b)Name of the Company / Organisation | OM DIVINE BUILDCON LLP | (c)Registered Address | office no 19, first floor, Hill spring Ghodbunder road Thane west,,Thane,Maharashtra-400615 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Vishal Gohil | (b)Designation (Owner/ Partner/ CEO) | Partner | (c)Address | office no 19, first floor, Hill spring, Ghodbunder road, Thane West,,,Thane,Maharashtra-400615 | (d)Pin code | 400615 | (e)E-mail | omdivinebuildconllp@gmail.com | (f)STD Code. | 0(f)Telephone No. | | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 8(a) Building and Construction projects
| Minor Activity | | (b)Category | B2 | Reason for Applying at Ministry | SEIAA | (c)Proposal Number | IA/MH/NCP/176585/2020 | (d)Master Proposal Number(Single Window) | SW/176582/2020 | (e)EAC concerned (for category A Projects only) | INFRA-1 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Plot bearing S. No. 146/1/A/1, 146/5/A/3, 147/1/A/ | (b)Pincode | 400606 | (c)Bounded Latitudes (North) | | From | | Degree | 19.2082 | Minutes | | Second | | From | | Degree | 19.2086 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 72.9590 | Minutes | | Second | | From | | Degree | 72.9596 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | E43A16 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 28 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 4 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Maharashtra | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR): | (a)Whether TOR is mandatory for submitting application | No | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | Not applicable for building construction project | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Bldg. (Residential + Commercial) | G + 3P +1stto 26th + 27th(pt) floor | Height: 97.10 m | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | FSI area (m2) | 14669.65 | Others | m2 | Others | m2 | (2.) | Total BUA (m2) | 33522.11 | Others | m2 | Others | m2 | (3.) | Plot area (m2) | 8347.04 | Others | m2 | Others | Area | (4.) | Non FSI (m2) | 18822.46 | Others | m2 | Others | area | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 30 Sep 2020 | (iv)Valid Upto | 30 Sep 2025 | (v)File No. | NA ( | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 80 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 1.22 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 1.6 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.24 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 0 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 0 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | NA (Bldg. construction project) | 0 | Others | NA | NA | Others | NA | 0 | Others | Not Applicable | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Feb 2020 To 29 Feb 2020 | (b)Season | Pre-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 1 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | NOx | | Micro Gram per Meter Cube | 31.5 | 22.6 | 31.5 | 80 | (2.) | PM10 | | Micro Gram per Meter Cube | 65.9 | 56.9 | 65.7 | 100 | (3.) | PM2.5 | | Micro Gram per Meter Cube | 34.9 | 25.5 | 34.9 | 60 | (4.) | SO2 | | Micro Gram per Meter Cube | 26.7 | 17.1 | 26.5 | 80 | (5.) | Others | CO | Mili Gram per Meter Cube | 1.3 | 0.5 | 1.3 | 2 | |
14.2. No. of Ground Water monitoring locations : 1 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Chlorides | | | mg/l | | 114 | 114 | 250 | 1000 | (2.) | pH | | | NA | | 7.3 | 7.3 | 6.5 | 8.5 | (3.) | Total Hardness | | | mg/l | | 187 | 187 | 200 | 600 | (4.) | TSS | | | mg/l | | 12.5 | 12.5 | 0 | 0 | (5.) | TDS | | | mg/l | | 652 | 652 | 500 | 2000 | (6.) | Fluoride | | | mg/l | | 0.4 | 0.4 | 1 | 1.5 | |
14.3. No. of Surface Water monitoring locations : 1 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.2 | 7.2 | B | (2.) | DO | | mg/l | | 4.3 | 4.3 | B | (3.) | BOD | | mg/l | | 27 | 27 | B | (4.) | COD | | mg/l | | 77 | 77 | B | |
14.4. No. of Ambient Noise monitoring locations : 1 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 52.5 | 52.2 | 55 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 43.6 | 43.6 | 45 | |
14.5. No. of Soil Sample Monitored locations : 1 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | P(Phosphorus) | Kilogram per hectare | | 34.5 | 34.5 | (2.) | pH | | | 7.5 | 7.5 | (3.) | N(Nitrogen) | Kilogram per hectare | | 19.5 | 19.5 | (4.) | K(Potassium) | Kilogram per hectare | | 24.2 | 24.2 | (5.) | Electric Conductivity | Millisiemens per Centimetre | | 0.8 | 0.8 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2 To 3 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 1.5 To 2.5 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Thane Municipal Corporation | 135 | 0.5 | Copy of Permission Letter | Pipeline | | Others | Municipal Water Supply (pipe line) | 0 | 01 Sep 2020 | 135 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Residential Bldg. | 125 | 150 | MBBR Tech. STP | Reuse within the Plant & Recycling,Green Belt Renewal Plant,Others | Municipal Sewer | 56 | 69 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 125 | (b)Total Discharged Water (Kilolitre per Day) | 69 | (c)Total Reused Water (Kilolitre per Day) | 56 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Bio-degradable waste | Municipal Solid Waste | | 0.3 | Tons | 0 | Others | Onsite treatment | Others | OWC will be used | (2.) | Non biodegradable waste | Municipal Solid Waste | | 0.2 | Tons | 0 | Road | | Others | Handed over to authorized recyclers | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 65.9 | 0.2 | 0.2 | 66.3 | 100 | (2.) | NOx | | Microgram per Meter Cube | 31.5 | 0.2 | 0.1 | 31.7 | 80 | (3.) | PM2.5 | | Microgram per Meter Cube | 34.9 | 0.2 | 0.1 | 35.1 | 60 | (4.) | SO2 | | Microgram per Meter Cube | 26.7 | 0.2 | 0.3 | 27.1 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DG stack | HSD | 6 | 0.1 | SO2 | | 0.5 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 1375 | (b)Source | MSEDCL | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 1 x 750 | (e)Stack Height (in m) | 6 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0.8347 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 0.8347 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Building construction project | 0 | Total (ha.) | 0.0000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Others | Building Construction project | 0.8347 | BUA: 33,522.11 m2 | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | ESAs | NA | 0 | NA | (2.) | Corridors | NA | 0 | NA | (3.) | Wildlife Corridors | NA | 0 | NA | (4.) | Critically Polluted Area | NA | 0 | NA | (5.) | WLS | Thane Creek Flamingo WS | 3 | Project site is located within the deemed ESZ of Thane creek flamingo sanctuary (TCFS) at a distance of 3 km from the protected area of TCFS. It is also out of the proposed draft ESZ of TCFS vide not | (6.) | NPA | NA | 0 | NA | (7.) | ESZs | Sanjay Gandhi National park ESZ | 1.2 | our site is ouside of ESZ of SGNP (100 m) | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | SGNP | 1.2 | our site is ouside of ESZ of SGNP (100 m) | (2.) | Archaeological Sites | | NA | 0 | NA | (3.) | Defence Installations | | NA | 0 | NA | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0.83 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Land is in possession of PP | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | | (b)No. of Households | | (c)No. of PDFs (Project Displaced Families) | | (d)No. of PAFs (Project Affected Families) | | (e)Funds Allocated for R&R(in INR) (in Lacs) | | (f)Status of R&R | NA | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Upvan lake | (ii)Direction of Water Bodies in Buffer Area | North East | (iii)Distance of Water Bodies in Buffer Area | 1 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 10 | (b)Permanent Employment-During Operation | 25 | (c)Temporary Employment- During Construction | 10 | (d)Temporary Employment- During Operation | 5 | (e)No. of working days | 365 | (f)Total Manpower | 50 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0.15 | (b)Percentage of Total Project Area | 17.97 | (c)No. of Plants to be Planted | 110 | (d)Funds Allocated for Plantation | 1300000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | We will generate CER funds that will be utilized in surrounding area. | (2.) | Environmental | The project is newly raised therefore; At the time of development plantation will be carried out. The various Environmental facilities and infrastructure planned in the project. This includes solid waste management facility, sewage treatment plant, and water harvesting facility, Storm water drainage, etc. | (3.) | Financial | The proposed project would have beneficial impacts through provision of direct and indirect employment opportunities. At the time of construction and operational phases, there would be requirement for large number of skilled, semi-skilled and unskilled work force for current activity. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For INFRA-1 |
|
1. | Details of Building Construction: | (a)Maximum Height of the Building (Meters) | 97.10 | (b)Total No. of Flats to be Build | 154 | (c)No. of Buildings | 1 | (d)Total plot area (sqm) | 8347.04 | (e)Total built up area (sqm) | 33522.11 | |
|
2. | Foreshore Facilities and/or Marine Disposal: | (a)Whether Project Involves Foreshore Activities and/or marine Disposal? | No | |
|
3. | Rain Water Harvesting: | (a)No. of Storage | 1 | (b)Capacity | 30 | (c)No. of Recharge Pits | 0 | (d)Capacity | 0 | |
|
4. | Parking: | (a)Details of 4 Wheeler/ 2 Wheeler Parking | 4W: 358 & 2W: 492 | |
|
5. | Energy Saving Measures: | (a)Source/Mode | LED lamps, Solar Hot water system, Energy efficien | (b)Percentage | 21.4 | (c)Quantity | 322 | |
|
|
7. Type of Industries to be established with Industrial Estate as per their category A/B |
---|
S. No. | Type of Industry | No. of Units | Category A/B |
---|
NIL | |
8. | Length of the alignment | N/A | |
|
9. | Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass | Details Not Applicable | |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | QCI/NABET/EIA/ACO/17/00427 | (ii)Name of the EIA Consultant | Mahabal Enviro Engineers Pvt. Ltd. | (iii)Address | Plot No. F-7, Road No. 21, Wagle Estate, Thane 400604, Maharashtra | (iv)Mobile No. | 9323058368 | (v)Landline No. | 21716389 | (vi)Email Id | dap_24@hotmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | INFRA-1 | (ix)Validity of Accreditation | 09 Oct 2022 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | We are in receipt of ADS regarding copy of acknowledgement for the application seeking NBWL recommendations as our site is located within the 10 km of Thane Creek Flamingo Sanctuary (TCFS) at a distance of 4.7 Km from the protected area of TCFS. This is required as per the procedure notified by the Ministry vide OM No. 22-3/2018 dated 8th August, 2019.We would like to inform you that, we have submitted our proposal for the NBWL enclosed herewith. We request you to kindly consider the same and grant us the Environmental Clearance. | 06 Jan 2021 | 2. | NA | Ref. Your aforementioned proposal.
While proposing the case, as per recommendation of EAC-Infra-2, it is observed that Project site is located within the 10 of Thane Creek Flamingo Sanctuary (TCFS) and is at a distance of 4.0 km from the protected area of TCFS. It is also out of the proposed draft ESZ of TCFS vide notification published by the MoEF&CC dt. 06.11.2019.
As on date, you have not submitted copy of acknowledgement to the effect that application seeking NBWL recommendations has been submitted. This is required as per the procedure notified by the Ministry vide OM No. 22-3/2018 dated 8th August, 2019. As per the aforesaid OM, proposals involving development activity / project located within 10 kilometers of National Park/Wildlife Sanctuary, wherein final ESZ notification is not notified, prior clearance Standing Committee of the National Board for Wildlife is mandatory. In such cases, the project proponent shall submit the application simultaneously for grant of TOR/ EC as well as wildlife clearance
Hence, you are requested to submit the acknowledgment to the effect that application seeking recommendations of National Board of Wild Life has been submitted. | 05 Jan 2021 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Vishal Gohil | Designation | Partner | Name of Company (Applicant Name should not be given here) | OM DIVINE BUILDCON LLP | Address | office no 19, first floor, Hill spring Ghodbunder road Thane west |
|